Home / Browse projects / Raigarh, Maharashtra / Riverium Villas
Riverium Villas
RG-MH-87843 · RERA P52000050462 · Last updated on MahaRERA portal: 23 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Riverium Villas is a Mixed project by M/S GAGANGIRI LIFESPACES in Raigarh, Maharashtra, registered with MahaRERA as P52000050462 on 17 Apr 2023. Possession is promised by 31 Jul 2027. 41 of the 89 units on this registration are recorded sold or booked, and 105 of 495 construction stages are filed complete.
At a glance
Project
- NameRiverium Villas
- TypeMixed
- Location
- PINGLAS
- KAJAT
- Karjat
- Raigarh
- 410201
- Pincode410201
- RERA no.P52000050462
- ReraGenie IDRG-MH-87843
Builder
- NameM/S GAGANGIRI LIFESPACES
- Entity typeOthers
- Named personNAYNA ROGE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Apr 2023
- Promised completion31 Jul 2027
- Revised completionNone
- Buildings45 building records
- Documents filed72 files
Current status
Figures as on 23 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PLOT NO 1 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 2 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 3 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 4 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 5 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 6 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 7 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 8 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 9 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 10 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 11 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 12 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 13 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 14 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 15 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 16 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 17 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 18 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 19 | NA | 0 | 0 | 0 | 0 | 0 |
| PLOT NO 20 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 21 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 22 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 23 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 24 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 25 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 26 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 27 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 28 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 29 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 30 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 31 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 32 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 33 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 34 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 35 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 36 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 37 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 38 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 39 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 40 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 41 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 42 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 43 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 44 | NA | 1 | 1 | 1 | 0 | 1 |
| PLOT NO 45 | NA | 1 | 1 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 23 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 46 buildings; the table lists the first 20.
105 of 495 construction stages are filed complete across 46 buildings. The stage furthest along is Internal walls, at 90%.
PLOT NO 145%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 615%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 60% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 739%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 845%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 937%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 1014%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 1173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
PLOT NO 1265%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
PLOT NO 1318%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 140%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 150%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 160%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 170%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 1873%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
PLOT NO 190%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PLOT NO 2031%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 20% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 3.23 cr | Rs 2.37 cr |
| PLOT NO 1 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 2 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 3 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 4 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 5 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 6 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 7 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 8 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 9 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 10 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
| PLOT NO 11 | NA | Rs 56.25 lakh | Rs 19.69 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NEMADE DESIGN STUDIO |
| Architect | PARIN SHAH |
| Architect | SHRIYA WARERKAR |
| Engineer | ADITYAH HARPUDE |
| Engineer | ADITYA HARPUDE |
| Chartered Accountant | NEHALI & CO |
| Chartered Accountant | M TRIVEDI AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| M/S GAGANGIRI LIFESPACES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2027
Documents filed72
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 23 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 23 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 23 May 2026 |
| Withdrawal Update Form 2File: Engg.pdf | 23 May 2026 |
| Withdrawal Update Form 2File: Engg.pdf | 23 May 2026 |
| Withdrawal Update Form 2File: Engg.pdf | 23 May 2026 |
| Withdrawal Update Form 3File: form3.pdf | 23 May 2026 |
| Withdrawal Update Form 3File: form3.pdf | 23 May 2026 |
| Withdrawal Update Form 3File: form3.pdf | 23 May 2026 |
| Withdrawal Update Form 1File: form 1 compress.pdf | 14 May 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 14 May 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: DOC-20251020-WA0256..pdf | 14 May 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 14 May 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 11 May 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 11 May 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 11 May 2026 |
| Form 2A (FY 2024-2025)File: riverium villas form 2a.pdf | 8 Oct 2025 |
| Form 5 (FY 2024-2025)File: riverum villas form 5.pdf | 8 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 16 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 architect certificate DEC 23.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer certificate DEC 23.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ca certificate DEC 23.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECTS-FORM 1-30092023 1.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECTS-FORM 1-30092023 2.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER form 2.pdf | 13 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed final CA Certificate-- Priyank Gala sep'23.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 18 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 18 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3.pdf | 18 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: revised signed CA Certificate Priyank rev.pdf | 6 Apr 2023 |
| PAN CardFile: letter_rera.pdf | 9 Mar 2023 |
| Proforma of Agreement for saleFile: Agreement for sale.pdf | 3 Mar 2023 |
| Proforma of Agreement for saleFile: Clarification_letter.pdf | 3 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation_report_on_agreement_ (1).pdf | 3 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrance self- declaration .pdf | 2 Mar 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrance self- declaration .pdf | 2 Mar 2023 |
| CERSAI detailsFile: Cersai declaration .pdf | 2 Mar 2023 |
| Other - TechnicalFile: PLANS 1 TO 2.pdf | 2 Mar 2023 |
| Other - TechnicalFile: CC.pdf | 2 Mar 2023 |
| Layout approvalFile: PLANS 1 TO 2.pdf | 21 Feb 2023 |
| Layout approvalFile: PLANS 3 TO 7.pdf | 21 Feb 2023 |
| Building plan approval or NA orderFile: PLANS 1 TO 2.pdf | 21 Feb 2023 |
| Building plan approval or NA orderFile: PLANS 3 TO 7.pdf | 21 Feb 2023 |
| PAN CardFile: NAYNA PAN CARD.pdf | 21 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: PLANS 1 TO 2.pdf | 21 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: PLANS 3 TO 7.pdf | 21 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLANS 1 TO 2.pdf | 21 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: PLANS 3 TO 7.pdf | 21 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A.pdf | 21 Feb 2023 |
| Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER FINAL.pdf | 21 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: No deviation allotment.pdf | 21 Feb 2023 |
| Copy of the legal title reportFile: TITLE AND SEARCH REPORT.pdf | 16 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE CERTIFICATE.pdf | 16 Feb 2023 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE CERTIFICATE.pdf | 16 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: NA FINEL ORDER 411C.pdf | 16 Feb 2023 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 16 Feb 2023 |
| Declaration in FORM BFile: FORM B.pdf | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 16 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf | 16 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA BANK AC DETAILS.pdf | 16 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 72 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Riverium Villas on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAJAT5,900+ in Raigarh
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: M/S GAGANGIRI LIFESPACES
M/S GAGANGIRI LIFESPACES has 1 registration on MahaRERA, including Riverium Villas. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Riverium Villas is delayed beyond 31 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Riverium Villas?
The registered promoter entity is M/S GAGANGIRI LIFESPACES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Riverium Villas?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Riverium Villas?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Riverium Villas?
The professionals named in the filing: Architect: NEMADE DESIGN STUDIO; Architect: PARIN SHAH; Architect: SHRIYA WARERKAR; Engineer: ADITYAH HARPUDE; Engineer: ADITYA HARPUDE; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Riverium Villas?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.