RAJEBAHADUR SHOPPING COMPLEX
RG-MH-13704 · RERA P51600027647 · Last updated on MahaRERA portal: 2 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 49 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJEBAHADUR SHOPPING COMPLEX is a Commercial project by SHREE SITA DEVELOPER in Nashik, Maharashtra, registered with MahaRERA as P51600027647 on 25 Dec 2020. Possession is promised by 31 Jul 2027. The completion date has moved by 49 months from the original filing. 41 of the 110 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameRAJEBAHADUR SHOPPING COMPLEX
- TypeCommercial
- Location
- NEAR TO OLD MUNICIPAL CORPORATION
- MAIN ROAD
- Nashik (M Corp.)
- Nashik
- 422001
- Pincode422001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600027647
- ReraGenie IDRG-MH-13704
Builder
- NameSHREE SITA DEVELOPER
- Entity typePartnership
- GSTIN27ABYFS8058H1Z8
- PartnersBHARAT KANJI SHAH, LALIT BHANUBHAI KAMANI, PREMJI BHURALAL GALA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Dec 2020
- Promised completion31 Jul 2027
- Revised completionRevised to 31 Jul 2027 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed218 files
Current status
Figures as on 2 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJEBAHADUR SHOPPING COMPLEX | NA | 5 | 4 | 0 | 110 | 110 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
RAJEBAHADUR SHOPPING COMPLEX: 85% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 2 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed42
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RAJEBAHADUR SHOPPING COMPLEX | NA | Rs 16.00 cr | Rs 11.85 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR PANKAJ JADHAV JADHAV |
| Engineer | MR SANJEEV M PATEL |
| Engineer | Amol Y Bhalerao |
| Engineer | Sanjeev M Patel |
| Chartered Accountant | CA VARDHAMAN S BHANDARI |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | P N Sabadra and Associates |
| Partner | Role in project |
|---|---|
| SHREE SITA DEVELOPER | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promotera) The said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still facing aftermath of COVID Pandemic. Though there is progress in construction of project, the project has got delayed due to COVID-19 Pandemic, the losses/cost overrun and the financial and liquidity problems resulted from delay due to the said Pandemic. Further, due to lockdowns and long COVID-19 Pandemic, we suffered by way of losing our manpower/employees resulting in difficulties in making compliance under MahaRERA.b) We have obtained part occupancy certificate
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC001000000110468 | Mahesh Parmar | Shree Sita Developers | 16/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2027
Documents filed218
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 218 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A March 2026.pdf | 2 Sep 2026 |
| Form 2A (FY 2024-2025)File: Form 2A March 2025.pdf | 2 Sep 2026 |
| Form 5 (FY 2024-2025)File: 1RERA Audit Report-FY24-25.pdf | 2 Sep 2026 |
| Form 1File: AR March 25.pdf | 1 Sep 2026 |
| Form 2File: ER March 25.pdf | 1 Sep 2026 |
| Form 3File: CA March 25.pdf | 1 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - march 25 .pdf | 1 Sep 2026 |
| Form 1File: AR Certificate June 24.pdf | 1 Sep 2026 |
| Form 2File: ER Certificate June 24.pdf | 1 Sep 2026 |
| Form 3File: CA-June 24_Final(1).pdf | 1 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure-June 24.pdf | 1 Sep 2026 |
| Form 1File: AR- Sep 24 .pdf | 1 Sep 2026 |
| Form 2File: ER_Sep 24.pdf | 1 Sep 2026 |
| Form 3File: CA-Sep-24-Final.pdf | 1 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Sep 24 .pdf | 1 Sep 2026 |
| Form 1File: AR certificate Dec 24.pdf | 1 Sep 2026 |
| Form 2File: ER certficate - Dec 24.pdf | 1 Sep 2026 |
| Form 3File: CA-DEC-24-Final.pdf | 1 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 24 .pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: AR june 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: AR june 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: AR - Sep 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: AR - Dec 25 .pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE March 2026.pdf | 1 Sep 2026 |
| Withdrawal Update Form 1File: AR - June 26-Final.pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: ER june 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: ER june 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: ER - Sep 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: ER - Dec 25 .pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate March 2026.pdf | 1 Sep 2026 |
| Withdrawal Update Form 2File: ER - June 26 -Final.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificare Final.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA June 25 final.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA Cert_Shri Sita_ Sept 25-.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA - Dec 25.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate March 26.pdf | 1 Sep 2026 |
| Withdrawal Update Form 3File: CA Cert_Shri Sita-June-26 pdf-Final 2.pdf | 1 Sep 2026 |
| Form 1File: AR - Dec 23.pdf | 31 Aug 2026 |
| Form 2File: ER - Dec 23.pdf | 31 Aug 2026 |
| Form 3File: CA Cert_Shri Sita_Dec-23.pdf | 31 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 23.pdf | 31 Aug 2026 |
| Form 1File: AR - March 24.pdf | 31 Aug 2026 |
| Form 2File: ER - March 24.pdf | 31 Aug 2026 |
| Form 3File: CA Cert_Shri Sita_March-24.pdf | 31 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure- March 24.pdf | 31 Aug 2026 |
| Form 2A (FY 2020-2021)File: Form-2A March 21.pdf | 20 Jul 2026 |
| Form 2A (FY 2021-2022)File: Form-2A March 22.pdf | 20 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form-2A March 23.pdf | 20 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form-2A March 24.pdf | 20 Jul 2026 |
| Form 1File: 1 shri sita developer AR March 2021.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER Mar 2021.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA March 2021.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - March 2021.pdf | 4 Jul 2026 |
| Form 1File: shri sita developer AR March 2022.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER Mar 2022.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA March 2022.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - March 2022.pdf | 4 Jul 2026 |
| Form 1File: shri sita developer AR June 2022.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER June 2022.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA June 2022.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - June 2022.pdf | 4 Jul 2026 |
| Form 1File: shri sita developer AR Sep 2022.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER Sep 2022.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA Sep 2022.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - SEP 2022.pdf | 4 Jul 2026 |
| Form 1File: shri sita developer AR Dec 2022.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER Dec 2022.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA Dec 2022.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - Dec 2022.pdf | 4 Jul 2026 |
| Form 1File: shri sita developer AR March 23.pdf | 4 Jul 2026 |
| Form 2File: shri sita developer ER Mar 2023.pdf | 4 Jul 2026 |
| Form 3File: shri sita developer CA March 2023.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - March 2023.pdf | 4 Jul 2026 |
| Form 1File: AR Certificate June 23.pdf | 4 Jul 2026 |
| Form 2File: ER - June 23.pdf | 4 Jul 2026 |
| Form 3File: 1 CA Cert_Shri Sita_June-23.pdf | 4 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Shri Sita Developer - June 2023.pdf | 4 Jul 2026 |
| Form 1File: AR.pdf | 4 Jul 2026 |
| Form 2File: ER.pdf | 4 Jul 2026 |
| Form 3File: CA.pdf | 4 Jul 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 218 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep RAJEBAHADUR SHOPPING COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAIN ROAD4,100+ in Nashik
Filed coordinates, straight-line distance. 249 registered projects within 2 km.
LOTUS CAPITAL
BORA REALTY LLP
SHREE KALIKA PLAZA
DEEPAK KALYANJI CHANDE
Shreeji Celestia
SHREEJI LIFE SPACE
BUSINESS PLUS
MANGO ESTTATE
Iconic Business Center Dwarka
BAGAD PROPERTIES
NAKSHTRA AVENUE
SHYAM DEVELOPERS
See every Nashik project, with the district possession charts
Builder: SHREE SITA DEVELOPER
SHREE SITA DEVELOPER has 1 registration on MahaRERA, including RAJEBAHADUR SHOPPING COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if RAJEBAHADUR SHOPPING COMPLEX is delayed beyond 31 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJEBAHADUR SHOPPING COMPLEX?
The registered promoter entity is SHREE SITA DEVELOPER, a partnership as per the filing. Its GSTIN 27ABYFS8058H1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJEBAHADUR SHOPPING COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RAJEBAHADUR SHOPPING COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RAJEBAHADUR SHOPPING COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAJEBAHADUR SHOPPING COMPLEX?
The professionals named in the filing: Architect: AR PANKAJ JADHAV JADHAV; Engineer: MR SANJEEV M PATEL; Engineer: Amol Y Bhalerao; Engineer: Sanjeev M Patel; Chartered Accountant: CA VARDHAMAN S BHANDARI; Chartered Accountant: RSPH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJEBAHADUR SHOPPING COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback