Home / Browse projects / Mysore, Karnataka / Pyramid Serenity
Pyramid Serenity
By Pyramid Timber Associates Private Limited
RG-KA-48777 · RERA PRM/KA/RERA/1268/378/PR/140525/007743 · Last updated on RERA Karnataka portal: 2 Jan 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Pyramid Serenity is a Plotted Development project by Pyramid Timber Associates Private Limited in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/140525/007743 on 14 May 2025. Possession is promised by 31 Dec 2027.
At a glance
Project
- NamePyramid Serenity
- TypePlotted Development
- Location
- MYSORE
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/378/PR/140525/007743
- ReraGenie IDRG-KA-48777
Builder
- NamePyramid Timber Associates Private Limited
- Entity typeCompany
- CINU68100KA1987PTC008701
- GSTIN29AABCP0488K1Z1
- Authorized SignatoryHussain M Vagh
- CeoAliasagar M vagh
- DirectorsAbbas Salehbhai Vagh, Abbas Taherally Vagh, Abdul Hussain S Vagh, Hyder Tyeb Vagh, Mohammedi Taherally Vagh, Moiz Saifuddin Vagh, Yusuf Hussaini Vagh
- Project HeadHussain M Vagh
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on14 May 2025
- Promised completion31 Dec 2027
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed70 files
Current status
Figures as on 2 Jan 2026, this project's latest RERA Karnataka filing.
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Pyramid Timber Associates Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.75 cr | Rs 3.64 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Lingaraju J |
| Chartered Accountant | Manju K |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed70
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/140525/007743 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Q3_CA Certificate.pdf | 2 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6_Q3_Engineer certificate.pdf | 2 Jan 2026 |
| Reciept as per financial statement and Source of fund clarificationFile: Reciept as per financial statement & Source of fund.pdf | 28 Apr 2025 |
| Affidavit undertaking B-kharab land in projectFile: B-Kharab Land Affidavit.pdf | 28 Apr 2025 |
| A Karab 0-17 Guntas_Order CopyFile: A Karab_0-17 Guntas_Order Copy.pdf | 28 Apr 2025 |
| Engineer License with self-attestedFile: Engineer License with self-attested.jpeg | 28 Apr 2025 |
| Noratised Affidavit section 3(1)File: Noratised Affidavit 3(1).pdf | 28 Apr 2025 |
| CESCOM NOC & fees Receipt with self attestedFile: CESCOM NOC & fees Receipt_with self attested.pdf | 28 Apr 2025 |
| Water NOC & fees Receipt with self attestedFile: Water NOC & fees Receipt_with self attested.pdf | 28 Apr 2025 |
| RTC, survey Old Sy No 81 (New Sy No 9) | - |
| Mutation, survey Old Sy No 81 (New Sy No 9) | - |
| Encumbrance Certificate, survey Old Sy No 81 (New Sy No 9) | - |
| Conversion/Alienation Order, survey Old Sy No 81 (New Sy No 9) | - |
| Sale/Title/Gift Deed, survey Old Sy No 81 (New Sy No 9) | - |
| Khatha, survey Old Sy No 81 (New Sy No 9) | - |
| Registration CertificateFile: Certf of Incorporation.pdf | - |
| Memorandum of AssociationFile: Attested MOA.pdf | - |
| Article of AssociationFile: Attested AOA.pdf | - |
| GST CertificateFile: GST Certificate.pdf | - |
| Organization StructureFile: MCA Certificate.pdf | - |
| Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form - 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: Affidavit Non-litigation.pdf | - |
| Balance Sheet 2023 - 2024File: Balance Sheet (FY 2023-24).pdf | - |
| Balance Sheet 2022 - 2023File: Balance Sheet (FY 2022-23).pdf | - |
| Balance Sheet 2021 - 2022File: Balance Sheet (FY 2021-22).pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Profit and Loss Account (FY 2023-24).pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss Account (FY 2022-23).pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss Account (FY 2021-22).pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR FY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR FY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR FY 2021-22.pdf | - |
| Director's Report 2023 - 2024File: Signed Directors Report (FY 2023-24).pdf | - |
| Director's Report 2022 - 2023File: Signed Directors Report (FY 2022-23).pdf | - |
| Director's Report 2021 - 2022File: Signed Directors Report (FY 2021-22).pdf | - |
| Cash Flow Statement 2023 - 2024File: Cash Flow Statement (FY 2023-24).pdf | - |
| Cash Flow Statement 2022 - 2023File: Cash Flow Statement (FY 2022-23).pdf | - |
| Auditor's Report 2023 - 2024File: Audit report (FY 2023-24).pdf | - |
| Auditor's Report 2022 - 2023File: Audit report (FY 2022-23).pdf | - |
| Auditor's Report 2021 - 2022File: Audit Report (FY 2021-22).pdf | - |
| Plan Approaval | - |
| Layout Plan | - |
| Agreement of Sale Proforma - for plotted development | - |
| Allotment Letter | - |
| Form B | - |
| Aakhar band | - |
| Abstract Estimate | - |
| ADLR Surrvey Skech with authority certified | - |
| Common Area Details | - |
| Land Cost Calculation Sheet | - |
| Master Plan certified by authority | - |
| Form -6 Engineer Certificate | - |
| PTCL letter | - |
| STP Drawing self-attested by Engineer | - |
| Village Map certified by authority | - |
| Work Order | - |
| Plot Excel SheetFile: Pyramid Serenity.xlsx | - |
| Final plan technical sanction LetterFile: Final Release Order.pdf | - |
| Final layout plan sanctionedFile: Final Layout Plan.pdf | - |
| Completion CertificateFile: Final Release Order.pdf | - |
| Site release order Copies(1st,2nd phase and final release order)File: Final Layout Plan.pdf | - |
| Relinquishment deed executed handed over detailsFile: Road_Relinquishment Deed.pdf | - |
| Certificate issued by the Karnataka Urban Water supplyFile: Water supply and UGD NOC.pdf | - |
| Certificate issued by the concerned power supply(ESCOM'S)File: CESCOM NOC.pdf | - |
| Whether the structures,civic amenities and other services handed over to local authority for maintenanceFile: Civil Work NOC.pdf | - |
| Chartered Accountant Certificate (Form-4)File: Form-4CC_CA Certificate.pdf | - |
| Engineer's Certificate (Form-6)File: Form-6_Engineer Certificate.pdf | - |
| Affidavit from Promoter for completing project as per advertisement published in brochure and as per project sFile: AFFIDAVIT CUM DECLARATION.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep Pyramid Serenity on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: Pyramid Timber Associates Private Limited
Pyramid Timber Associates Private Limited has 1 registration on RERA Karnataka, including Pyramid Serenity. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if Pyramid Serenity is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Pyramid Serenity?
The registered promoter entity is Pyramid Timber Associates Private Limited, a company as per the filing. Its CIN U68100KA1987PTC008701 and GSTIN 29AABCP0488K1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Pyramid Serenity?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Pyramid Serenity?
The professionals named in the filing: Engineer: Lingaraju J; Chartered Accountant: Manju K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pyramid Serenity?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback