ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / Provident Deansgate

Registration approved Litigation declared Residential/Group Housing project

Provident Deansgate

By Puravankara Limited

RG-KA-21401 · RERA PRM/KA/RERA/1250/303/PR/041123/006373 · Last updated on RERA Karnataka portal: 8 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2027Possession promisedno revision filed
3 of 15Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 88%
22 of 147Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 131 documents Report an error

Provident Deansgate is a Residential/Group Housing project by Puravankara Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/041123/006373 on 4 Nov 2023. Possession is promised by 31 May 2027. 125 of the 147 units on this registration are recorded sold or booked, and 3 of 15 construction stages are filed complete.

At a glance

Project

  • NameProvident Deansgate
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/041123/006373
  • ReraGenie IDRG-KA-21401

Builder

  • NamePuravankara Limited
  • Entity typeCompany
  • CINL45200KA1986PLC051571
  • GSTIN29AAACP2550R1ZX
  • Authorized SignatoryJatin Ujjini C S
  • CeoAbhishek Kapoor
  • DirectorsNani R Choksey, Ashish Puravankara
  • Project HeadKarthikeyan
  • Other registrations26 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredNov 2023PromisedMay 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Nov 2023
  • Promised completion31 May 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed131 files

Current status

85%125 of 147 units booked
73.9%Of the estimated cost spent so far

Figures as on 8 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Provident Deansgate Phase 1---1470147

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 15 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 88%.

Building: 64% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)88%
Retaining wall (All types)Not applicable
RCC or MS Framed structure88%
Masonry Construction88%
Plastering inside , outside & Ceiling53%
Joinery: Doors, Windows, Ventilators etc53%
Basic work of Water supply, Sanitary and Electrification8%
Dadoing, Skirting, Flooring, Tiles work (All types)88%
Railing and Grill fixing88%
Electrification, Water supply and Sanitary Finishing8%
Painting49%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work49%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes79%
LiftsYes79%
Corridor/LobbiesYes79%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes79%
Outer WallYes79%
Open parking areasYes79%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area30,445 sq m
Named landowners4
LandownerVillageDistrict
Puravankara Limited--
Puravankara Limited--
Puravankara Limited--
130/1 Ulsoor Road--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 131.88 cr
Cost incurredRs 97.43 cr
Spent of the estimate73.88%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 131.88 crRs 78.03 cr
On-site expenditure-Site Overhead-Rs 8.86 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrban Frame Private Limited
EngineerH P Yogesh
Chartered AccountantV D S R & CO LLP

Litigation declaredYes

The promoter declares litigation on this registration. The case records are in the filed documents.

