Provident Deansgate Phase 2

By Puravankara Limited

RG-KA-04614 · RERA PRM/KA/RERA/1250/303/PR/170325/007590 · Last updated on RERA Karnataka portal: 20 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2028Possession promisedno revision filed
3 of 16Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 43%
57 of 141Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 148 documents Report an error

Provident Deansgate Phase 2 is a Residential/Group Housing project by Puravankara Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/170325/007590 on 17 Mar 2025. Possession is promised by 31 Mar 2028. 84 of the 141 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.

At a glance

Project

  • NameProvident Deansgate Phase 2
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/170325/007590
  • ReraGenie IDRG-KA-04614

Builder

  • NamePuravankara Limited
  • Entity typeCompany
  • CINL45200KA1986PLC051571
  • GSTIN29AAACP2550R1ZX
  • Authorized SignatoryJatin Ujjini C S
  • MdAshish Ravi Puravankara
  • DirectorsAshish Ravi Puravankara, Abhishek Kapoor, Ravi Puravankara
  • Project HeadNagendra
  • Other registrations26 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredMar 2025PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Mar 2025
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed148 files

Current status

60%84 of 141 units booked
18.1%Of the estimated cost spent so far

Figures as on 20 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Provident Deansgate Phase 2---1410141

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 43%.

Building: 37% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)43%
Retaining wall (All types)Not applicable
RCC or MS Framed structure43%
Masonry Construction43%
Plastering inside , outside & Ceiling39%
Joinery: Doors, Windows, Ventilators etc39%
Basic work of Water supply, Sanitary and Electrification39%
Dadoing, Skirting, Flooring, Tiles work (All types)39%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,925 sq m
Named landowners6
LandownerVillageDistrict
Puravankara Ltd--
Puravankara Ltd--
Puravankara Ltd--
Puravankara Ltd--
Puravankara Ltd--
Puravankara Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 152.80 cr
Cost incurredRs 27.65 cr
Spent of the estimate18.1%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 125.77 crRs 23.85 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 15.00 cr-
On-site expenditure-Site OverheadRs 10.54 crRs 3.80 cr
On-site expenditure-Consultants FeesRs 1.49 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrban Frame Private Limited
EngineerH P Yogesh
Chartered AccountantV D S R & CO LLP

Litigation declaredYes

The promoter declares litigation on this registration. The case records are in the filed documents.

