Home / Browse projects / Nanded, Maharashtra / Ramanuj A
Ramanuj A
RG-MH-51104 · RERA P51100077316 · Last updated on MahaRERA portal: 13 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Nanded registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Ramanuj A is a Residential / Group Housing project by Uttam Kishanrao Bacchewar in Nanded, Maharashtra, registered with MahaRERA as P51100077316 on 6 Aug 2024. Possession is promised by 31 Dec 2028.
At a glance
Project
- NameRamanuj A
- TypeResidential / Group Housing
- Location
- Wadi Bk
- Wadi Bk.
- Nanded
- 431602
- Pincode431602
- RERA no.P51100077316
- ReraGenie IDRG-MH-51104
Builder
- NameUttam Kishanrao Bacchewar
- Entity typeIndividual
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Aug 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings58 building records
- Documents filed88 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Row House No 01 on Plot No 08 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 02 on Plot No 09 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 03 on Plot No 10 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 04 on Plot No 11 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 05 on Plot No 201 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 06 on Plot No 202 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 07 on Plot No 203 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 08 on Plot No 204 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 09 on Plot No 205 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 10 on Plot no 206 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House no 11 on Plot no 207 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 12 on Plot No 208 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 13 on Plot No 243 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 14 on Plot No 243 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 15 on Plot No 244 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 16 on Plot No 244 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 17 on Plot No 245 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 18 on Plot No 245 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 19 on Plot No 246 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 20 on Plot No 246 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 21 on Plot No 249 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 22 on Plot No 249 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 23 on Plot No 247 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 24 on Plot No 247 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 25 on Plot No 248 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 26 on Plot No 248 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 27 on Plot No 242 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 28 on Plot No 242 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 29 on Plot No 179 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 30 on Plot No 179 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 31 on Plot No 231 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 32 on Plot No 232 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 33 on Plot No 198 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 34 on Plot No 199 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 35 on Plot No 180 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 36 on Plot No 181 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 37 on Plot No 182 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House no 38 on Plot no 183 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 39 on Plot no 184 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 40 on Plot No 185 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 41 on Plot No 186 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 42 on Plot No 187 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 43 on Plot No 188 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 44 on Plot No 189 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 45 on Plot No 192 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 46 on Plot No 193 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 47 on Plot No 194 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 48 on Plot No 195 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 49 on Plot No 196 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 50 on Plot no 197 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 51 on Plot No 233 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 52 on Plot No 234 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 53 on Plot No 235 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 54 on Plot No 236 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 55 on Plot No 237 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 56 on Plot No 238 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 57 on Plot No 239 | NA | 1 | 0 | 0 | 0 | 0 |
| Row House No 58 on Plot No 240 | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 58 buildings; the table lists the first 20.
327 of 638 construction stages are filed complete across 58 buildings. The stage furthest along is Internal walls, at 50%.
Row House No 01 on Plot No 0882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Row House No 02 on Plot No 0982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Row House No 03 on Plot No 1082%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Row House No 04 on Plot No 1182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Row House No 05 on Plot No 20164%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 06 on Plot No 20247%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 07 on Plot No 20364%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 08 on Plot No 20464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 09 on Plot No 20564%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 10 on Plot no 20647%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House no 11 on Plot no 20764%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 12 on Plot No 20847%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 13 on Plot No 24364%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 14 on Plot No 24364%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 15 on Plot No 24464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 16 on Plot No 24447%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 17 on Plot No 24564%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 18 on Plot No 24547%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 19 on Plot No 24664%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row House No 20 on Plot No 24664%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ravi Kadge |
| Engineer | Ravi Kadge |
