Registered No litigation declared Others project

RKH Mountain Manor

By Sitai Construction

RG-MH-31146 · RERA P52100079480 · Last updated on MahaRERA portal: 20 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 15.00 crore secured on the land, in favour of TRUHOME FINANCE LTD

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Podiums (if any), 75%
152 of 188Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

RKH Mountain Manor is a Others project by Sitai Construction in Pune, Maharashtra, registered with MahaRERA as P52100079480 on 7 Mar 2025. Possession is promised by 31 Dec 2027. 36 of the 188 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameRKH Mountain Manor
  • TypeOthers
  • Location
    • Kudale wasti
    • Near Kudale Garden
    • Moshi
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100079480
  • ReraGenie IDRG-MH-31146

Builder

  • NameSitai Construction
  • Entity typePartnership
  • PartnersKiran Baban Alhat, Yogesh Gorakhnath Alhat, Sampat Baban Alhat, Prakash Baban Alhat, Mayur Uttam Alhat
  • Declared earlier projects3 →

Key dates

this monthRegisteredMar 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Mar 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed93 files

Current status

19%36 of 188 units booked
21.3%Work done, per cost certificate

Figures as on 20 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA161517513188

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 75%.

A Wing: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)62%
Podiums (if any)75%
Plinth75%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed211