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed131

As listed on the registration, under the names the promoter filed them with; the newest 80 of 131 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/041123/006373 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Deangate-1 RERA Form4 Dec25.pdf8 Jul 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Deansgate Phase 1 Architect Certificate Dec25.pdf8 Jul 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Deansgate-1 Engineer Certificate Dec25.pdf8 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Deansgate Phase 1 RERA Form 4 Mar26.pdf8 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Deansgate 1 Architect Certificate Mar26.pdf8 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4,Deansgate,ph-1.pdf8 Jul 2026
Financials 2020-21File: PL Consol Financials 31-Mar-20 (Compressed).pdf20 Oct 2023
Financials 2021-22File: PL-Audited Financial Statements-Consol-Mar-21.pdf20 Oct 2023
Financials 2022-23File: PGEPPL_Signed Financials_Mar 2022_compressed.pdf20 Oct 2023
Bank StatementFile: 777705752023 70% AC.pdf20 Oct 2023
Balance sheet FundFile: 22 Balance Sheet.pdf20 Oct 2023
CA Certificate Form 1File: CA Form 1.pdf20 Oct 2023
Litigation AffidavitFile: Litigation Affidavit.pdf20 Oct 2023
Area details clarificationFile: Area Details clarification.pdf20 Oct 2023
Carpet Area detailsFile: Carpet Area Details Deans Phase 1_compressed.pdf20 Oct 2023
CDPFile: DEANSGATE LOCATION IN CDP.pdf20 Oct 2023
Village MapFile: 9 - Village map.pdf20 Oct 2023
Building LicenceFile: BIAAPA.pdf20 Oct 2023
Development PlanFile: Development Plan.pdf20 Oct 2023
Site PlanFile: 1.jpg20 Oct 2023
Block 1 Ground,first,second terrace floor planFile: Block 1 Ground,first,second and terrace floor plan.jpg20 Oct 2023
Block 2 Ground,first,second terrace floor planFile: Block 2 Ground,first,second and Terrace floor plan.jpg20 Oct 2023
Block 2 Section and elevation PlanFile: Block 2 Section and Elevation Plan.jpg20 Oct 2023
Block 3 Ground,first,second terrace floor planFile: Block 3 Ground,first, second and terrace floor plan.jpg20 Oct 2023
Block 3 Section and elevation PlanFile: Block 3 Section and elevation plan-min.jpg20 Oct 2023
Block 4 and 6 Floor PlanFile: Block 4 & 6 Second and terrace floor plan.jpg20 Oct 2023
Block 5 and 7 Floor PlanFile: Block 5 & 7 Ground, first ,second and terrace floor plan.jpg20 Oct 2023
Block 5 and 7 Section PlanFile: Block 5 & 7 Section and elevation plan.jpg20 Oct 2023
Block 14 Floor PlanFile: Block 14 Ground,first,second terrace section and elevation plan.jpg20 Oct 2023
Block 1 Section and elevation planFile: Block 1 Section and elevation plan.jpg20 Oct 2023
PlanFile: Floor Plan 5-min (1).jpg20 Oct 2023
PlanFile: Floor Plan-min.jpg20 Oct 2023
Block 3 Section and elevation PlanFile: Section and elevation plan-min (1).jpg20 Oct 2023
Site plan demarcatedFile: Site boundary marked phase -1.pdf20 Oct 2023
Block wise DemarcatedFile: Block Wise Demarcated.pdf20 Oct 2023
STP Plan SignedFile: STP PLAN.pdf20 Oct 2023
Land cost guideline costFile: Guidline Value Self Attested.pdf20 Oct 2023
AOSFile: Deansgate-ATS Final (2).pdf20 Oct 2023
AffidavitFile: Sec 3 Affidavit.pdf20 Oct 2023
Brief Estimated Cost of ConstructionFile: Budget signed estimated Cost.pdf20 Oct 2023
KSPCB NOCFile: KSPCB Attested.pdf20 Oct 2023
BESCOM NOCFile: BESCOM NOC Deansgate.pdf20 Oct 2023
SEIAAFile: SEAIAA Attested.pdf20 Oct 2023
Water NOCFile: Water NOC Attested.pdf20 Oct 2023
Airport NOCFile: Airport NOC Attested.pdf20 Oct 2023
Allotment LetterFile: Allotment Letter (8).pdf20 Oct 2023
Change of Land UseFile: CLU.pdf20 Oct 2023
Club House PlanFile: Club House Floor plan.jpg20 Oct 2023
RTC, survey 37/2-
Mutation, survey 37/2-
Encumbrance Certificate, survey 37/2-
Conversion/Alienation Order, survey 37/2-
Sale/Title/Gift Deed, survey 37/2-
Khatha, survey 37/2-
RTC, survey 37/4(Old Sy No 37/2)-
Mutation, survey 37/4(Old Sy No 37/2)-
Encumbrance Certificate, survey 37/4(Old Sy No 37/2)-
Conversion/Alienation Order, survey 37/4(Old Sy No 37/2)-
Sale/Title/Gift Deed, survey 37/4(Old Sy No 37/2)-
Khatha, survey 37/4(Old Sy No 37/2)-
RTC, survey 38/5(Old Sy No 38/2)-
Mutation, survey 38/5(Old Sy No 38/2)-
Encumbrance Certificate, survey 38/5(Old Sy No 38/2)-
Conversion/Alienation Order, survey 38/5(Old Sy No 38/2)-
Sale/Title/Gift Deed, survey 38/5(Old Sy No 38/2)-
Khatha, survey 38/5(Old Sy No 38/2)-
RTC, survey 40-
Mutation, survey 40-
Encumbrance Certificate, survey 40-
Conversion/Alienation Order, survey 40-
Sale/Title/Gift Deed, survey 40-
Khatha, survey 40-
Registration CertificateFile: CoI PL.PDF-
Organization StructureFile: Org chart 2022.xlsx-
Certificate issued by CA Form 1File: CA Form 1.pdf-
Certificate issued by Architect Form 2File: Architect.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engi.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Provident Woodfield130/1 Ulsoor RoadCompleted-No date filed

How this compares with Bengaluru Rural

85%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Provident Deansgate on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmProvident DeansgateOther 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: Puravankara Limited

Puravankara Limited has 27 registrations on RERA Karnataka, including Provident Deansgate and Provident Deansgate Phase 2. Its filings declare 5 earlier projects, 5 of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Provident Deansgate is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Provident Deansgate?

The registered promoter entity is Puravankara Limited, a company as per the filing. Its CIN L45200KA1986PLC051571 and GSTIN 29AAACP2550R1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Provident Deansgate?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Provident Deansgate?

The professionals named in the filing: Architect: Urban Frame Private Limited; Engineer: H P Yogesh; Chartered Accountant: V D S R & CO LLP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Provident Deansgate?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Provident Deansgate. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Provident Deansgate to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.