ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / RKH Golden Sunrise Building A

Registration lapsed No litigation declared Residential / Group Housing project

RKH Golden Sunrise Building A

By Sargun Developers

RG-MH-17157 · RERA P52100028036 · Last updated on MahaRERA portal: 19 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

RKH Golden Sunrise Building A is a Residential / Group Housing project by Sargun Developers in Pune, Maharashtra, registered with MahaRERA as P52100028036 on 26 Jan 2021. Possession was promised by 30 Mar 2025 and is now 19 months past that date.

At a glance

Project

  • NameRKH Golden Sunrise Building A
  • TypeResidential / Group Housing
  • Location
    • Moshi Alandi Road
    • Moshi
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028036
  • ReraGenie IDRG-MH-17157

Builder

  • NameSargun Developers
  • Entity typePartnership
  • PartnersYogesh Alhat, Nilesh Kudale, Sumangala Pandurang Jadhav

Key dates

19 months past promisethis monthRegisteredJan 2021PromisedMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jan 2021
  • Promised completion30 Mar 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RKH Golden Sunrise Building ANA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

RKH Golden Sunrise Building A: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed252

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots252
Closed/Covered227
Open Space25

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Shanta Mahendra Alhat-Pune
Vilas Dattu Alhat-Pune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI2023.58
Proposed, not sanctioned2,024 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMoshi Pune, MH, Pune-412105

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYogesh Manakshe
EngineerVikas Pote
Chartered AccountantCA Parag Bhujbal
Chartered AccountantCA Jashan Chandani
Chartered AccountantParag Bhujbal
PartnerRole in project
Sargun Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECT CERTIFICATE q3.pdf19 Jun 2025
Form 2File: form 2 q3.pdf19 Jun 2025
Form 3File: sargun form 3 date 27-1-25_compressed.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Rera sold unsold 13-01-25.pdf19 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE q3.pdf1 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sargun form 3 date 27-1-25_compressed.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 q3.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sargun_compressed (1).pdf10 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sargun Developers form 5.pdf28 Jan 2024
Layout approvalFile: Layout Plan-compressed.pdf25 Aug 2023
Layout approvalFile: Layout Plan-compressed (1).pdf25 Aug 2023
Building plan approvalFile: Parking Floor Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Podium Parking Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Terrace Floor Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Typical Floor Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Ground Floor Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Elevation Plan-compressed.pdf25 Aug 2023
Building plan approvalFile: Elevation Section A and B.pdf25 Aug 2023
Copy of Layout Approval (in case of layout)File: Layout Plan-compressed.pdf25 Aug 2023
Copy of Layout Approval (in case of layout)File: Layout Plan-compressed (1).pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Parking Floor Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Podium Parking Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Terrace Floor Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Typical Floor Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Ground Floor Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Elevation Plan-compressed.pdf25 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Elevation Section A and B.pdf25 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf25 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sargun Dev Form 5.PDF17 Oct 2022
Building plan approvalFile: scan771.pdf1 Jul 2022
Building plan approvalFile: scan772.pdf1 Jul 2022
Building plan approvalFile: scan773.pdf1 Jul 2022
Building plan approvalFile: scan775.pdf1 Jul 2022
Building plan approvalFile: scan777.pdf1 Jul 2022
Details of encumbrances concerned to LegalFile: scan776.pdf1 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: scan771.pdf1 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: scan772.pdf1 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: scan773.pdf1 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: scan775.pdf1 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: scan777.pdf1 Jul 2022
Declaration in FORM BFile: Nilesh_Kudale_B_form.pdf1 Jul 2022
Declaration in FORM BFile: Sumngala_Jadhav_B_form.pdf1 Jul 2022
Declaration in FORM BFile: Yogesh_Alhat_B_Form.pdf1 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.PDF31 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sargun Developers Form 1.pdf5 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sargun Developers Form 2.pdf5 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sargun Developers Form 2A.pdf5 Feb 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Details.pdf5 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sargun developers Form 2.pdf12 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sargun Developers Form 2A.pdf12 Nov 2021
Disclosure of sold/ booked inventoryFile: Sargun Developers Format D.pdf12 Nov 2021
Disclosure of sold/ booked inventoryFile: Discolsure sold unsold.pdf24 Aug 2021
Declaration about Commencement CertificateFile: FORMAT-D.pdf21 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sargun Dev Form 3.PDF17 Aug 2021
Building plan approvalFile: Section .pdf14 Aug 2021
Layout approvalFile: Lay out Parking Plan.pdf14 Aug 2021
Building plan approvalFile: Typical 2nd to 10th Floor .pdf14 Aug 2021
Building plan approvalFile: Typical and elevations .pdf14 Aug 2021
Copy of Layout Approval (in case of layout)File: Lay out Parking Plan.pdf14 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Typical 2nd to 10th Floor .pdf14 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Typical and elevations .pdf14 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Section .pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect’s Certificate.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No 2.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form No 2A.pdf14 Aug 2021
Details of encumbrancesFile: no encumbrances.pdf19 Jan 2021
Declaration in FORM BFile: sargun Form B-compressed.pdf19 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Sargun developers.pdf19 Jan 2021
Layout approvalFile: Terrace Plan.pdf18 Jan 2021
Building plan approvalFile: Stamp Of Approval.pdf18 Jan 2021
Layout approvalFile: 1st Floor Plan.pdf18 Jan 2021
Layout approvalFile: 3rd Floor Plan.pdf18 Jan 2021
Building plan approvalFile: Elevation Plan.pdf18 Jan 2021
Building plan approvalFile: Parking Plan.pdf18 Jan 2021
PAN CardFile: sargun PAN.pdf18 Jan 2021
Copy of the legal title reportFile: Title Report 153.pdf18 Jan 2021
Copy of the legal title reportFile: Title Report 151.pdf18 Jan 2021
Copy of Layout Approval (in case of layout)File: Terrace Plan.pdf18 Jan 2021
Copy of Layout Approval (in case of layout)File: 1st Floor Plan.pdf18 Jan 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RKH Golden Sunrise Building A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Moshi13,700+ in Pune

2 kmRKH Golden Sunrise BuildCompleted 77Lapsed / revoked 39Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 209 registered projects within 2 km.

Builder: Sargun Developers

Sargun Developers has 1 registration on MahaRERA, including RKH Golden Sunrise Building A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that RKH Golden Sunrise Building A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RKH Golden Sunrise Building A is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RKH Golden Sunrise Building A?

The registered promoter entity is Sargun Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RKH Golden Sunrise Building A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RKH Golden Sunrise Building A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RKH Golden Sunrise Building A?

The professionals named in the filing: Architect: Yogesh Manakshe; Engineer: Vikas Pote; Chartered Accountant: CA Parag Bhujbal; Chartered Accountant: CA Jashan Chandani; Chartered Accountant: Parag Bhujbal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RKH Golden Sunrise Building A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RKH Golden Sunrise Building A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RKH Golden Sunrise Building A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.