ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Dioro & Beryl at Brigade El Dorado

Registration approved No litigation declared Mixed Development project

Dioro & Beryl at Brigade El Dorado

By Brigade Tetrarch Private Limited

RG-KA-21089 · RERA PRM/KA/RERA/1251/309/PR/160224/006634 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2028Possession promisedno revision filed
4 of 17Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 50%
5 of 1,325Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 123 documents Report an error

Dioro & Beryl at Brigade El Dorado is a Mixed Development project by Brigade Tetrarch Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/160224/006634 on 16 Feb 2024. Possession is promised by 30 Jun 2028. 1,320 of the 1,325 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete.

At a glance

Project

  • NameDioro & Beryl at Brigade El Dorado
  • TypeMixed Development
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 562149
  • Pincode562149
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/160224/006634
  • ReraGenie IDRG-KA-21089

Builder

  • NameBrigade Tetrarch Private Limited
  • Entity typeCompany
  • CINU92412KA1995PTC018247
  • GSTIN29AAACT7266Q1ZG
  • Authorized SignatoryViswa Prathap Desu
  • DirectorsPavitra Shankar, Pavitra Shankar, Amar Shivram Mysore, ROSHIN MATHEW
  • Project HeadBalasubramanian M N
  • Other registrations9 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredFeb 2024PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Feb 2024
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed123 files

Current status

100%1320 of 1,325 units booked
3.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dioro---5250525
Beryl-----823

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 50%.

Building: 53% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)100%
RCC or MS Framed structure40%
Masonry Construction40%
Plastering inside , outside & Ceiling40%
Joinery: Doors, Windows, Ventilators etc40%
Basic work of Water supply, Sanitary and Electrification40%
Dadoing, Skirting, Flooring, Tiles work (All types)40%
Railing and Grill fixing40%
Electrification, Water supply and Sanitary Finishing27%
Painting38%
Fire prevention and fire fighting fitting and fixture with network40%
Weather Proof work(tile,concrete)40%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings30%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Sewage and Drainage SystemYes30%
Water conservation/rain water harvesting/recharge of ground waterYes40%
Energy managementYes30%
Fire protection and fire safety requirementsYes30%
Solid waste management and disposalYes30%
Emergency Evacuation servicesYes30%
Internal Roads & FootpathsYes30%
Electricity supply transformer and substationYes30%
Storm water drainsYes30%
Use of renewable energyYes30%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes50%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes20%
Air ConditioningNoNot applicable
StaircasesYes30%
LiftsYes30%
Corridor/LobbiesYes30%
Fire escapesYes30%
Common entrance and exit for the building/common portico/foyer/verandahYes30%
BasementYes30%
TerraceYes30%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,578 sq m
Named landowners1
LandownerVillageDistrict
Brigade Tetrarch Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 424.25 cr
Cost incurredRs 15.40 cr
Spent of the estimate3.63%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 400.23 crRs 14.93 cr
On-site expenditure-Site OverheadRs 19.97 crRs 43.78 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.40 cr-
On-site expenditure-Salaries of workersRs 96.81 lakhRs 1.90 lakh
On-site expenditure-Consultants FeesRs 38.84 lakhRs 76,015
Payment of taxesRs 25.93 lakhRs 50,746
Payment of PremiumsRs 1.68 lakhRs 3,291
Payment of cessRs 1.48 lakhRs 2,900

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhay Itty Zachariah, M/s. Zachariah Consultants
EngineerVIJAY KUMAR S.B
Chartered AccountantR. Srinivasan

