Home / Browse projects / Bengaluru Urban, Karnataka / RADIANCE FLORESTA

Registration approved No litigation declared Residential/Group Housing project

RADIANCE FLORESTA

By RADIANCE REALTY DEVELOPERS INDIA LIMITED

RG-KA-77207 · RERA PRM/KA/RERA/1251/446/PR/060424/006781 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2028Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
0 of 65Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 141 documents Report an error

RADIANCE FLORESTA is a Residential/Group Housing project by RADIANCE REALTY DEVELOPERS INDIA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/060424/006781 on 6 Apr 2024. Possession is promised by 31 May 2028. 65 of the 65 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameRADIANCE FLORESTA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 562149
  • Pincode562149
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/060424/006781
  • ReraGenie IDRG-KA-77207

Builder

  • NameRADIANCE REALTY DEVELOPERS INDIA LIMITED
  • Entity typeCompany
  • CINU45201TN2007PLC062662
  • GSTIN29AACCN5152H1ZE
  • Authorized SignatoryR VINAYAGAMURTHY
  • Managing DirectorVARUN MANIAN
  • DirectorsVARUN MANIAN, G PANCHAPAGESAN, JOE BENJAMIN F, SNEHA G BHAT, TANVI ANAND
  • Project HeadR VINAYAGAMURTHY
  • Other registrations5 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredApr 2024PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Apr 2024
  • Promised completion31 May 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed141 files

Current status

100%65 of 65 units booked
8.1%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---30030
BLOCK B---30030
BLOCK C---505

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationNoNot applicable
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes99%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes99%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes99%
Swimming PoolYes99%
GymYes99%
ParksNoNot applicable
Power BackupYes99%
Piped GasNoNot applicable
Water and SanitationYes99%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,411 sq m
Named landowners1
LandownerVillageDistrict
LEELA KANUNGA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 59.53 cr
Cost incurredRs 4.82 cr
Spent of the estimate8.09%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 54.71 crRs 4.16 cr
INTREST ON BORROWINGSRs 4.82 cr-
On-site expenditure-Site Overhead-Rs 65.84 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmernath A
EngineerJegatheesan P
Chartered AccountantS.NARASIMAN

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed141

As listed on the registration, under the names the promoter filed them with; the newest 80 of 141 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/060424/006781 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Sep 26.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Sep 26.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Sep 26.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU June 26.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU March 26.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU Dec 25.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
Reply to QueryFile: Reply to Query.pdf2 Apr 2024
RTC, survey 57/2-
Mutation, survey 57/2-
Encumbrance Certificate, survey 57/2-
Conversion/Alienation Order, survey 57/2-
JDA, survey 57/2-
Khatha, survey 57/2-
Registration CertificateFile: certificate of incorporation.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect certi.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: BS with Schedule 2022-23.pdf-
Balance Sheet 2021 - 2022File: BS with Schedules 2021-22.pdf-
Balance Sheet 2020 - 2021File: BS wirh Schedules 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2020-21.pdf-
Director's Report 2022 - 2023File: Directors Report 2022-23.pdf-
Director's Report 2021 - 2022File: Directors Report 2021-22.pdf-
Director's Report 2020 - 2021File: Directors Report 2020-21.pdf-
Cash Flow Statement 2022 - 2023File: Cash flow 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Cashflow 2021-22.pdf-
Auditor's Report 2022 - 2023File: Audoitors Report 2022-23.pdf-
Auditor's Report 2021 - 2022File: Auditors Report 2021-22.pdf-
Auditor's Report 2020 - 2021File: Auditors Report 2020-21.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021-22.pdf-
Approved Letter-
BESCOM Noc with Fee Receipt-
Water Noc-
Approved Building Plan-
Sectional Plan and Specification-
Sectional Drawing-
Project Specification-
Section & Elevation-
Structural Stability Certificate-
Legal Report-
JDA _ Radiance-
Master Plan-
Conversion Orders-
Title Deed_Radiance - 2 Acres-
Proforma of AOS-
proforma of Allotment Letter-
Form B Affidavit-
Section 3 1 Affidavit-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 under way, not due yet1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
RADIANCE GARDENIASY NO 48/1, 48/2, 49/1, 49/2 & 50/2, Chikkagubbi Villege, Bidarahalli Hobli, Bengaluru East Taluk, BengaluruOngoingDec 2027Not due yet
RADIANCE BLOSSOM PHASE- IIRadiance Realty Developers India Limited, 167/1A,167/1B,167/1C & 128/P10, , Village Mandur,Taluka Bangalore East, , Village Mandur,Taluka Bangalore East , HOSKOTEOngoingDec 2024Not delivered
RADIANCE BLOSSOMSY NO’S. 167/2,168/1A, 168/1B, 168/1C, 168/2. MANDUR VILLAGE, BIDARAHALLI HOBLI, BANGALORE EAST TALUKCompleted-No date filed

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep RADIANCE FLORESTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmRADIANCE FLORESTAOther 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 33 registered projects within 2 km.

Builder: RADIANCE REALTY DEVELOPERS INDIA LIMITED

RADIANCE REALTY DEVELOPERS INDIA LIMITED has 6 registrations on RERA Karnataka, including RADIANCE BLOSSOM PHASE- II and Radiance Emerald. Its filings declare 12 earlier projects, 8 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if RADIANCE FLORESTA is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of RADIANCE FLORESTA?

The registered promoter entity is RADIANCE REALTY DEVELOPERS INDIA LIMITED, a company as per the filing. Its CIN U45201TN2007PLC062662 and GSTIN 29AACCN5152H1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in RADIANCE FLORESTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RADIANCE FLORESTA?

The professionals named in the filing: Architect: Amernath A; Engineer: Jegatheesan P; Chartered Accountant: S.NARASIMAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADIANCE FLORESTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADIANCE FLORESTA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADIANCE FLORESTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.