ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / RAAHI KASTURI

Completed No litigation declared Residential / Group Housing project

RAAHI KASTURI

By RAAHI YASHILA

RG-MH-23183 · RERA P52100032695 · Last updated on MahaRERA portal: 23 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
1 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 95%
61 of 182Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 310 documents Report an error

RAAHI KASTURI is a Residential / Group Housing project by RAAHI YASHILA in Pune, Maharashtra, registered with MahaRERA as P52100032695 on 24 Jan 2022. The registration is recorded completed; possession was promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 121 of the 182 units on this registration are recorded sold or booked, and 1 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRAAHI KASTURI
  • TypeResidential / Group Housing
  • Location
    • CHARHOLI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032695
  • ReraGenie IDRG-MH-23183

Builder

  • NameRAAHI YASHILA
  • Entity typePartnership
  • PartnersRAMDAS TULSIRAM VIDHATE, SUMIT VITTHAL DEOKAR, DEVENDRA MURLIDHAR MURKUTE, ATUL BHAUSAHEB DOKE

Key dates

this monthRegisteredJan 2022First promiseDec 2025Revised toDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2022
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed310 files

Current status

66%121 of 182 units booked
70.1%Work done, per cost certificate

Figures as on 23 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA11991091
B BUILDINGNA151391091

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 95%.

A BUILDING8%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B BUILDING67%
ActivityProgress
Excavation95%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered45
BuildingClosed/CoveredTotal
A BUILDING2222
B BUILDING2323

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,562 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jul 2025
LandownerVillageDistrict
MR JAGANNATH TUKARAM KALJECHARHOLIPune
MR BABULAL TUKARAM KALJECHARHOLIPune
MR SHANKAR TUKARAM KALJECHARHOLIPune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI14246.14
Proposed, not sanctioned11,159 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchALANDI PUNE
Estimated costRs 32.29 cr
Cost incurredRs 22.64 cr
Work done70.13%
BuildingWingEstimatedIncurred
A BUILDINGNARs 14.85 crRs 5.89 cr
B BUILDINGNARs 14.85 crRs 14.53 cr
-NARs 2.59 crRs 2.23 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHREE SPACES
EngineerMR ABHIJIT THAKUR
Chartered AccountantPGMJ AND ASSOCIATES
Chartered AccountantPRAVIN PISE AND ASSOCIATES
Chartered AccountantVAIBHAV S BHISE & ASSOCIATES
PartnerRole in project
RAAHI YASHILA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024286Dec 2025 → Dec 2026

Reason as filed by the promoterTechnical issues with the planning authority, resulting in delays in issuing the full Completion Certificate. Insufficient funding, material shortages, and unavailability of labour, further hindering our progress.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600356Pravin Ramesh PatilRAAHI YASHILA19/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Jan 2025

Documents filed310

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 310 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: F1-Q4.pdf23 Apr 2026
Withdrawal Update Form 1File: F1-Q3.pdf23 Apr 2026
Withdrawal Update Form 2File: F2-Q4.pdf23 Apr 2026
Withdrawal Update Form 2File: F2-Q3.pdf23 Apr 2026
Withdrawal Update Form 3File: F3-Q4_compressed.pdf23 Apr 2026
Withdrawal Update Form 3File: F3-Q3.pdf23 Apr 2026
Withdrawal Update Form 1File: F1.pdf12 Nov 2025
Withdrawal Update Form 2File: FORM-2.pdf12 Nov 2025
Withdrawal Update Form 3File: FORM-3 (RAAHI YASHILA)_compressed.pdf12 Nov 2025
Form 5 (FY 2024-2025)File: F5-RAAHI YASHILA (1).pdf29 Sep 2025
Form 1File: F1-FINAL.pdf19 Jul 2025
Form 2File: F2-FINAL.pdf19 Jul 2025
Form 3File: F3-FINAL.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: SU-FINAL.pdf19 Jul 2025
Declaration in FORM BFile: LATEST NOTARY-FINAL.pdf30 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf30 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-22-23-Q1.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-21-22-Q4.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-24-25-Q4.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-24-25-Q3.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-24-25-Q2.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-24-25-Q1.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-23-24-Q4-1-3.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-23-24-Q3.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-23-24-Q2.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-23-24-Q1.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-22-23-Q4.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-22-23-Q3.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-22-23-Q2.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-DEC-22.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-25.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-DEC-24.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-SEPT-24_compressed.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-JUNE-24.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-24.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-DEC-23.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-SEPT-23.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-JUNE-23.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-23.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-SEPT-22.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-JUNE-22.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-MARCH-22.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-23.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-25.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-DEC-24.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-SEPT-24.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-JUNE-24.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-24.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-DEC-23.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-JUNE-23.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-DEC-22.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-SEPT-22.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-JUNE-22.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-MARCH-22.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-SEPT-23.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-DEC-23.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-MARCH-25.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-MARCH-25.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-DEC-24.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-SEPT-24.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-JUNE-24.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-MARCH-24.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-SEPT-23.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-JUNE-23.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-MARCH-23.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-DEC-22.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-SEPT-22.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-JUNE-22.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SU-MARCH-22.pdf27 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT-A-FINAL.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-21-22.pdf27 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 1.pdf27 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 2.pdf27 Jun 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 3.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-22-23.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-23-24.pdf27 Jun 2025
Form 1File: F1-21-22-Q4.pdf27 Jun 2025
Form 2File: F2-MARCH-22.pdf27 Jun 2025
Form 3File: F3-MARCH-22.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: SU-MARCH-22.pdf27 Jun 2025

How this compares with Pune

66%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAAHI KASTURI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARHOLI13,700+ in Pune

2 kmRAAHI KASTURICompleted 74Lapsed / revoked 37Other 87Dot size: filed unitsN

Filed coordinates, straight-line distance. 198 registered projects within 2 km.

Builder: RAAHI YASHILA

RAAHI YASHILA has 1 registration on MahaRERA, including RAAHI KASTURI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if RAAHI KASTURI is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAAHI KASTURI?

The registered promoter entity is RAAHI YASHILA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAAHI KASTURI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAAHI KASTURI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAAHI KASTURI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAAHI KASTURI?

The professionals named in the filing: Architect: SHREE SPACES; Engineer: MR ABHIJIT THAKUR; Chartered Accountant: PGMJ AND ASSOCIATES; Chartered Accountant: PRAVIN PISE AND ASSOCIATES; Chartered Accountant: VAIBHAV S BHISE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAAHI KASTURI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAAHI KASTURI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAAHI KASTURI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.