ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / Radhe Residency

Valid until 30 Jan 2026 Residential/Group Housing project

Radhe Residency

By RADHE DEVELOPERS

RG-GJ-38631 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA09433/081221 · Last updated on GujRERA portal: 7 Oct 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 13 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jan 2026Possession promisedmoved 13 months from the original
4 of 9Construction stages donefurthest along: Internal walls, 98%
7 of 47Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Radhe Residency is a Residential/Group Housing project by RADHE DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA09433/081221 on 8 Dec 2021. Possession is promised by 30 Jan 2026. The completion date has moved by 13 months from the original filing. 40 of the 47 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameRadhe Residency
  • TypeResidential/Group Housing
  • Location
    • Radhe Residency
    • Shiholi Moti
    • Gandhinagar
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA09433/081221
  • ReraGenie IDRG-GJ-38631

Builder

  • NameRADHE DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations8 more →
  • Past their filed date6

Key dates

this monthRegisteredDec 2021First promiseDec 2024Revised toJan 2026

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2026
  • Registered on8 Dec 2021
  • Promised completion30 Jan 2026
  • Revised completionRevised to 30 Jan 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed41 files

Current status

85%40 of 47 units booked
80.0%Of the estimated cost spent so far

Figures as on 7 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---47047

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

A: 63% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats98%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing65%

Progress on shared amenities19

As on 7 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes0%
Street lightingYes30%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationYes0%
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,681 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.40 cr
Cost incurredRs 5.12 cr
Spent of the estimate80.0%
BuildingWingEstimatedIncurred
ANARs 6.40 crRs 5.12 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumikkumar C Donga
EngineerPravin Thakkar

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Feb 2025; no approval date filed

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA09433/081221 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Oct 2024
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
Architect's certificate (Form 1)5 Oct 2024
Site photograph, A31 Aug 2024
Site photograph, A31 Aug 2024
RERA registration certificate8 Dec 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

85%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 13 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Radhe Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmRadhe ResidencyOther 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: RADHE DEVELOPERS

RADHE DEVELOPERS has 9 registrations on GujRERA, including RADHE HEIGHTS and RATNARAJ GREEN. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Radhe Residency is delayed beyond 30 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Radhe Residency?

The registered promoter entity is RADHE DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Radhe Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Radhe Residency?

The professionals named in the filing: Architect: Bhaumikkumar C Donga; Engineer: Pravin Thakkar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Radhe Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Radhe Residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Radhe Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.