ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / RADIANCE

Registered No litigation declared Residential / Group Housing project

RADIANCE

By Mohammed Sabir Husain Shaikh

RG-MH-96726 · RERA P52100047482 · Last updated on MahaRERA portal: 17 Oct 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

RADIANCE is a Residential / Group Housing project by Mohammed Sabir Husain Shaikh in Pune, Maharashtra, registered with MahaRERA as P52100047482 on 2 Nov 2022. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameRADIANCE
  • TypeResidential / Group Housing
  • Location
    • CTS No 315-316 at Mahatma Phule Peth
    • PUNE
    • Haveli
    • 411042
  • Pincode411042
  • RERA no.P52100047482
  • ReraGenie IDRG-MH-96726

Builder

  • NameMohammed Sabir Husain Shaikh
  • Entity typeIndividual

Key dates

this monthRegisteredNov 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Nov 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RADIANCENA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

RADIANCE: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area610 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
Mohammed Sabir Husain ShaikhPethPune
SUNIL SHANKAR JANAPune (M Corp.)Pune
SHAKUNTALA RAMAKRISHNA JANAPune (M Corp.)Pune
RAJU SHANKAR JANAPune (M Corp.)Pune
BALKRISHNA NARAD JANAPune (M Corp.)Pune
RAMESH JAGANATH JANAPune (M Corp.)Pune
NARENDRA S JANAPune (M Corp.)Pune
RAHUL TUKARAM JANAPune (M Corp.)Pune

Approvals and building plan

Permissible FSI609.59
Proposed, not sanctioned484 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCAMP PUNE-411001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHIL SHAIKH
EngineerRAHIL SHAIKH
Chartered AccountantIMRAN MEMON
PartnerRole in project
Mohammed Sabir Husain Shaikh-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FORM-B-NOTARIZED.pdf17 Oct 2022
Other - TechnicalFile: FORM-B-NOTARIZED.pdf17 Oct 2022
Proforma of Agreement for saleFile: Letter of allotment-F.pdf17 Sep 2022
Proforma of Allotment letterFile: Letter of allotment-F.pdf17 Sep 2022
Other - LegalFile: Development agreement.pdf17 Sep 2022
Proforma of Allotment letterFile: ANNEXURE-A (1) (1)-F.pdf16 Sep 2022
Proforma of Agreement for saleFile: ANNEXURE-A (1) (1)-F.pdf16 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Final-New.pdf6 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Agreement for sale.pdf6 Sep 2022
Deviation Report with respect to Allotment letterFile: Declaration for Deviation report.pdf27 Aug 2022
Copy of the legal title reportFile: Search Report-New.pdf18 Aug 2022
Layout approvalFile: Statement of Layout.pdf30 Jul 2022
Building plan approvalFile: PLAN_compressed.pdf30 Jul 2022
PAN CardFile: PAN-ADHAR.pdf30 Jul 2022
Details of encumbrances concerned to FinanceFile: Details of encumbrances-F.pdf30 Jul 2022
Details of encumbrances concerned to LegalFile: Details of encumbrances-F.pdf30 Jul 2022
Copy of Layout Approval (in case of layout)File: Statement of Layout.pdf30 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed.pdf30 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Jul 2022
Declaration about Commencement CertificateFile: Declaration for Commencement certificate.pdf30 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200243441412_For_Asset_Based_Search_29_07_2022_11_05_35_999.pdf30 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Separate account.pdf30 Jul 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RADIANCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

Builder: Mohammed Sabir Husain Shaikh

Mohammed Sabir Husain Shaikh has 1 registration on MahaRERA, including RADIANCE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if RADIANCE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RADIANCE?

The registered promoter entity is Mohammed Sabir Husain Shaikh, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RADIANCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RADIANCE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RADIANCE?

The professionals named in the filing: Architect: RAHIL SHAIKH; Engineer: RAHIL SHAIKH; Chartered Accountant: IMRAN MEMON. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADIANCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADIANCE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADIANCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.