ReraGenieLog inGet a buyer report

Home / Browse projects / Nanded, Maharashtra / GOKULDHAM CITY PART A

Registered No litigation declared Residential / Group Housing project

GOKULDHAM CITY PART A

By RAMA DEVELOPERS

RG-MH-08534 · RERA P51100020534 · Last updated on MahaRERA portal: 18 Jul 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Nanded registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
270 of 385Construction stages doneacross 35 buildings; furthest along: Internal walls, 50%
0 of 35Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

GOKULDHAM CITY PART A is a Residential / Group Housing project by RAMA DEVELOPERS in Nanded, Maharashtra, registered with MahaRERA as P51100020534 on 18 Apr 2019. Possession is promised by 30 Dec 2030. 35 of the 35 units on this registration are recorded sold or booked, and 270 of 385 construction stages are filed complete.

At a glance

Project

  • NameGOKULDHAM CITY PART A
  • TypeResidential / Group Housing
  • Location
    • KAUTHA
    • NEAR RAVI NAGAR
    • Nanded Waghala (M Corp.)
    • Nanded
    • 431602
  • Pincode431602
  • RERA no.P51100020534
  • ReraGenie IDRG-MH-08534

Builder

  • NameRAMA DEVELOPERS
  • Entity typeOthers
  • Named personsNANDLAL MUNNALAL BHAGAT, DURGADAS MUNNALAL BHAGAT
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2019PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Apr 2019
  • Promised completion30 Dec 2030
  • Revised completionNone
  • Buildings35 building records
  • Documents filed71 files

Current status

100%35 of 35 units booked

Figures as on 18 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSE AN 1NA22101
ROW HOUSE BN 2NA22101
ROW HOUSE BN 3NA22101
ROW HOUSE BN 4NA22101
ROW HOUSE BN 5NA22101
ROW HOUSE CW 6NA22101
ROW HOUSE DW 7NA22101
ROW HOUSE DW 8NA22101
ROW HOUSE DW 9NA22101
ROW HOUSE DW 10NA22101
ROW HOUSE DW 11NA22101
ROW HOUSE DW 12NA22101
ROW HOUSE DW 13NA22101
ROW HOUSE EW 14NA22101
ROW HOUSE FW 15NA22101
ROW HOUSE GE 34NA22101
ROW HOUSE HE 35NA22101
ROW HOUSE IE 36NA22101
ROW HOUSE IE 37NA22101
ROW HOUSE IE 38NA22101
ROW HOUSE IE 39NA22101
ROW HOUSE IE 40NA22101
ROW HOUSE IE 41NA22101
ROW HOUSE IE 42NA22101
ROW HOUSE JE 43NA22101
ROW HOUSE KW 44NA22101
ROW HOUSE LW 45NA22101
ROW HOUSE LW 46NA22101
ROW HOUSE LW 47NA22101
ROW HOUSE LW 48NA22101
ROW HOUSE MW 49NA22101
ROW HOUSE MW 50NA22101
ROW HOUSE MW 51NA22101
ROW HOUSE NW 52NA22101
ROW HOUSE OW 53NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 18 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 35 buildings; the table lists the first 20.

270 of 385 construction stages are filed complete across 35 buildings. The stage furthest along is Internal walls, at 50%.

ROW HOUSE AN 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE BN 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE BN 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE BN 491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE BN 591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE CW 657%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
ROW HOUSE DW 791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE DW 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE DW 991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE DW 1057%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
ROW HOUSE DW 1191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE DW 1291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE DW 1391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE EW 1447%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
ROW HOUSE FW 1547%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
ROW HOUSE GE 3447%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
ROW HOUSE HE 3554%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
ROW HOUSE IE 3691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE IE 3791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE IE 3891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes20%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered2
Open Space2
BuildingClosed/CoveredOpen SpaceTotal
ROW HOUSE AN 1101
ROW HOUSE BN 2101
ROW HOUSE IE 41011
ROW HOUSE MW 50011

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,189 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Sep 2025
LandownerVillageDistrict
CHAITNYA GANESH FARKANDENanded Waghala (M Corp.)Nanded
NANDLAL MUNNALAL BHAGATNanded Waghala (M Corp.)Nanded
DURGADAS MUNNALAL BHAGATNanded Waghala (M Corp.)Nanded

Approvals and building plan

Sanctioning authorityNnaded Waghala City Muncipalty
Permissible FSI3356.25
Proposed, not sanctioned3,356 sq m
Buildings approved35
Buildings sanctioned35

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSANT KRIPA MARKET G G ROAD NANDED

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHIRISH PUROHIT
EngineerCHAITANYA FARKANDE
Chartered AccountantSHAILESH PARTANI
PartnerRole in project
RAMA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Jun 2024