| Chartered Accountant | CA Shailesh Partani |
| Partner | Role in project |
|---|---|
| Uttam Kishanrao Bacchewar | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Feb 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM1_11zon.pdf | 13 Jul 2026 |
| Form 2File: FORM2.pdf | 13 Jul 2026 |
| Form 3File: FORM3_11zon.pdf | 13 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SS Sold INV.pdf | 13 Jul 2026 |
| Form 1File: Architects Certificate 1_11zon.pdf | 9 Apr 2026 |
| Form 2File: Engineers Certificate SS 1 (1)_11zon.pdf | 9 Apr 2026 |
| Form 3File: CA Certificate 1 (1)_11zon.pdf | 9 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory March 26 1.pdf | 9 Apr 2026 |
| Form 1File: Form 1.pdf | 3 Jan 2026 |
| Form 2File: Form 2.pdf | 3 Jan 2026 |
| Form 3File: Form 3.pdf | 3 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: inventory 316.pdf | 3 Jan 2026 |
| Form 1File: Architects Certificate.pdf | 10 Oct 2025 |
| Form 2File: Engineers Certificate SS.pdf | 10 Oct 2025 |
| Form 3File: CA Certificate.pdf | 10 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory.pdf | 10 Oct 2025 |
| Form 1File: Form 1.pdf | 11 Jul 2025 |
| Form 2File: Form 2.pdf | 11 Jul 2025 |
| Form 3File: Form 3.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory.pdf | 11 Jul 2025 |
| Form 1File: Form 1.pdf | 11 Jul 2025 |
| Form 2File: Form 2.pdf | 11 Jul 2025 |
| Form 3File: Form 3.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory.pdf | 11 Jul 2025 |
| Form 1File: Form 1.pdf | 11 Jul 2025 |
| Form 2File: Form 2.pdf | 11 Jul 2025 |
| Form 3File: Form 3.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory.pdf | 11 Jul 2025 |
| Form 1File: Form 1.pdf | 11 Jul 2025 |
| Form 2File: Form 2.pdf | 11 Jul 2025 |
| Form 3File: Form 3.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SS Sold Book Inventory.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: SS Sold Book Inventory.pdf | 4 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect SS_11zon.pdf | 3 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate SS_11zon.pdf | 3 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI SS.pdf | 3 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate S S 12-12-24.pdf | 4 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Ramanuj - 12-12-24.pdf | 4 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate12-12-24.pdf | 4 Feb 2025 |
| Other - TechnicalFile: Ramanuj Society Letter.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Certi 09-09-24.pdf | 8 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH SS 10-10-24.pdf | 8 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Ramanuj SS_09-09-2024.pdf | 8 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A SS 10-10-24.pdf | 8 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate SS 09-09-24.pdf | 8 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI SS 10-10-24.pdf | 8 Nov 2024 |
| Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (31) (1) (1).pdf | 2 Aug 2024 |
| Other - TechnicalFile: ilovepdf_merged (55).pdf | 8 Jul 2024 |
| Other - FinanceFile: ilovepdf_merged (53).pdf | 21 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Sarla sangi mail.pdf | 9 May 2024 |
| Other - TechnicalFile: ilovepdf_merged (50).pdf | 9 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 3 Commencement Certificates _ NA Order for plotted development (6).pdf | 10 Apr 2024 |
| CERSAI detailsFile: CERSAI Declaration Ramanuj A.pdf | 13 Mar 2024 |
| Other - TechnicalFile: RERA LETTER.pdf | 13 Mar 2024 |
| Copy of the legal title reportFile: 1 Copy of the legal title report.pdf | 20 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 38 permission-1.pdf | 15 Feb 2024 |
| Other - TechnicalFile: Declaration of Non Registration Layout Project Ramanuj A2.pdf | 8 Feb 2024 |
| Declaration in FORM BFile: Ramanuj A.pdf | 7 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 222_0001 (1).pdf | 7 Feb 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200296065795_For_Asset_Based_Search_07_02_2024_12_55_27_178.pdf | 7 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ramanuj A (1)_organized (1)_compressed.pdf | 7 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Real Estate Projects Ramanuj A.pdf | 7 Feb 2024 |
| Other - LegalFile: Name Mismatch.pdf | 7 Feb 2024 |
| Other - LegalFile: S28C-2240130130500_organized_compressed.pdf | 7 Feb 2024 |
| Other - TechnicalFile: Name Mismatch Tech.pdf | 7 Feb 2024 |
| Other - TechnicalFile: S28C-2240130130500_organized_compressed.pdf | 7 Feb 2024 |
| Layout approvalFile: 1_compressed (2).pdf | 6 Feb 2024 |
| Building plan approvalFile: 1_compressed (2).pdf | 6 Feb 2024 |
| Building plan approvalFile: 2_compressed.pdf | 6 Feb 2024 |
| Building plan approvalFile: 3_compressed (1).pdf | 6 Feb 2024 |
| Building plan approvalFile: 4_compressed.pdf | 6 Feb 2024 |
| Building plan approvalFile: 5_compressed.pdf | 6 Feb 2024 |
| PAN CardFile: 1 PAN Card (12).pdf | 6 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Declaration Finance Ramanuj A.pdf | 6 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Declaration Legal Ramanuj A.pdf | 6 Feb 2024 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Declaration Finance Ramanuj A.pdf | 6 Feb 2024 |
| Details of encumbrances concerned to LegalFile: No Encumbrance Declaration Legal Ramanuj A.pdf | 6 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: 1_compressed (2).pdf | 6 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_compressed (2).pdf | 6 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf | 6 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nanded
Computed across the 100+ Nanded projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Ramanuj A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Wadi Bk100+ in Nanded
Jinen Square
Jinen Infra
SAKET HEIGHTS
SAKET HEIGHTS
GOKULDHAM CITY PART A
RAMA DEVELOPERS
Lotus Heights
M. M. DEVELOPERS
ANUSAYA HEIGHTS
ANUSAYA HEIGHTS
BHARADIYA TOWER
RAJ ASSOCIATES
See every Nanded project, with the district possession charts
Builder: Uttam Kishanrao Bacchewar
Uttam Kishanrao Bacchewar has 2 registrations on MahaRERA, including Ramanuj A and Ramanuj A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nanded district page.
Frequently asked questions
What are my rights if Ramanuj A is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Ramanuj A?
The registered promoter entity is Uttam Kishanrao Bacchewar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Ramanuj A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Ramanuj A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Ramanuj A?
The professionals named in the filing: Architect: Ravi Kadge; Engineer: Ravi Kadge; Chartered Accountant: CA Shailesh Partani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ramanuj A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback