Home / Browse projects / Solapur, Maharashtra / R N GOLI SUNDARBAN PHASE 1 2

Registration lapsed No litigation declared Mixed project

R N GOLI SUNDARBAN PHASE 1 2

By SHUBHAM DEVELOPERS

RG-MH-20751 · RERA P52600004264 · Last updated on MahaRERA portal: 16 Jan 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
10 of 11Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
3 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

R N GOLI SUNDARBAN PHASE 1 2 is a Mixed project by SHUBHAM DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600004264 on 9 Aug 2017. Possession was promised by 1 Jul 2023 and is now 39 months past that date. 10 of the 13 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameR N GOLI SUNDARBAN PHASE 1 2
  • TypeMixed
  • Location
    • Solapur (M Corp.)
    • Solapur North
    • Solapur
    • 413007
  • Pincode413007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52600004264
  • ReraGenie IDRG-MH-20751

Builder

  • NameSHUBHAM DEVELOPERS
  • Entity typePartnership
  • PartnersRAGHAVENDRA SHRIDHAR GOLI, LAXMIKANT RAMCHANDRA UDGIRI
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

39 months past promisethis monthRegisteredAug 2017PromisedJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion1 Jul 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed19 files

Current status

77%10 of 13 units booked

Figures as on 16 Jan 2020, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R N GOLI SUNDARBAN PHASE 1 2NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

R N GOLI SUNDARBAN PHASE 1 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 16 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,573 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3573.56
Proposed, not sanctioned1,070 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchASHOK CHOWK

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHESH PATIL
PartnerRole in project
SHUBHAM DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jan 2020

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PLOT NO-34 001.pdf16 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PLOT NO-33 001.pdf16 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: POLT NO-19 001.pdf16 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PLOT NO -24 001.pdf16 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SHUBHAM PLOT NO 25.pdf24 Aug 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SHUBHAM PLOT NO 30.pdf24 Aug 2019
Building plan approval or NA orderFile: SHUBHAM PL.pdf31 Jul 2017
Copy of the legal title reportFile: SH SEARCH PART1.pdf31 Jul 2017
Copy of the legal title reportFile: SH SEARCH PART2.pdf31 Jul 2017
Building Plan Approval (IOD)File: SHUBHAM PL.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SHUBHAM ARCHT.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA CERT.pdf31 Jul 2017
Details of encumbrancesFile: SHUBHAM ENC 001.pdf30 Jul 2017
Proforma of Allotment letterFile: shubham all1.pdf30 Jul 2017
Layout approvalFile: 8 6 LAYOUT .pdf29 Jul 2017
PAN CardFile: SHUBHAM DEV PAN 1.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 8 6 LAYOUT .pdf29 Jul 2017
Declaration in FORM BFile: SHUBHAM AFFD 001 .pdf29 Jul 2017

How this compares with Solapur

77%of this project is bookeddistrict median 15%
15%of Solapur projects moved their completion datethis one has not
39%of Solapur registrations have lapsed or been cancelledthis one is among them

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep R N GOLI SUNDARBAN PHASE 1 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Solapur (M Corp.)550+ in Solapur

2 kmR N GOLI SUNDARBAN PHASECompleted 3Lapsed / revoked 2Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: SHUBHAM DEVELOPERS

SHUBHAM DEVELOPERS has 6 registrations on MahaRERA, including OSCAR PLAZZA and R N GOLI SUNDARBAN PHASE 1 2. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What does it mean that R N GOLI SUNDARBAN PHASE 1 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if R N GOLI SUNDARBAN PHASE 1 2 is delayed beyond 1 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of R N GOLI SUNDARBAN PHASE 1 2?

The registered promoter entity is SHUBHAM DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in R N GOLI SUNDARBAN PHASE 1 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for R N GOLI SUNDARBAN PHASE 1 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at R N GOLI SUNDARBAN PHASE 1 2?

The professionals named in the filing: Architect: MAHESH PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in R N GOLI SUNDARBAN PHASE 1 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About R N GOLI SUNDARBAN PHASE 1 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save R N GOLI SUNDARBAN PHASE 1 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.