Home / Browse projects / Mumbai Suburban, Maharashtra / Rudra Paradise

Registered No litigation declared Residential / Group Housing project

Rudra Paradise

By R-Stone Design and Build Private Limited

RG-MH-20365 · RERA P51800008159 · Last updated on MahaRERA portal: 29 Apr 2026

Source: official MahaRERA filing

Red flags

  • Possession 3 months past the filed date
  • Completion date moved by 66 months
  • 3 extensions taken
  • Rs 31.00 crore secured on the land, in favour of AU Small Finance Bank Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 94%
38 of 66Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 151 documents Report an error

Rudra Paradise is a Residential / Group Housing project by R-Stone Design and Build Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008159 on 18 Aug 2017. Possession was promised by 21 Jul 2026 and is now 3 months past that date. The completion date has moved by 66 months from the original filing. 28 of the 66 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameRudra Paradise
  • TypeResidential / Group Housing
  • Location
    • Gurunarayan Marg
    • Santacruz East
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008159
  • ReraGenie IDRG-MH-20365

Builder

  • NameR-Stone Design and Build Private Limited
  • Entity typeCompany
  • DirectorsRudra Janakbhai Barot, Brijesh Kantibhai Goswami

Key dates

3 months past promisethis monthRegisteredAug 2017First promiseJan 2021Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion21 Jul 2026
  • Revised completionRevised to 21 Jul 2026 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed151 files

Current status

42%28 of 66 units booked
73.5%Work done, per cost certificate

Figures as on 29 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rudra ParadiseNA161658866

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 94%.

Rudra Paradise: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%
Sanitary Fittings within the flats / premises18%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.43%

Progress on shared amenities15

As on 29 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes12%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes37%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes12%
Electrical meter room, sub-station, receiving stationYes11%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area803 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAU Small Finance Bank Limited
Secured amountRs 31.00 crore
CERSAI search filedYes
Declared on5 Dec 2025

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI4450.02
Proposed, not sanctioned2,032 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS No 637A, Chanda Warkar Road, Borivali, Mumbai 400092
Estimated costRs 28.40 cr
Cost incurredRs 20.88 cr
Work done73.52%
BuildingWingEstimatedIncurred
Rudra ParadiseNARs 28.40 crRs 20.88 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShilp Associates
EngineerRajesh Tailor
EngineerUnistep Consulting Private Limited
Chartered AccountantR H Shukla & Associates
Chartered AccountantSurana Maloo & Co.
Chartered AccountantC D S & Associates
PartnerRole in project
R-Stone Design and Build Limited-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012336Jan 2021 → Dec 2024

Reason as filed by the promoterThe project was not progressing due to some reasons that the erstwhile developer of the project M/s. Rite Developers Private Limited was unable to manage. We are the new developers of the project and have taken over the project last quarter. Since the construction of project was stalled for quite some time now and we have re-started the construction after taking over the project, we will need 24 to 27 months' time to complete the project and then some time for getting all the NOCs and approvals including OC. We have accordingly obtained consents of buyers for the extended time.

EXT51800009254Jan 2021 → Jan 2022

Reason as filed by the promoterDelay in project and delay in getting approvals are attributable to MCGM and MHADA, due to no clarity on implementation of DCPR 2034 for MHADA Policy and to get finalised and also Transition MHADA Policy was not framed, as we wanted to migrate project from one MHADA Policy to another Policy, but due to unframed Transition Policy files of the said project could not be moved for further approvals. We further state that due to outbreak of life threatening COVID-19 which had already been declared as a Pandemic by World Health Organization (WHO) and complete lockdown imposed in the country and Auth

EXT51800019382Jan 2021 → Jul 2026

Reason as filed by the promoterSir, The development of the project is underway, and construction of structure is completed up to 4th Upper floor. We anticipate that the completion of entire construction will take more time than compared to what we have declared at the time of taking over of project from the erstwhile developer. Also, due to slow sales, we are in the process of arranging funds for competing the construction work of the proposed project and the current application for extension is being submitted as part of arrangement with the lending institution. Accordingly, we have obtained consents from the Allottees for

