Home / Browse projects / Gadchiroli, Maharashtra / Residential Layout
Residential Layout
By M/S RAM BUILDERS AND DEVELOPERS
RG-MH-50518 · RERA P50800025832 · Last updated on MahaRERA portal: 2 Mar 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 2 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Gadchiroli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Residential Layout is a Plotted project by M/S RAM BUILDERS AND DEVELOPERS in Gadchiroli, Maharashtra, registered with MahaRERA as P50800025832 on 19 Jul 2020. The registration is recorded completed; possession was promised by 31 Dec 2020. 0 of the 24 units on this registration are recorded sold or booked.
At a glance
Project
- NameResidential Layout
- TypePlotted
- Location
- Visapur road
- Gadchiroli
- Gadchiroli (M Cl)
- 442605
- Pincode442605
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50800025832
- ReraGenie IDRG-MH-50518
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on19 Jul 2020
- Promised completion31 Dec 2020
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed18 files
Current status
Figures as on 2 Mar 2023, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 2 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAM BUILDERS AND DEVELOPERS | Gadchiroli (M Cl) | Gadchiroli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NAYAN KULLARWAR |
| Engineer | RAHUL RAMESH SUNKURWAR |
| Chartered Accountant | PD CHOPDA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| M/S RAM BUILDERS AND DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Mar 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Feb 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Feb 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Mar 2023
Documents filed18
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: encumbrences layout.pdf | 2 Mar 2023 |
| Details of encumbrances concerned to LegalFile: encumbrences layout.pdf | 2 Mar 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NOC from Nagparishad visapur layout.pdf | 2 Mar 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 new.pdf | 2 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM B for layout.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Ram builder balance sheet 21-22.pdf | 5 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ram builder balance sheet 21-22.pdf | 5 Feb 2023 |
| Copy of the legal title reportFile: search report.pdf | 14 Mar 2020 |
| Proforma of Allotment letterFile: SALE DEED VISAPUR1.pdf | 7 Mar 2020 |
| Layout approvalFile: sanctioned layout map visapur.pdf | 14 Feb 2020 |
| Building plan approval or NA orderFile: NA order visapur.pdf | 14 Feb 2020 |
| PAN CardFile: PAN Ram Builders.pdf | 14 Feb 2020 |
| Details of encumbrancesFile: encumbrences layout.pdf | 14 Feb 2020 |
| Copy of Layout Approval (in case of layout)File: sanctioned layout map visapur.pdf | 14 Feb 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: NA order visapur.pdf | 14 Feb 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: NA order visapur.pdf | 14 Feb 2020 |
| Declaration in FORM BFile: notary.pdf | 14 Feb 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate for Residential layout.pdf | 14 Feb 2020 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Markandey Nagari | survey no. 232 mouza-Visapur Tah and Dist Gadchiroli | - | Completed | Dec 2020 | Dec 2020 |
| Markandey Apartment | plot no 12 survey no 880-2 visapur road Gadchiroli | 14 | Completed | Dec 2020 | Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 18 filed documents as one ZIP, foldered, with a manifest
Keep Residential Layout on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gadchiroli10 in Gadchiroli
Divya Gruha Residency
M/s Markhanday Developer and Builders
MARKANDEYA APARTMENT
M/S RAM BUILDERS AND DEVELOPERS
PRABHA KIRAN RESIDENCY
ANAND NAMDEORAO SHRUNGARPAWAR
RIYA TOWER
GULSAKKAR EKBAL MOTI
SHREE GANESH APARTMENT
PRABHAKAR AKHADE
RESIDENTIAL LAYOUT AT MAUZA - AMGAON, S. NO. -
KESHAO HARISHCHANDRA WARJURKAR
See every Gadchiroli project, with the district possession charts
Builder: M/S RAM BUILDERS AND DEVELOPERS
M/S RAM BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including MARKANDEYA APARTMENT and Residential Layout. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Gadchiroli district page.
Frequently asked questions
What are my rights if Residential Layout is delayed beyond 31 Dec 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Residential Layout?
The registered promoter entity is M/S RAM BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Residential Layout?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Residential Layout?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Residential Layout?
The professionals named in the filing: Architect: NAYAN KULLARWAR; Engineer: RAHUL RAMESH SUNKURWAR; Chartered Accountant: PD CHOPDA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Residential Layout?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback