Home / Browse projects / Raigarh, Maharashtra / Radhey Galaxy - Phase I

Completed No litigation declared Residential / Group Housing project

Radhey Galaxy - Phase I

By Radhey Properties LLP

RG-MH-24788 · RERA P52000004479 · Last updated on MahaRERA portal: 5 Mar 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 4 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Nov 2022Possession promisedregistration recorded completed
66 of 66Construction stages doneacross 6 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Radhey Galaxy - Phase I is a Residential / Group Housing project by Radhey Properties LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000004479 on 9 Aug 2017. The registration is recorded completed; possession was promised by 28 Nov 2022.

At a glance

Project

  • NameRadhey Galaxy - Phase I
  • TypeResidential / Group Housing
  • Location
    • karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000004479
  • ReraGenie IDRG-MH-24788

Builder

  • NameRadhey Properties LLP
  • Entity typePartnership
  • PartnersPrathit Vinit Kedia, Rachna Vinit Kedia, Vinit Jagdishprasad Kedia
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017PromisedNov 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Aug 2017
  • Promised completion28 Nov 2022
  • Revised completionNone
  • Buildings6 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Radhey Galaxy - Phase I - 2ANA90000
Radhey Galaxy - Phase I - 2BNA90000
Radhey Galaxy - Phase I - 3ANA90000
Radhey Galaxy - Phase I - 3BNA90000
Radhey Galaxy - Phase I - 5CNA90000
Radhey Galaxy - Phase I - 5DNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 5 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

66 of 66 construction stages are filed complete across 6 buildings.

Radhey Galaxy - Phase I - 2A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Radhey Galaxy - Phase I - 2B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Radhey Galaxy - Phase I - 3A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Radhey Galaxy - Phase I - 3B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Radhey Galaxy - Phase I - 5C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Radhey Galaxy - Phase I - 5D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities18

As on 5 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingYes100%
Community BuildingsYes25%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes80%
Open ParkingYes100%
Battery Backup for Lift and LobbyYes100%
IntercomYes100%
swimming poolYes50%

Parking filed85

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots85
Closed/Covered85
BuildingClosed/CoveredTotal
Radhey Galaxy - Phase I - 2A1111
Radhey Galaxy - Phase I - 2B1111
Radhey Galaxy - Phase I - 3A1717
Radhey Galaxy - Phase I - 3B1717
Radhey Galaxy - Phase I - 5C1111
Radhey Galaxy - Phase I - 5D1818

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,794 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Shree Siddhivinayak EnterprisesNavi Mumbai (M Corp.)Thane

Approvals and building plan

Permissible FSI9239.0
Proposed, not sanctioned9,239 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMittal Court, C Wing, Nariman Point, Mumbai, Maharashtra 400021

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVastukalp
ArchitectDhrishti Architect & Interior Designers
EngineerVastukalp
Chartered AccountantAgrawal Purohit & Co
PartnerRole in project
Radhey Properties LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Feb 2021