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed151

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Rudra Paradise Amended IoA.pdf29 Apr 2026
Building plan approvalFile: Rudra paradise new amended plan-1.pdf29 Apr 2026
Building plan approvalFile: Rudra paradise new amended plan-2.pdf29 Apr 2026
Building plan approvalFile: Rudra paradise new amended plan-3.pdf29 Apr 2026
Building plan approvalFile: Rudra paradise new amended plan-4.pdf29 Apr 2026
Building plan approvalFile: Rudra paradise new amended plan-5.pdf29 Apr 2026
Commencement certificateFile: Rudra Paradise FCC.pdf29 Apr 2026
Withdrawal Update Form 1File: Rudra Paradise Form-1 Dec 2025.pdf29 Apr 2026
Withdrawal Update Form 2File: Rudra Paradise Form-2 Dec 2025.pdf29 Apr 2026
Withdrawal Update Form 3File: Rudra Paradise Form-3 Dec 2025.pdf29 Apr 2026
Withdrawal Update Form 1File: Rudra Paradise Form-1 Sep 25.pdf20 Apr 2026
Withdrawal Update Form 2File: Rudra Paradise Form-2 Sep 25.pdf20 Apr 2026
Withdrawal Update Form 3File: Rudra Paradise Form-3 Sep 2025.pdf20 Apr 2026
Withdrawal Update Form 1File: Rudra Paradise Form 1_June 2025.pdf5 Dec 2025
Withdrawal Update Form 2File: Rudra Paradise Form 2_June 2025.pdf5 Dec 2025
Withdrawal Update Form 3File: Rudra Paradise Form 3_June 2025.pdf5 Dec 2025
Form 1File: RP Arch Form 1 202303.pdf21 Nov 2025
Form 2File: RP Engr Form 2 202303.pdf21 Nov 2025
Form 3File: RP CA Form 3 202303.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rudra Disclosure of sold booked inventory 202303.pdf21 Nov 2025
Form 1File: RP Arch Form 1 202403.pdf21 Nov 2025
Form 2File: RP Engr Form 2 202403.pdf21 Nov 2025
Form 3File: RP CA Form 3 202403.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: RP Disclosure of sold booked inventory Mar 24.pdf21 Nov 2025
Form 1File: RP Arch Form 1 202309.pdf21 Nov 2025
Form 2File: RP Engr Form 2 202309.pdf21 Nov 2025
Form 3File: RP CA Form 3 202309.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: RP Sold unsold discl Sep 23.pdf21 Nov 2025
Form 1File: RP Arch Form 1 202406.pdf21 Nov 2025
Form 2File: RP Engr Form 2 202406.pdf21 Nov 2025
Form 3File: RP CA Form 3 202406.pdf21 Nov 2025
Disclosure of Sold and Booked InventoryFile: Rudra Disclosure of sold booked inventory 202406.pdf21 Nov 2025
Form 1File: F 1 Dec 2017.pdf15 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F 1 SEP 2024.pdf5 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F 1 DEC 2024.pdf5 Feb 2025
Certificates of CA (Form 3)File: F 3 SEP 2024.pdf5 Feb 2025
Certificates of CA (Form 3)File: F 3 DEC 2024.pdf5 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F 2 SEP 2024.pdf5 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F 2 DEC 2024.pdf5 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202406_Ar.pdf3 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202406_Er.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: 202406_Sold.pdf3 Aug 2024
Certificates of CA (Form 3)File: 202406_CA.pdf3 Aug 2024
Building plan approvalFile: 5_IoD_Letter.pdf1 Jul 2024
Copy of the legal title reportFile: 2A_Title.pdf1 Jul 2024
Building Plan Approval (IOD)File: 5_IoD_Letter.pdf1 Jul 2024
Declaration about Commencement CertificateFile: CC declaration.pdf1 Jul 2024
Proforma of Agreement for saleFile: AfS_Final_2024.pdf4 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrance_AU Bank.pdf28 May 2024
Details of encumbrances concerned to LegalFile: Encumbrance_AU Bank.pdf28 May 2024
CERSAI detailsFile: 202405_CERSAI-Declaration.pdf28 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2023-24_Form-5.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202403_Ar.pdf16 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202403_Er.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: 202403_Sold.pdf16 May 2024
Certificates of CA (Form 3)File: 202403_CA.pdf16 May 2024
Declaration in FORM BFile: Notary Affidavit revise.pdf21 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202312_Ar.pdf2 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202312_Er.pdf2 Mar 2024
Certificates of CA (Form 3)File: 202312_CA.pdf2 Mar 2024
Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf29 Dec 2023
Disclosure of sold/ booked inventoryFile: 202309_Sold.pdf29 Dec 2023
Disclosure of sold/ booked inventoryFile: Rudra Paradise sold_ booked inventory June 2023.pdf15 Dec 2023
Disclosure of sold/ booked inventoryFile: Rudra Paradise sold_ booked inventory Sept 2023.pdf15 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202309_Er.pdf12 Dec 2023
Declaration in FORM BFile: Fom-B_31122024.pdf9 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar.pdf9 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar-1.pdf9 Nov 2023
Certificates of CA (Form 3)File: 202309_CA.pdf9 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23_Form-5.pdf19 Oct 2023
Building plan approvalFile: IoD-2_Part1.pdf17 Oct 2023
Building plan approvalFile: IoD-2_Part2.pdf17 Oct 2023
Building Plan Approval (IOD)File: IoD-2_Part1.pdf17 Oct 2023
Building Plan Approval (IOD)File: IoD-2_Part2.pdf17 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: 20230908_CC.pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202306_Ar.pdf17 Oct 2023
Certificates of CA (Form 3)File: 202306_CA.pdf17 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202303_Ar.pdf9 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 202303_Er.pdf9 Sep 2023
Certificates of CA (Form 3)File: 202303_CA.pdf9 Sep 2023

How this compares with Mumbai Suburban

42%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rudra Paradise on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Santacruz East6,700+ in Mumbai Suburban

2 kmRudra ParadiseCompleted 131Lapsed / revoked 74Other 132Dot size: filed unitsN

Filed coordinates, straight-line distance. 337 registered projects within 2 km.

Builder: R-Stone Design and Build Private Limited

R-Stone Design and Build Private Limited has 1 registration on MahaRERA, including Rudra Paradise. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Rudra Paradise is delayed beyond 21 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rudra Paradise?

The registered promoter entity is R-Stone Design and Build Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rudra Paradise?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rudra Paradise?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rudra Paradise?

The professionals named in the filing: Architect: Shilp Associates; Engineer: Rajesh Tailor; Engineer: Unistep Consulting Private Limited; Chartered Accountant: R H Shukla & Associates; Chartered Accountant: Surana Maloo & Co.; Chartered Accountant: C D S & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rudra Paradise?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rudra Paradise. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rudra Paradise to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.