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q4 FY 24-25.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q1 FY 25-26.pdf18 Jul 2025
Certificates of CA (Form 3)File: New Form 3 Format gokuldham city A Q-4 24-25.pdf18 Jul 2025
Certificates of CA (Form 3)File: New Form 3 Format gokuldham city A Q-4 24-25.pdf18 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer cetificate Q4 Part A 24-25.pdf18 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer cetificate Q1 Part A 25-26.pdf18 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q4 24-25.pdf18 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q1 25-26.pdf18 Jul 2025
Certificates of CA (Form 3)File: CA FORM 3 PART A.pdf21 Jan 2025
Certificates of CA (Form 3)File: Annexure D Form 3 Part A_compressed.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City B Q2.pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q2 FY 24-25.pdf16 Dec 2024
Certificates of CA (Form 3)File: New Form 3 Format gokuldham city A.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer cetificate Q2 Part A 24-25.pdf16 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: format A Part A.pdf16 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 part FY 22 23.pdf16 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23 24.pdf16 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Gokuldham City Part A Format A.pdf13 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Gokuldham City Part A Format B (3).pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate Par A.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A Part A.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Par A.pdf3 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Part A.pdf3 Aug 2024
Certificates of CA (Form 3)File: Form 3 Chartered accountants certificate Par A_compressed.pdf3 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form - 2A - Engineer's Certificate (Quality Assurance) Gokuldham City A Q4 23-24.pdf18 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Part A Q4-23-24.pdf14 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Q4 23-24.pdf14 Jun 2024
Certificates of CA (Form 3)File: Form 3 Q4 23-24_compressed.pdf14 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 5-5_compressed.pdf14 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q3 23-24.pdf12 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q2 23-24.pdf28 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A Q2 23-24.pdf28 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Egineer cetificate Q2 Part A 23-24.pdf28 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Egineer cetificate Q3 Part A 23-24.pdf28 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Engineer's Certificate (Quality Assurance) Q2 A.pdf28 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Engineer's Certificate (Quality Assurance) Q3 A.pdf28 Apr 2024
Certificates of CA (Form 3)File: New Form 3 Format gokuldham city A Q2- 23-24_compressed.pdf28 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Certificate Gokuldham City A.pdf22 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer cetificate Q1 Part A 23-24.pdf22 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Engineer's Certificate (Quality Assurance) Q4 Part-A.pdf22 Jul 2023
Certificates of CA (Form 3)File: New Form 3 Format gokuldham city A_compressed.pdf22 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CIRTIFICATE PART-A.pdf19 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CIRTIFICATE PART-A.pdf19 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A PART-A.pdf19 May 2023
Certificates of CA (Form 3)File: CA CIRTIFICATE PART-A_compressed.pdf19 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final OC Cover Letter Gokuldham City_0001.pdf19 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gokuldham_City_Form_-_1_Architect;s_Certificate[1].pdf18 Feb 2023
Certificates of CA (Form 3)File: Form 3_0001_compressed.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Gokuldham City Part A , Form 1.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Gokuldham City Part A Engg.pdf10 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Gokuldham City Part A , Form 2A.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf10 Feb 2023
Copy of the legal title reportFile: Kautha Search Report.pdf12 Apr 2019
Proforma of Allotment letterFile: विक्री करारनामा.pdf11 Apr 2019
Building plan approvalFile: 3-3.pdf9 Apr 2019
Building plan approvalFile: 2-3.pdf9 Apr 2019
Building plan approvalFile: 1-3.pdf9 Apr 2019
Layout approvalFile: lay out map.pdf9 Apr 2019
PAN CardFile: chaitnya pan card.pdf9 Apr 2019
PAN CardFile: PAN CARD NANDLALJI AND DURGADASJI.pdf9 Apr 2019
Details of encumbrancesFile: Declaration.pdf9 Apr 2019
Copy of Layout Approval (in case of layout)File: lay out map.pdf9 Apr 2019
Building Plan Approval (IOD)File: 3-3.pdf9 Apr 2019
Building Plan Approval (IOD)File: 2-3.pdf9 Apr 2019
Building Plan Approval (IOD)File: 1-3.pdf9 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Bild Permission.pdf9 Apr 2019
Declaration in FORM BFile: Form B.pdf9 Apr 2019
Certificates of CA (Form 3)File: CA Certificate.pdf9 Apr 2019
Certificates of CA (Form 5)File: CA Certificate.pdf9 Apr 2019

How this compares with Nanded

100%of this project is bookeddistrict median 6%
3%of Nanded projects moved their completion datethis one has not
25%of Nanded registrations have lapsed or been cancelledthis one is on the register

Computed across the 100+ Nanded projects on ReraGenie, from their own filings.

Keep GOKULDHAM CITY PART A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR RAVI NAGAR100+ in Nanded

Builder: RAMA DEVELOPERS

RAMA DEVELOPERS has 2 registrations on MahaRERA, including GOKULDHAM CITY PART A and GOKULDHAM CITY PART B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nanded district page.

Frequently asked questions

What are my rights if GOKULDHAM CITY PART A is delayed beyond 30 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GOKULDHAM CITY PART A?

The registered promoter entity is RAMA DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GOKULDHAM CITY PART A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GOKULDHAM CITY PART A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GOKULDHAM CITY PART A?

The professionals named in the filing: Architect: SHIRISH PUROHIT; Engineer: CHAITANYA FARKANDE; Chartered Accountant: SHAILESH PARTANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOKULDHAM CITY PART A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOKULDHAM CITY PART A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOKULDHAM CITY PART A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.