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed123

As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/160224/006634 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Dioro & Beryl at Brigade EL Dorado - Form 4 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Dioro & Beryl - Form 5 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Dioro & Beryl - Form 6 - Q2.pdf15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA Form-4 BCV (Dioro & Berly at Brigade EL Dorado).pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Dioro & Beryl- Form 5 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Dioro & Beryl - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Dioro & Berly at Brigade EL Dorado - Form 4 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Dioro & Beryl - Form 5 - Q4.PDF15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Dioro & Beryl - Form 6 - Q4.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Dioro & Beryl - Form 4 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: D & B - Form 5 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: D & B - Form 6 - Q3.pdf14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Form 2 with COA detailsFile: Dioro & Beryl - Form 2.PDF13 Feb 2024
Engineer license certificateFile: BBMP - REGISTRATION CERTIFICATE - SELF ATTESTED.pdf13 Feb 2024
CDP MapFile: CDP Map.pdf13 Feb 2024
Phasewise demarcation drawingFile: Brigade El Dorado - Phase Wise Demarcation Plan.pdf13 Feb 2024
KIADB Allotment LettersFile: KIADB - Allotment Letters.pdf13 Feb 2024
Proforma Allotment LetterFile: Dioro & Berly - Proforma Allotment Letter.pdf13 Feb 2024
Agreement for SaleFile: Dioro & Beryl at Brigade El Dorado - Agreement for Sale.pdf13 Feb 2024
Guideline Value Details - Self AttestedFile: Guideline Valuation Details.pdf13 Feb 2024
Demarcation Area DetailsFile: Blownup Plan with Area Details.pdf13 Feb 2024
AAI NOC - Self AttestedFile: Brigade El Dorado - AAI NOC - Self Attested.pdf13 Feb 2024
BESCOM NOC - Self AttestedFile: Brigade El Dorado - BESCOM NOC - Self Attested.pdf13 Feb 2024
BSNL - Self AttestedFile: Brigade El Dorado - BSNL NOC - Self Attested.pdf13 Feb 2024
KSPCB NOC - Self AttestedFile: Brigade El Dorado - CFE - Self Attested.pdf13 Feb 2024
FIRE NOC - Self AttestedFile: Brigade El Dorado - Fire NOC - Self Attested.pdf13 Feb 2024
Environment Clearance - Self AttestedFile: Brigade El Dorado - SEIAA - Self Attested.pdf13 Feb 2024
Reply to the queriesFile: Dioro & Beryl - Reply to the Queries.pdf13 Feb 2024
Registration CertificateFile: Certificate of Incorporation BTPL.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Dioro & Beryl - Form 1.pdf-
Certificate issued by Architect Form 2File: Dioro & Beryl - Form 2.PDF-
Certificate issued by Engineer Form 3File: Dioro & Beryl - Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Dioro & Beryl - No Litigation.pdf-
Certificate from Chartered AccountFile: Dioro & Beryl - Approval Certificate.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet - 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet - 2021-22.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet - 2020-21 - CA UDIN.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P & L 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit & Loss - 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit & Loss - 2020-21.pdf-
Director's Report 2022 - 2023File: Directors Report 2022-23.pdf-
Director's Report 2021 - 2022File: Directors Report 2021-22.pdf-
Director's Report 2020 - 2021File: Directors Report 2020-21.pdf-
Cash Flow Statement 2022 - 2023File: Cash Flow Statement - 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Cash Flow Statement - 2021-22.pdf-
Auditor's Report 2022 - 2023File: Auditors Report - 2022-23.pdf-
Auditor's Report 2021 - 2022File: Auditors Report - 2021-22_compressed.pdf-
Auditor's Report 2020 - 2021File: Auditors Report - 2020-21.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITRV - 2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITRV - 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 20-21.pdf-
Brigade El Dorado - Revised Sanction Plan-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Dioro & Beryl at Brigade El Dorado on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDioro & Beryl at BrigadeOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Brigade Tetrarch Private Limited

Brigade Tetrarch Private Limited has 10 registrations on RERA Karnataka, including Jasper and Iridium at Brigade El Dorado and Aurum at Brigade El Dorado. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Dioro & Beryl at Brigade El Dorado is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Dioro & Beryl at Brigade El Dorado?

The registered promoter entity is Brigade Tetrarch Private Limited, a company as per the filing. Its CIN U92412KA1995PTC018247 and GSTIN 29AAACT7266Q1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Dioro & Beryl at Brigade El Dorado?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Dioro & Beryl at Brigade El Dorado?

The professionals named in the filing: Architect: Abhay Itty Zachariah, M/s. Zachariah Consultants; Engineer: VIJAY KUMAR S.B; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dioro & Beryl at Brigade El Dorado?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dioro & Beryl at Brigade El Dorado. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dioro & Beryl at Brigade El Dorado to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.