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed148

As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/170325/007590 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Deansgate phase 2 RERA Form 4 Mar26.pdf20 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Deansgate 2 Architect Certificate Mar26.pdf20 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4,Deansgate,ph-2.pdf20 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Deangate-2 RERA Form4 Dec25.pdf16 Jul 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Deangate-2 RERA Form4 Dec25.pdf16 Jul 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Deansgate-2 Engineer Certificate Dec25.pdf16 Jul 2026
Site Plan ApprovedFile: Site Approved Plan.pdf12 Mar 2025
Site Plan Approved Clear VersionFile: Site Approved Plan.jpg12 Mar 2025
Block 8 Floor PlanFile: Block 8 Floor Plan.jpg12 Mar 2025
Block 8 Elevation and sectionFile: Block 8 Section and Elevation.jpg12 Mar 2025
Block 9 Floor PlanFile: Block 9 Floor Plan.jpg12 Mar 2025
Block 9 Section and elevationFile: Block 9 Section and Elevation.jpg12 Mar 2025
Block 10 Floor PlanFile: Block 10 Floor Plan.jpg12 Mar 2025
Block 10 Section and elevationFile: Block 10 Section and Elevation.jpg12 Mar 2025
Block 11 Floor PlanFile: Block 11 Floor Plan.jpg12 Mar 2025
Block 11 Section and elevationFile: Block 11 Section and Elevation.jpg12 Mar 2025
Block 12 Floor PlanFile: Block 12 Floor Plan.jpg12 Mar 2025
Block 12 Section and elevationFile: Block 12 Section and Elevation.jpg12 Mar 2025
Block 13 Floor PlanFile: Block 13 Floor Plan.jpg12 Mar 2025
Block 13 Section and elevationFile: Block 13 Section and Elevation.jpg12 Mar 2025
41/1 Conversion OrderFile: 41-1.pdf12 Mar 2025
Plan OrderFile: Plan Approval.pdf12 Mar 2025
Guidline Value Self AttestedFile: Guildine Value Self Attested.pdf12 Mar 2025
Village MapFile: 9 - Village map.pdf12 Mar 2025
Brief Estimated CostFile: R0-Deansgate Budget-Signed on 14-04-23.pdf12 Mar 2025
ADLR SketchFile: ADLR Sketch.pdf12 Mar 2025
EC Till DateFile: ECC-15022025-10598129.pdf12 Mar 2025
Litigation DeclarationFile: Litigation Affidavit.pdf12 Mar 2025
release deed for the mortgage with KGB Sy No 43_3File: Loan Release KGB.pdf12 Mar 2025
STP drawing as per KSPCBFile: STP drawing as per KSPCB.pdf12 Mar 2025
Commencement CertificateFile: Plan Approval.pdf12 Mar 2025
Agreement for SaleFile: ATS - DEANSGATE 2 (1).pdf12 Mar 2025
Water NOCFile: Water NOC Attested Upload.pdf12 Mar 2025
Financials with UDIN 2023-24File: PL FS FY 24.pdf12 Mar 2025
Advocate Search ReportFile: Search Report Advocate.pdf12 Mar 2025
KSPCB NOCFile: KSPCB Attested.pdf12 Mar 2025
Common Area and AmenitiesFile: Arear Detrails Common and amenties.pdf12 Mar 2025
CDPFile: DEANSGATE- CDP.JPG12 Mar 2025
CDP DemarcatedFile: DEANSGATE LOCATION IN CDP.JPG12 Mar 2025
Engineer LicenseFile: BANGALORE MAHANAGARA PALIKE.pdf12 Mar 2025
RTC, survey 41/1-
Mutation, survey 41/1-
Encumbrance Certificate, survey 41/1-
Conversion/Alienation Order, survey 41/1-
Sale/Title/Gift Deed, survey 41/1-
Khatha, survey 41/1-
RTC, survey 43/3-
Mutation, survey 43/3-
Encumbrance Certificate, survey 43/3-
Conversion/Alienation Order, survey 43/3-
Sale/Title/Gift Deed, survey 43/3-
Khatha, survey 43/3-
RTC, survey 37/2-
Mutation, survey 37/2-
Encumbrance Certificate, survey 37/2-
Conversion/Alienation Order, survey 37/2-
Sale/Title/Gift Deed, survey 37/2-
Khatha, survey 37/2-
RTC, survey 37/4 (Old Sy No 37/1)-
Mutation, survey 37/4 (Old Sy No 37/1)-
Encumbrance Certificate, survey 37/4 (Old Sy No 37/1)-
Conversion/Alienation Order, survey 37/4 (Old Sy No 37/1)-
Sale/Title/Gift Deed, survey 37/4 (Old Sy No 37/1)-
Khatha, survey 37/4 (Old Sy No 37/1)-
RTC, survey 36/4(Old SY No 36/3)-
Mutation, survey 36/4(Old SY No 36/3)-
Encumbrance Certificate, survey 36/4(Old SY No 36/3)-
Conversion/Alienation Order, survey 36/4(Old SY No 36/3)-
Sale/Title/Gift Deed, survey 36/4(Old SY No 36/3)-
Khatha, survey 36/4(Old SY No 36/3)-
RTC, survey 36/1-
Mutation, survey 36/1-
Encumbrance Certificate, survey 36/1-
Conversion/Alienation Order, survey 36/1-
Sale/Title/Gift Deed, survey 36/1-
Khatha, survey 36/1-
Registration CertificateFile: CoI PL.PDF-
Memorandum of AssociationFile: MOA AOA of PL.pdf-
Article of AssociationFile: MOA AOA of PL.pdf-
GST CertificateFile: GST PL Karnataka.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Provident WoodfieldKachanayakanahalli Jigani Anekal Taluk BengaluruCompleted-No date filed

How this compares with Bengaluru Rural

60%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Provident Deansgate Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmProvident Deansgate PhasOther 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: Puravankara Limited

Puravankara Limited has 27 registrations on RERA Karnataka, including Provident Deansgate and Provident Deansgate Phase 2. Its filings declare 5 earlier projects, 5 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Provident Deansgate Phase 2 is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Provident Deansgate Phase 2?

The registered promoter entity is Puravankara Limited, a company as per the filing. Its CIN L45200KA1986PLC051571 and GSTIN 29AAACP2550R1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Provident Deansgate Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Provident Deansgate Phase 2?

The professionals named in the filing: Architect: Urban Frame Private Limited; Engineer: H P Yogesh; Chartered Accountant: V D S R & CO LLP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Provident Deansgate Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Provident Deansgate Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Provident Deansgate Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.