Home / Browse projects / Bengaluru Urban, Karnataka / Provident Ecopolitan Phase 1

Registration approved No litigation declared Residential/Group Housing project

Provident Ecopolitan Phase 1

By Provident White Oaks LLP

RG-KA-43060 · RERA PRM/KA/RERA/1251/309/PR/180823/006187 · Last updated on RERA Karnataka portal: 31 Mar 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Sep 2027Possession promisedno revision filed
5 of 17Construction stages donefurthest along: RCC or MS Framed structure, 78%
3 of 264Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 112 documents Report an error

Provident Ecopolitan Phase 1 is a Residential/Group Housing project by Provident White Oaks LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180823/006187 on 18 Aug 2023. Possession is promised by 30 Sep 2027. 261 of the 264 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameProvident Ecopolitan Phase 1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 562149
  • Pincode562149
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180823/006187
  • ReraGenie IDRG-KA-43060

Builder

  • NameProvident White Oaks LLP
  • Entity typePartnership Firm
  • GSTIN29ABCFP9036A1ZB
  • Authorized SignatoryJatin Ujjini C S
  • Other registrations5 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2023PromisedSep 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Aug 2023
  • Promised completion30 Sep 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed112 files

Current status

99%261 of 264 units booked
41.5%Of the estimated cost spent so far

Figures as on 31 Mar 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 3---1320132
Wing 4---1320132

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 78%.

Building: 40% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure78%
Masonry Construction78%
Plastering inside , outside & Ceiling5%
Joinery: Doors, Windows, Ventilators etc5%
Basic work of Water supply, Sanitary and Electrification20%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes20%
LiftsYes20%
Corridor/LobbiesYes20%
Fire escapesYes20%
Common entrance and exit for the building/common portico/foyer/verandahYes20%
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes20%
Open parking areasYes20%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,044 sq m
Named landowners1
LandownerVillageDistrict
Provident White Oaks LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 162.53 cr
Cost incurredRs 67.48 cr
Spent of the estimate41.52%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 105.38 crRs 62.32 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 19.71 crRs 21.02 lakh
Payment of taxesRs 18.97 crRs 12.74 lakh
On-site expenditure-Site OverheadRs 18.47 crRs 4.82 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKembhavi Architecture
EngineerShantharaju. K
Chartered AccountantM Padmanabha Bhat

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01647/2023-Provident White Oaks LLP02/11/2023

Documents filed112

As listed on the registration, under the names the promoter filed them with; the newest 80 of 112 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180823/006187 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ecopolitan Phase1 Form4 RERA Dec25.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Ecopolitan Architect certificate Dec25.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Ecopolithan-1 Engineer Certificate Dec25.pdf31 Mar 2026
FinancialsFile: White Oaks - 2021-22.pdf13 Aug 2023
Balance Sheet 21-22File: White Oaks - 2021-22 Balance Sheet.pdf13 Aug 2023
P and L 21-22File: White Oaks - 2021-22 P & L Account.pdf13 Aug 2023
1st Floor PlanFile: 1st floor plan.pdf13 Aug 2023
CFEFile: CFE from KSPCB_merged (1).pdf13 Aug 2023
Form 2File: Form-2 Architect Certificate Phase 1 Final.pdf13 Aug 2023
CDP Plan DemarcatedFile: KIADB CDP Plam Demarcated.pdf13 Aug 2023
Floor Plan DemarcatedFile: ECOPOLITAN - FIRST FLOOR PLAN.pdf13 Aug 2023
Building permission CertificateFile: certificate.pdf13 Aug 2023
PlanFile: DWG PAGE 1.pdf13 Aug 2023
SEIAAFile: Environmental Clearance.pdf13 Aug 2023
COIFile: Certificate of Incorporation.pdf13 Aug 2023
FinancialsFile: White Oaks - 2021-22.pdf3 Aug 2023
Balance SheetFile: White Oaks - 2021-22 Balance Sheet.pdf3 Aug 2023
Area Details Phase wiseFile: Area Details Phase wise.pdf3 Aug 2023
GST CertificateFile: GST Certificate.pdf3 Aug 2023
Bank Account statementFile: ACK_AADFW6547R_2022-23_288754720300722.pdf3 Aug 2023
Area Details Phase wiseFile: Area Details Phase wise.pdf3 Aug 2023
Carpet Area StatementFile: Carpet Area Statement Phase 1 Ecopolitan.pdf3 Aug 2023
FAR ClarificationFile: FAR Declaration.pdf3 Aug 2023
Built Up Area calculation Phase wiseFile: Built Up Area Phase wise.pdf3 Aug 2023
Carpet Area CalculationFile: Carpet Area Statement Phase 1 Ecopolitan.pdf3 Aug 2023
Master PlanFile: Master Plan.jpg3 Aug 2023
Village MapFile: Villagemaps merged copy.jpg3 Aug 2023
Commencement CertificateFile: Commencement Certificate Declaration.pdf3 Aug 2023
PlanFile: DWG PAGE 1.pdf3 Aug 2023
Architect CertificateFile: Form-2 Architect Certificate Phase 1.pdf3 Aug 2023
Demarcated Signed copy with area detailsFile: Demarcated Plan Phase wise signed.pdf3 Aug 2023
Demarcated Plan Clear copyFile: Demarcated Plan Clear copy.pdf3 Aug 2023
Sanction PlansFile: DWG PAGE 1.pdf3 Aug 2023
Sanction PlansFile: DWG PAGE 3.pdf3 Aug 2023
Sanction PlansFile: DWG PAGE 5.pdf3 Aug 2023
Sanction PlansFile: DWG PAGE 7.pdf3 Aug 2023
Sanction PlansFile: DWG PAGE 10.pdf3 Aug 2023
Sanction PlansFile: Block A & B Stild Floor Plan.pdf3 Aug 2023
Sanction PlansFile: Elevation and Section Plan.pdf3 Aug 2023
Sanction PlansFile: Floor Plan 2nd.pdf3 Aug 2023
Sanction PlansFile: Floor Plan 3rd and 4th.pdf3 Aug 2023
Sanction PlansFile: Floor Plan 5th.pdf3 Aug 2023
Sanction PlansFile: Floor Plan 6th to 19th.pdf3 Aug 2023
Sanction PlansFile: Floor Plan Basement.pdf3 Aug 2023
Sanction PlansFile: Section Plan 1.pdf3 Aug 2023
Sanction PlansFile: dwg page2.pdf3 Aug 2023
Incorporation certificateFile: Certificate of Incorporation.pdf3 Aug 2023
Fire NOC Self attestedFile: Fire NOC.pdf3 Aug 2023
BESCOM NOCFile: BESCOM.pdf3 Aug 2023
Water NOCFile: Water NOC.pdf3 Aug 2023
KSPCBFile: KSPCB.pdf3 Aug 2023
Common area and amenity CalculationFile: Common area and Amenities Area calculation.pdf3 Aug 2023
Guideline value self attestedFile: Guidline Value Self Attested.pdf3 Aug 2023
STP DrawingFile: STP Drawing PCB_compressed.pdf3 Aug 2023
Brief Estimated costFile: Budget.pdf3 Aug 2023
AOSFile: Agreement to Sell.pdf3 Aug 2023
Allotment LetterFile: Allotment Letter Phase 1.pdf3 Aug 2023
Airport NOCFile: AIRPORTS AUTHORITY OF INDIA.pdf3 Aug 2023
RTC, survey Plot No R-4-Part-A and R-4-Part-B Parts of 177 (Block No. 1,2 & 3) 72,73/1,73/2,73/3,73/4,74/1,74/-
Mutation, survey Plot No R-4-Part-A and R-4-Part-B Parts of 177 (Block No. 1,2 & 3) 72,73/1,73/2,73/3,73/4,74/-
Encumbrance Certificate, survey Plot No R-4-Part-A and R-4-Part-B Parts of 177 (Block No. 1,2 & 3) 72,73/1,73/-
Khatha, survey Plot No R-4-Part-A and R-4-Part-B Parts of 177 (Block No. 1,2 & 3) 72,73/1,73/2,73/3,73/4,74/1,-
Registration CertificateFile: Certificate of Incorporation.pdf-
Partnership DeedFile: Partnership Deed - Provident White Oaks.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1-Phase 1.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate Phase 1.pdf-
Certificate issued by Engineer Form 3File: Form 3 Phase 1.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1-Phase 1.pdf-
Balance Sheet 2021 - 2022File: White Oaks - 2021-22 Balance Sheet.pdf-
Balance Sheet 2020 - 2021File: White Oaks - 2021-22 Balance Sheet.pdf-
Audited Profit and Loss Statement 2021 - 2022File: White Oaks - 2021-22 P & L Account.pdf-
Audited Profit and Loss Statement 2020 - 2021File: White Oaks - 2021-22 P & L Account.pdf-
Auditor's Report 2021 - 2022File: White Oaks - 2021-22 Independent Auditors Report.pdf-

How this compares with Bengaluru Urban

99%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Provident Ecopolitan Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmProvident Ecopolitan PhaOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Provident White Oaks LLP

Provident White Oaks LLP has 6 registrations on RERA Karnataka, including Provident Ecopolitan Phase 1A and Provident Ecopolitan Phase 2. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Provident Ecopolitan Phase 1 is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Provident Ecopolitan Phase 1?

The registered promoter entity is Provident White Oaks LLP, a partnership firm as per the filing. Its GSTIN 29ABCFP9036A1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Provident Ecopolitan Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Provident Ecopolitan Phase 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Provident Ecopolitan Phase 1?

The professionals named in the filing: Architect: Kembhavi Architecture; Engineer: Shantharaju. K; Chartered Accountant: M Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Provident Ecopolitan Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Provident Ecopolitan Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Provident Ecopolitan Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.