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots211
Open Space211

Land and ownership33

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,900 sq m
Land owned byNot the promoter
Named landowners33
Encumbrance on the landDeclared present
Charge in favour ofTRUHOME FINANCE LTD
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on12 Aug 2025
LandownerVillageDistrict
Sahil Baban AlhatMoshiPune
Dattatray Khandu AlhatMoshiPune
Barku Nana AlhatMoshiPune
Hausabai Barku AlhatMoshiPune
Popat Barku AlhatMoshiPune
Rajani Popat AlhatMoshiPune
Vidya Sunil BorateMoshiPune
Anita Nagnath TilekarMalewadiPune
Gita Nandkumar TilekarMalewadiPune
Savita Ankush JadhavChikhaliPune
Pallavi Rahul LadkatPune (CB)Pune
Archana Dinesh KudalePimpri Chinchawad (M Corp.)Pune
Ashwini Dattatray AlhatMoshiPune
Kartik Dattatray AlhatMoshiPune
Vaishnavi Dattatray AlhatMoshiPune
Hanumant Sopan AlhatMoshiPune
Usha Hanumant AlhatMoshiPune
Shraddha Hanumant AlhatMoshiPune
Harsh Hanumant AlhatMoshiPune
Baban Sopan AlhatMoshiPune
Kumudini Baban AlhatMoshiPune
Mrunal Baban AlhatMoshiPune
Atharv Popat AlhatMoshiPune
Arnav Popat AlhatMoshiPune
Arjun Nana AlhatMoshiPune
Sharada Arjun AlhatMoshiPune
Samir Arjun AlhatMoshiPune
Madhuri Samir AlhatMoshiPune
Gayatri Samir AlhatMoshiPune
Gauri Samir AlhatMoshiPune
Shivam Samir AlhatMoshiPune
Surekha Vijay ShevkariChikhaliPune
Chaya Santosh ZurangeMoshiPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI14866.16
Proposed, not sanctioned14,830 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD FLR SHOP NO 1 3 4 5 KAMALRAJ ESTATE KAMALRAJ CENTRAL MOSHI DEHU ROAD PIMPRI CHINCHWAD MAHARASHTRA 412105
Estimated costRs 44.31 cr
Cost incurredRs 9.43 cr
Work done21.28%
BuildingWingEstimatedIncurred
A WingNARs 40.96 crRs 9.43 cr
-NARs 3.35 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLANDMARK DESIGN GROUP
EngineerSWAMIRAJ PMC
Chartered AccountantCA.Jayesh R Meena
Chartered AccountantA I MODI AND CO
PartnerRole in project
Sitai Construction-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Feb 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q 4 form 1.pdf20 May 2026
Withdrawal Update Form 2File: Q 4 Form2.pdf20 May 2026
Withdrawal Update Form 3File: Q 4 Form 3.pdf20 May 2026
Withdrawal Update Form 1File: Sitai Construction Form 1 (4).pdf18 Feb 2026
Withdrawal Update Form 2File: RKH mountain manor engineering certificate 07-01-2026 (1).pdf18 Feb 2026
Withdrawal Update Form 3File: Sitai Cons_Form 3 (1).pdf18 Feb 2026
Withdrawal Update Form 1File: Sitai Construction Form-1.pdf19 Nov 2025
Withdrawal Update Form 2File: Sitai Construction Form-2.pdf19 Nov 2025
Withdrawal Update Form 3File: Sitai Cons_Form 3 (1).pdf19 Nov 2025
Layout approvalFile: Plan 1.pdf9 Oct 2025
Building plan approvalFile: Plan 2.pdf9 Oct 2025
Building plan approvalFile: Plan 3.pdf9 Oct 2025
Building plan approvalFile: Plan 4.pdf9 Oct 2025
Building plan approvalFile: Plan 5.pdf9 Oct 2025
Building plan approvalFile: Plan 6.pdf9 Oct 2025
Building plan approvalFile: Plan 7.pdf9 Oct 2025
Building plan approvalFile: Plan 8.pdf9 Oct 2025
Building plan approvalFile: Plan 9.pdf9 Oct 2025
Withdrawal Update Form 1File: FROM 1.pdf24 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf24 Sep 2025
Withdrawal Update Form 3File: Form 3 Q1 Revised.pdf24 Sep 2025
Withdrawal Update Form 1File: FROM 1.pdf21 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf21 Sep 2025
Withdrawal Update Form 3File: Form 3 Q1 Revised.pdf21 Sep 2025
Withdrawal Update Form 1File: FROM 1.pdf13 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf13 Sep 2025
Withdrawal Update Form 3File: Form 3 Q1.pdf13 Sep 2025
Withdrawal Update Form 1File: FROM 1.pdf11 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf11 Sep 2025
Withdrawal Update Form 3File: Form 3 Q1.pdf11 Sep 2025
Withdrawal Update Form 1File: FROM 1.pdf26 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf26 Aug 2025
Withdrawal Update Form 3File: FROM 3.pdf26 Aug 2025
Withdrawal Update Form 1File: Form 1 Q1.pdf24 Aug 2025
Withdrawal Update Form 1File: Form 1 Q1.pdf24 Aug 2025
Withdrawal Update Form 2File: Form 2 Q1.pdf24 Aug 2025
Withdrawal Update Form 2File: Form 2 Q1.pdf24 Aug 2025
Withdrawal Update Form 3File: Form 3 Q1.pdf24 Aug 2025
Withdrawal Update Form 3File: Form 3 Q1.pdf24 Aug 2025
Form 1File: Form 1 Q4.pdf18 Aug 2025
Form 2File: Form 2 Q4.pdf18 Aug 2025
Form 3File: Form 3 Q4.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: Promoters disclosure Q4 RKH M.pdf18 Aug 2025
Building plan approvalFile: NA Order for plotted development.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: NA Order for plotted development.pdf4 Mar 2025
Other - TechnicalFile: cc verif.pdf11 Feb 2025
Copy of the legal title reportFile: Updated Legal Title report_11zon (1).pdf9 Feb 2025
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE.pdf9 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3(1)-output_11zon.pdf9 Feb 2025
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE.pdf9 Feb 2025
Proforma of Agreement for saleFile: Sitai Draft final sitai - sec 2 (1).pdf9 Feb 2025
Other - FinanceFile: pdf_to_scan_67a7180535e54_temp_67a717fa6e879.pdf8 Feb 2025
Deviation Report with respect to model copy of AgreementFile: Deviation.pdf5 Feb 2025
Declaration in FORM BFile: form b promoter.pdf1 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: dis.pdf1 Feb 2025
Proforma of Allotment letterFile: ALLOTMENT LETTER (1).pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate RKH Mountain Manor 15-02-2025-output.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 (3)-output (2).pdf27 Jan 2025
Other - LegalFile: मोशी_305_Satbara (1).pdf25 Jan 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf25 Jan 2025
Details of encumbrances concerned to FinanceFile: details encumbrances to finance.pdf24 Jan 2025
Other - LegalFile: Annexure A .pdf24 Jan 2025
CERSAI detailsFile: CERSAI Report.pdf24 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: A .pdf24 Jan 2025
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment .pdf24 Jan 2025
Details of encumbrances concerned to LegalFile: details encumbrances to finance.pdf24 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclousre in other real estate org-1.pdf24 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclousre in other real estate org-2.pdf24 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclousre in other real estate org-3.pdf24 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclousre in other real estate org-4-output (1).pdf24 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: pdf_to_scan_679cb40d02c67_temp_679cb40a18c78.pdf24 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: b.pdf24 Jan 2025
Layout approvalFile: 2_11zon.pdf23 Jan 2025
Layout approvalFile: 3_11zon.pdf23 Jan 2025
Layout approvalFile: 4_11zon.pdf23 Jan 2025
Layout approvalFile: 5_11zon.pdf23 Jan 2025
Layout approvalFile: 6_11zon.pdf23 Jan 2025
Layout approvalFile: 7_11zon.pdf23 Jan 2025
Layout approvalFile: 8_11zon.pdf23 Jan 2025
Building plan approvalFile: LAYOUT.pdf23 Jan 2025

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
RKH PRIDEPimpri17CompletedJun 2024Late, Nov 2024
RKH BLESSINGSMoshi and Chikhali118CompletedAug 2023Dec 2022
RKH REALITIESMoshi16CompletedJun 2023Late, May 2024

How this compares with Pune

19%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RKH Mountain Manor on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Kudale Garden13,700+ in Pune

2 kmRKH Mountain ManorCompleted 51Lapsed / revoked 28Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 144 registered projects within 2 km.

Builder: Sitai Construction

Sitai Construction has 1 registration on MahaRERA, including RKH Mountain Manor. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if RKH Mountain Manor is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RKH Mountain Manor?

The registered promoter entity is Sitai Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RKH Mountain Manor?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RKH Mountain Manor?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RKH Mountain Manor?

The professionals named in the filing: Architect: LANDMARK DESIGN GROUP; Engineer: SWAMIRAJ PMC; Chartered Accountant: CA.Jayesh R Meena; Chartered Accountant: A I MODI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RKH Mountain Manor?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RKH Mountain Manor. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RKH Mountain Manor to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.