New projects and RERA data in Gadchiroli district, Maharashtra
10 of the projects in this build are in Gadchiroli district: 58 units across them, 0 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 10 covered registrations, 0 have revised their promised completion date and 0 declare litigation. The median project here is 3% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
When Gadchiroli projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 10 projects with a promised date, 3 are recorded delivered, 2 are still on the register and 5 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
2 projects promise possession in 2026 or later. Facts as per filings on RERA website.
0 flats are promised in 2026 or later, across the 0% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.
How far Gadchiroli possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 0 of 10 projects (0%) have moved at least once; the median move is 0 months and the longest is 0 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Projects in Gadchiroli
| Project | Developer | Units | Booked | Registered |
|---|---|---|---|---|
| RESIDENTIAL LAYOUT AT MAUZA - AMGAON, S. NO. - 12 | KESHAO HARISHCHANDRA WARJURKAR | 34 | 6% | 9 Jan 2020 |
| Residential Layout | M/S RAM BUILDERS AND DEVELOPERS | 24 | 0% | 19 Jul 2020 |
| GALAXY APARTMENT | FRIENDS DEVELOPERS | - | - | 30 Nov 2017 |
| SHREE GANESH APARTMENT | PRABHAKAR AKHADE | - | - | 8 Feb 2018 |
| MARKANDEYA APARTMENT | M/S RAM BUILDERS AND DEVELOPERS | - | - | 9 Apr 2018 |
| ASHRAYSTHA AVENUE | ASHRAYSTHA INFRASTRUCTURES PRIVATE LIMITED | - | - | 2 Jan 2020 |
| RIYA TOWER | GULSAKKAR EKBAL MOTI | - | - | 18 Mar 2020 |
| Royal City | SAMSTITHIINFRASRUCTURES PRIVATE LIMITED | - | - | 29 Sep 2021 |
| PRABHA KIRAN RESIDENCY | ANAND NAMDEORAO SHRUNGARPAWAR | - | - | 16 Oct 2023 |
| Divya Gruha Residency | M/s Markhanday Developer and Builders | - | - | 6 May 2024 |
Developers active in Gadchiroli
M/S RAM BUILDERS AND DEVELOPERS (2), KESHAO HARISHCHANDRA WARJURKAR (1), FRIENDS DEVELOPERS (1), PRABHAKAR AKHADE (1), ASHRAYSTHA INFRASTRUCTURES PRIVATE LIMITED (1), GULSAKKAR EKBAL MOTI (1). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Gadchiroli projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 3% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Gadchiroli project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Gadchiroli district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Gadchiroli registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Gadchiroli project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Data from official MahaRERA filings.