ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Regency Landmark

Completed No litigation declared Commercial project

Regency Landmark

By Regency Reality Developers LLP

RG-MH-28675 · RERA P51700026921 · Last updated on MahaRERA portal: 6 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2024Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Excavation, 0%
1Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

Regency Landmark is a Commercial project by Regency Reality Developers LLP in Thane, Maharashtra, registered with MahaRERA as P51700026921 on 3 Nov 2020. The registration is recorded completed; possession was promised by 30 Apr 2024. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRegency Landmark
  • TypeCommercial
  • Location
    • New Link Road
    • Furniture Bazar
    • Ulhasnagar
    • Ulhasnagar (M Corp.)
    • Thane
    • 421003
  • Pincode421003
  • RERA no.P51700026921
  • ReraGenie IDRG-MH-28675

Builder

  • NameRegency Reality Developers LLP
  • Entity typePartnership
  • PartnersMahesh Satyanarayan Khairari, Subhash Satyanarayan Khairari, Ramkishore Satyanarayan Khairari, Dinesh Bherumal Bhojwani, Vicky Udhav Rupchandani, Anil Jessaram Bathija, Anilkumar Vijaykumar Tulsian, Dineshkumar Murlidhar Pasoria, Ram Jamiyatrai Talreja, Sahil Anil Bathija, Mokshay Pradeep Sadhwani

Key dates

this monthRegisteredNov 2020PromisedApr 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on3 Nov 2020
  • Promised completion30 Apr 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Regency Landmark - Building No 1NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Regency Landmark - Building No 1: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,293 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Mahesh Jaisingh SadhwaniUlhasnagar (M Corp.)Thane
Lal Jaisingh SadhwaniUlhasnagar (M Corp.)Thane

Approvals and building plan

Permissible FSI4294.5
Proposed, not sanctioned4,294 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Regency House, Opp Vishnu Darshan Building, Aman Talkies Road, Ulhasnagar 421002

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVitan Consultants
EngineerVishal Chandrakant Sawale
Chartered AccountantAjay Hassija & Associates
PartnerRole in project
Regency Reality Developers LLP-

Litigation declared1

CaseCourtStatus
76 /2016CIVIL JUDGE SENIOR DIVISION KALYANARGUEMENT STAGE

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000196568Hiralal Ghanshamdas KukrejaRegency Reality Developers LLP05/04/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Dec 2023

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Regency Reality Form 4.pdf6 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate (Basement and Ground Floor).PDF5 Dec 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FINAL OC 05-08-22.PDF5 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Regency Reality Developers LLP.pdf29 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 RERA AUDIT REGENCY REALITY DEVELOPERS LLP.PDF30 Jan 2023
Proforma of Allotment letterFile: Maya Lawns RERA Agreement for Upload.pdf28 Dec 2021
Proforma of Allotment letterFile: Allotment Ground Floor.pdf10 Nov 2021
Proforma of Allotment letterFile: Allotment First Floor.pdf10 Nov 2021
Layout approvalFile: LAYOUT COMPRESSED.pdf23 Oct 2020
Building plan approvalFile: LAYOUT COMPRESSED.pdf23 Oct 2020
Copy of Layout Approval (in case of layout)File: LAYOUT COMPRESSED.pdf23 Oct 2020
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT COMPRESSED.pdf23 Oct 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Regency Reality Developers RERA CA Certificate.pdf23 Oct 2020
Proforma of Allotment letterFile: AFS Declaration.PDF23 Oct 2020
Copy of the legal title reportFile: Title Certificate for CTS No 9458B, 9475B, 9478B.pdf21 Oct 2020
Copy of the legal title reportFile: Title Certificate for CTS No 9475C.pdf21 Oct 2020
Copy of the legal title reportFile: Title Certificate for CTS No 9476.pdf21 Oct 2020
Copy of the legal title reportFile: Title Certificate for CTS No 9477, 30672.pdf21 Oct 2020
Copy of the legal title reportFile: Title Certificate for CTS No 9478A, 9479B, 30673.pdf21 Oct 2020
Details of encumbrancesFile: no encumbarance.PDF21 Oct 2020
PAN CardFile: Regency Reality Developers LLP.PDF12 Oct 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf12 Oct 2020
Declaration in FORM BFile: affidavit compressed.pdf12 Oct 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Regency Landmark on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ulhasnagar7,600+ in Thane

Builder: Regency Reality Developers LLP

Regency Reality Developers LLP has 1 registration on MahaRERA, including Regency Landmark. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Regency Landmark is delayed beyond 30 Apr 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Regency Landmark?

The registered promoter entity is Regency Reality Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Regency Landmark?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Regency Landmark?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Regency Landmark?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Regency Landmark?

The professionals named in the filing: Architect: Vitan Consultants; Engineer: Vishal Chandrakant Sawale; Chartered Accountant: Ajay Hassija & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Regency Landmark?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Regency Landmark. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Regency Landmark to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.