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_Architects certificate.pdf5 Mar 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf14 Feb 2022
OtherFile: KMC permission dated 15102018 club house land release.pdf14 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf13 Oct 2021
Certificates of CA (Form 3)File: Form 3.pdf13 Oct 2021
Certificates of CA (Form 5)File: Form 5.pdf13 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf13 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 30062021.pdf9 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 30062021.pdf9 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineer Certificate Phase I 30062021.pdf9 Aug 2021
Certificates of CA (Form 3)File: Form 3 CA Certificate Phase I dtd 30062021.pdf9 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 fy 1819.pdf9 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 1920.pdf9 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A-PhaseI-31032021.pdf23 Jul 2021
Certificates of CA (Form 5)File: Form 5.pdf23 Jul 2021
OtherFile: Form-2A-PhaseI-31032021.pdf23 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclousure of Inventory.pdf21 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf8 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Phase I.pdf1 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Phase I.pdf1 Feb 2021
Certificates of CA (Form 3)File: Form 3 CA Certificate Phase I.pdf1 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Phase I.pdf28 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Phase I.pdf28 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Maharera form 2A phase 1.pdf28 Jan 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Maharera form 2A phase 1_1.pdf28 Jan 2020
Certificates of CA (Form 3)File: Form 3 CA Certificate Phase I.pdf28 Jan 2020
Details of encumbrancesFile: Declaration of Bank change.pdf20 Jan 2020
Details of encumbrancesFile: Declaration of Encumbrances.pdf20 Jan 2020
Details of encumbrancesFile: NOC ABHFL.pdf20 Jan 2020
Certificates of CA (Form 5)File: FORM 5 fy 18-19.pdf30 Sep 2019
Proforma of Allotment letterFile: ABHFL_RPPLP_to_Customer_Agreement Format.pdf30 Sep 2019
OtherFile: No Dues Certificate.pdf30 Sep 2019
Details of encumbrancesFile: Declaration of Encumbrances.pdf3 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf22 Jul 2019
Certificates of CA (Form 3)File: CA certificate_Form-3.pdf22 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf23 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginers Certificate.pdf23 Apr 2019
Certificates of CA (Form 3)File: CA certificate_Form-3.pdf23 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf23 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginers Certificate.pdf23 Jan 2019
Certificates of CA (Form 3)File: CA certificate_Form-3.pdf23 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Achitect Certificate.pdf9 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginner Certificate.pdf9 Oct 2018
Certificates of CA (Form 3)File: CA certificate.pdf9 Oct 2018
Certificates of CA (Form 5)File: Ca Certified Form 5.pdf9 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificates of Architect.pdf16 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate.pdf16 Jun 2018
Certificates of CA (Form 3)File: CA Certificate.pdf16 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech_certificate_RPLLP_Compressed.pdf15 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering_certificate_RPLLP_Compressed.pdf15 Mar 2018
Certificates of CA (Form 3)File: CA_certificate_RPLLP_Compressed.pdf15 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf16 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: f1 ac.pdf16 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: f2 eg.pdf16 Dec 2017
Certificates of CA (Form 3)File: Radhey Galaxy Form 3.pdf16 Dec 2017
Certificates of CA (Form 3)File: f3 ca.pdf16 Dec 2017
OtherFile: f4 ag.pdf16 Dec 2017
Layout approvalFile: Plan 1.pdf28 Jul 2017
Building plan approvalFile: Plan-Phase I.pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance Letter.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan 1.pdf28 Jul 2017
Building Plan Approval (IOD)File: Plan-Phase I.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Form 3 Phase I_with SSE Flats.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter and Agreement for Sale.pdf28 Jul 2017
PAN CardFile: Radhey Properties LLP Pan Card.pdf27 Jul 2017
Copy of the legal title reportFile: Title.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 01.pdf27 Jul 2017
Declaration in FORM BFile: Form B_sign n Notary.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Phase I.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 Phase I.pdf27 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Radhey Galaxy Phase-1Karjat Bhisegoan- 410201210CompletedNov 2021Feb 2020
Radhey Residency ExtensionSurvey No 16 Village Vichumbe Taluka Panvel Dist Raigad 410206112CompletedDec 2015Aug 2014
Radhey HeritageSurvey No 110-0 & 113-1 village Palaspe Taluka Panvel Dis Raigad 410206304CompletedDec 2015Mar 2014
Green EarthSurvey No 89-0 Village Umroli Taluka Panvel Dist Raigad180CompletedJun 2015Jun 2015

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Radhey Galaxy - Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near karjat5,900+ in Raigarh

2 kmRadhey Galaxy - Phase ICompleted 29Lapsed / revoked 31Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: Radhey Properties LLP

Radhey Properties LLP has 3 registrations on MahaRERA, including Radhey Galaxy - Phase I and Radhey Galaxy - Phase 2. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Radhey Galaxy - Phase I is delayed beyond 28 Nov 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Radhey Galaxy - Phase I?

The registered promoter entity is Radhey Properties LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Radhey Galaxy - Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Radhey Galaxy - Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Radhey Galaxy - Phase I?

The professionals named in the filing: Architect: Vastukalp; Architect: Dhrishti Architect & Interior Designers; Engineer: Vastukalp; Chartered Accountant: Agrawal Purohit & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Radhey Galaxy - Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Radhey Galaxy - Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Radhey Galaxy - Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.