ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / ROONGTA HORIZON APARTMENT

Completed No litigation declared Residential / Group Housing project

ROONGTA HORIZON APARTMENT

By ROONGTA HOMES LLP

RG-MH-00891 · RERA P51600001399 · Last updated on MahaRERA portal: 1 Mar 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 9 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 25 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jul 2020Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

ROONGTA HORIZON APARTMENT is a Residential / Group Housing project by ROONGTA HOMES LLP in Nashik, Maharashtra, registered with MahaRERA as P51600001399 on 28 Jul 2017. The registration is recorded completed; possession was promised by 31 Jul 2020.

At a glance

Project

  • NameROONGTA HORIZON APARTMENT
  • TypeResidential / Group Housing
  • Location
    • NASHIK
    • 422001
  • Pincode422001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600001399
  • ReraGenie IDRG-MH-00891

Builder

  • NameROONGTA HOMES LLP
  • Entity typePartnership
  • GSTIN27AAUFR4502Q2ZE
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersAKHIL LALIT ROONGTA, LALIT SATYANARAYAN ROONGTA, NIKHIL LALIT ROONGTA
  • Other registrations25 more →
  • Completed25 of 26
  • Declared earlier projects9 →

Key dates

this monthRegisteredJul 2017PromisedJul 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Jul 2017
  • Promised completion31 Jul 2020
  • Revised completionNone
  • Buildings2 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROONGTA HORIZON APARTMENT- A WINGNA80000
ROONGTA HORIZON APARTMENT- B WINGNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

ROONGTA HORIZON APARTMENT- A WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROONGTA HORIZON APARTMENT- B WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Closed/Covered47
Open Space29
BuildingClosed/CoveredOpen SpaceTotal
ROONGTA HORIZON APARTMENT- A WING231538
ROONGTA HORIZON APARTMENT- B WING241438

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,909 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S S. P. VENTURESNashikNashik

Approvals and building plan

Permissible FSI6344.15
Proposed, not sanctioned5,271 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURKAN ARCADE, BHUJBAL FARM ROAD,PLOT NO ME-1,CIDCO,INDIRA NAGAR,NASHIK-422009

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR SAGAR ARUN KABRE
EngineerSANJEEV MADHUSUDAN PATEL
EngineerAMOL YADAVRAO BHALERAO
Chartered AccountantANAND RATHI & ASSOCIATES, CHARTERED ACCOUNTANT
Chartered AccountantPravin R. Rathi & Assocaites
Chartered AccountantPrem R. Patil & Associates
PartnerRole in project
ROONGTA HOMES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Mar 2023

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: HORIZON COMPLETION.pdf1 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: APARTMENT DECLARATION INDEX II.pdf25 Dec 2019
Status of ConveyanceFile: APARTMENT DECLARATION INDEX II.pdf25 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: HORIZON.pdf31 Oct 2019
Certificates of Architect (Form 4)File: FORM 4 HORIZON.pdf14 May 2019
OtherFile: HORIZON COMPLETION.pdf14 May 2019
Certificates of CA (Form 5)File: HORIZON.pdf30 Sep 2018
Details of encumbrancesFile: HORIZON.pdf14 Dec 2017
Proforma of Allotment letterFile: RERA uploading draft.pdf2 Dec 2017
Building plan approvalFile: horizon 1 no sheet.pdf25 Jul 2017
Building plan approvalFile: sheet 2 horizonm.pdf25 Jul 2017
Building plan approvalFile: 3 new.pdf25 Jul 2017
Copy of the legal title reportFile: HORIZON ADVOCATE TITLE.pdf25 Jul 2017
Building Plan Approval (IOD)File: horizon 1 no sheet.pdf25 Jul 2017
Building Plan Approval (IOD)File: sheet 2 horizonm.pdf25 Jul 2017
Building Plan Approval (IOD)File: 3 new.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: comencement certificate.pdf25 Jul 2017
Certificates of CA (Form 3)File: ca certificate.pdf25 Jul 2017
Layout approvalFile: HORIZON DLR.pdf19 Jul 2017
Layout approvalFile: HORIZON LAYOUT.PDF19 Jul 2017
Copy of Layout Approval (in case of layout)File: HORIZON DLR.pdf19 Jul 2017
Copy of Layout Approval (in case of layout)File: HORIZON LAYOUT.PDF19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: horizon architect certificate new.pdf19 Jul 2017
PAN CardFile: PAN.pdf15 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf15 Jul 2017
Details of encumbrancesFile: SELF DECLARATION FOR NON ENCUMBRANCES.pdf15 Jul 2017
Declaration in FORM BFile: FORM B.pdf15 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf15 Jul 2017
Proforma of Allotment letterFile: DECLARATION FOR PERFORMA OF ALLOTMENT.pdf15 Jul 2017

Promoter's earlier projects9

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHREE TIRUMALA GULMOHAR APARTMENTDivision Makhmalabad Shiwar NASHIK Taluka NASHIK Dist NASHIK156CompletedApr 2022Aug 2020
SHREE TIRUMALA PARAMOUNT APARTMENTTaluka NASHIK Dist NASHIK-422009173CompletedJun 2021Feb 2020
SHREE TIRUMALA REGENCY APARTMENTDeepali Nagar NASHIK Taluka NASHIK Dist NASHIK 42200950CompletedDec 2020May 2020
ROONGTA IMPERIA APARTMENTNASHIK 422001112CompletedJul 2020Mar 2019
ROONGTA HORIZON APARTMENTNASHIK 422001112CompletedJul 2020Mar 2019
SHREE TIRUMALA PLATINUM APARTMENTCOLLEGE ROAD NASHIK 42200510CompletedMay 2020Dec 2018
SHREE TIRUMALA PARADISE APARTMENTCHETANA NAGAR NASHIK 42200928CompletedSep 2019Nov 2018
SHREE TIRUMALA HARINIWAS APARTMENTSR.NO.78 PLOT NO.83 SATPUR NASHIK42CompletedMar 2019May 2018
SHREE TIRUMALA SWASTIK APARTMENTINDIRA NAGAR NASHIK28CompletedDec 2018Jun 2018

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROONGTA HORIZON APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASHIK4,100+ in Nashik

2 kmROONGTA HORIZON APARTMENCompleted 80Lapsed / revoked 15Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: ROONGTA HOMES LLP

ROONGTA HOMES LLP has 26 registrations on MahaRERA, including SHREE TIRUMALA SWASTIK APARTMENT and SHREE TIRUMALA PARADISE APARTMENT. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if ROONGTA HORIZON APARTMENT is delayed beyond 31 Jul 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROONGTA HORIZON APARTMENT?

The registered promoter entity is ROONGTA HOMES LLP, a partnership as per the filing. Its GSTIN 27AAUFR4502Q2ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROONGTA HORIZON APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROONGTA HORIZON APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROONGTA HORIZON APARTMENT?

The professionals named in the filing: Architect: MR SAGAR ARUN KABRE; Engineer: SANJEEV MADHUSUDAN PATEL; Engineer: AMOL YADAVRAO BHALERAO; Chartered Accountant: ANAND RATHI & ASSOCIATES, CHARTERED ACCOUNTANT; Chartered Accountant: Pravin R. Rathi & Assocaites; Chartered Accountant: Prem R. Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROONGTA HORIZON APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROONGTA HORIZON APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROONGTA HORIZON APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.