ReraGenieLog inGet a buyer report

Home / Browse projects / Dhule, Maharashtra / REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE

Registered No litigation declared Residential / Group Housing project

REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE

By SHIRPUR WARWADE MUNICIPLE COUNCIL

RG-MH-58212 · RERA P49800052133 · Last updated on MahaRERA portal: 26 Jun 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dhule registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedmoved 60 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 16%
0Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE is a Residential / Group Housing project by SHIRPUR WARWADE MUNICIPLE COUNCIL in Dhule, Maharashtra, registered with MahaRERA as P49800052133 on 24 Jul 2023. Possession is promised by 31 Mar 2029. The completion date has moved by 60 months from the original filing.

At a glance

Project

  • NameREVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE
  • TypeResidential / Group Housing
  • Location
    • R C PATEL COLLEGE ROAD AMBIKA NAGAR
    • SHIRPUR WARWADE
    • Shirpur-Warwade (M Cl)
    • Shirpur
    • Dhule
    • 425405
  • Pincode425405
  • RERA no.P49800052133
  • ReraGenie IDRG-MH-58212

Builder

  • NameSHIRPUR WARWADE MUNICIPLE COUNCIL
  • Entity typePublic Authority

Key dates

this monthRegisteredJul 2023First promiseMar 2024Revised toMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jul 2023
  • Promised completion31 Mar 2029
  • Revised completionRevised to 31 Mar 2029 (originally 31 Mar 2024)
  • Buildings2 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EWS BUILDINGNA30000
MIG BUILDINGNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 26 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 16%.

EWS BUILDING2%
ActivityProgress
Excavation16%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure2%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MIG BUILDING2%
ActivityProgress
Excavation16%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor1%
Slabs of Super Structure2%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes0%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Open Space5

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area36,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHIRPUR WARWADE MUNICIPLE COUNCILShirpur-Warwade (M Cl)Dhule

Approvals and building plan

Permissible FSI36716.58
Proposed, not sanctioned36,717 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIRPUR BRACH TAH SHIRPUR DIST DHULE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIT K AGRAWAL
EngineerDNYANESHVAR RAMCHANDRA PATIL
Chartered AccountantANKUSH ANIL JAIN
PartnerRole in project
SHIRPUR WARWADE MUNICIPLE COUNCIL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT49800019637Mar 2024 → Mar 2029

Reason as filed by the promoterDevelopers may require extra time to devise effective marketing strategies, engage potential buyers, or adjust pricing and offerings to align with market preferences and maximize sales potential

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2029

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Notary FormB.pdf26 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form- 2A.pdf26 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form- 2A.pdf26 Jun 2024
Disclosure of sold/ booked inventoryFile: sold inventory.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form No-5.pdf26 Jun 2024
Details of encumbrances concerned to FinanceFile: Financial new Encumbrances.pdf21 Jul 2023
Details of encumbrances concerned to LegalFile: Financial new Encumbrances.pdf21 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Final Discloser.pdf18 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Jan 2023
Building plan approvalFile: Block B Plan1.pdf19 Jan 2023
Building plan approvalFile: Block B Plan2.pdf19 Jan 2023
Building plan approvalFile: Block C Plan.pdf19 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Block B Plan1.pdf19 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Block B Plan2.pdf19 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Block C Plan.pdf19 Jan 2023
Layout approvalFile: Layout.pdf17 Nov 2022
Building plan approvalFile: Layout Map.pdf17 Nov 2022
PAN CardFile: pan card.pdf17 Nov 2022
Copy of the legal title reportFile: Revised Search Report.pdf17 Nov 2022
Details of encumbrances concerned to FinanceFile: Legal Encumbrance Final.pdf17 Nov 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrance Final.pdf17 Nov 2022
Copy of Layout Approval (in case of layout)File: Layout.pdf17 Nov 2022
Building Plan Approval / NA Order for plotted developmentFile: Layout Map.pdf17 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf17 Nov 2022
Declaration about Commencement CertificateFile: Format D.pdf17 Nov 2022
Declaration in FORM BFile: Formate B.pdf17 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.pdf17 Nov 2022
CERSAI detailsFile: Cersai Final.pdf17 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Nov 2022
Proforma of Allotment letterFile: Allotment Letter.pdf17 Nov 2022
Proforma of Agreement for saleFile: Agreement for Sale.pdf17 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Final.pdf17 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation for Allotment Letter.pdf17 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for Sale.pdf17 Nov 2022

How this compares with Dhule

21%of Dhule projects moved their completion datethis one moved by 60 months
30%of Dhule registrations have lapsed or been cancelledthis one is on the register

Computed across the 71 Dhule projects on ReraGenie, from their own filings.

Keep REVISED TO PROPOSED 400 EWS AND 288 MIG HOUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIRPUR WARWADE71 in Dhule

Builder: SHIRPUR WARWADE MUNICIPLE COUNCIL

SHIRPUR WARWADE MUNICIPLE COUNCIL has 1 registration on MahaRERA, including REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dhule district page.

Frequently asked questions

What are my rights if REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE?

The registered promoter entity is SHIRPUR WARWADE MUNICIPLE COUNCIL, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE?

The professionals named in the filing: Architect: AMIT K AGRAWAL; Engineer: DNYANESHVAR RAMCHANDRA PATIL; Chartered Accountant: ANKUSH ANIL JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About REVISED TO PROPOSED 400 EWS AND 288 MIG HOUSING AT SITE NO.1A SURVEY NO.60 MAUJJA.WARWADE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save REVISED TO PROPOSED 400 EWS AND 288 MIG HOUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.