ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / RATNA MOHAN TRIVENI CHSL

Completed No litigation declared Residential / Group Housing project

RATNA MOHAN TRIVENI CHSL

By ATUL CORPORATES

RG-MH-92453 · RERA P51800006783 · Last updated on MahaRERA portal: 6 Mar 2021

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Installation of Lifts, 95%
1Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

RATNA MOHAN TRIVENI CHSL is a Residential / Group Housing project by ATUL CORPORATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006783 on 16 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 36 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRATNA MOHAN TRIVENI CHSL
  • TypeResidential / Group Housing
  • Location
    • Dattapada Road
    • Rajendra Nagar
    • Magathane
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006783
  • ReraGenie IDRG-MH-92453

Builder

  • NameATUL CORPORATES
  • Entity typePartnership
  • PartnersHITEN TARUN MOTTA, BHAVYA RASHMIN SHAH, DEVESH TARUN MOTTA

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIVENINA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

TRIVENI: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises91%
Sanitary Fittings within the flats / premises91%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.83%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 6 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes18%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered1
Open Space29

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,445 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6862.76
Proposed, not sanctioned6,170 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLR, SHREE AMBA SHANTI CHAMBERS OPP HOTEL LEELA ANDHERI KURLA ROAD, ANDHERI EAST MUMBAI 400059

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTARUN MOTTA
EngineerHARESH PATEL
PartnerRole in project
ATUL CORPORATES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001002Dec 2018 → Dec 2019

Reason as filed by the promoterOur project is of Gr+Stilt+Podium+17 upper floors as registered in MAHARERA. We have been perusing for sanction of R.L. to existing road by MCGM from past 3 years. Due to which there is delay in project. We have uploaded supporting documents along. Our project is complete in all respect till 15 floors and we have applied for Part Occupation Certificate for Gr+Stilt+Podium+15 upper floors. We will give possession to all flat holders up to 15 Floors as soon as we get part OC. We haven’t sold any flat on 16th & 17th floor. We request you to extend date of possession of the entire project till 31s

EXT51800006105Dec 2018 → Jun 2021

Reason as filed by the promoterOur Project is of Gr+Stilt+podium+17th upper floors as registered in MAHARERA. Our project is completed in all respect till 15th floors and we have received part occupation certificate for Gr+Stilt+Podium+15 upper floors on January 2019. We have given possession to all flat holders with whom we have made registered sale agreements till date and also to the existing society members. All ground work and finishing work is also completed in all respect. We had been pursuing for sanction of R.L. to existing road from past 3 to 4 years. It was cleared by Road Dept. on 20th August 2019, copy of which

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000023720Bhupendra T PhondbaDevesh Tarun Motha01/04/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Mar 2021

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: society formation _opt_opt.pdf6 Mar 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC.pdf5 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Final CC_signed.pdf20 Nov 2019
Certificates of CA (Form 5)File: From 5.pdf14 Jan 2019
Certificates of Architect (Form 4)File: From 4.pdf12 Jan 2019
OtherFile: Part OC.pdf11 Jan 2019
OtherFile: CFO NOC 1.pdf11 Jan 2019
OtherFile: Amended Plan.pdf21 Dec 2018
OtherFile: Lift No1 A Wing.pdf21 Dec 2018
OtherFile: Lift No1 B Wing.pdf21 Dec 2018
OtherFile: Lift No 2 A Wing.pdf21 Dec 2018
OtherFile: Lift No 2 B Wing.pdf21 Dec 2018
OtherFile: Stability Certificate of Structure.pdf17 Dec 2018
OtherFile: Dainage Completion Certificate.pdf17 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Dec 2018
Building plan approvalFile: IOD.pdf31 Jul 2017
Layout approvalFile: IOD.pdf31 Jul 2017
PAN CardFile: pan.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE (1).pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: IOD.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C.pdf31 Jul 2017
Declaration in FORM BFile: fORM B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CIRTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: ca certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RATNA MOHAN TRIVENI CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rajendra Nagar, Magathane6,700+ in Mumbai Suburban

2 kmRATNA MOHAN TRIVENI CHSLCompleted 117Lapsed / revoked 72Other 179Dot size: filed unitsN

Filed coordinates, straight-line distance. 368 registered projects within 2 km.

Builder: ATUL CORPORATES

ATUL CORPORATES has 1 registration on MahaRERA, including RATNA MOHAN TRIVENI CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if RATNA MOHAN TRIVENI CHSL is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RATNA MOHAN TRIVENI CHSL?

The registered promoter entity is ATUL CORPORATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RATNA MOHAN TRIVENI CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RATNA MOHAN TRIVENI CHSL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RATNA MOHAN TRIVENI CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RATNA MOHAN TRIVENI CHSL?

The professionals named in the filing: Architect: TARUN MOTTA; Engineer: HARESH PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RATNA MOHAN TRIVENI CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RATNA MOHAN TRIVENI CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RATNA MOHAN TRIVENI CHSL to a free account