Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Provident Capella 2 is a Residential/Group Housing project by Provident Housing Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/190719/002702 on 19 Jul 2019. Possession is promised by 30 Jun 2025. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameProvident Capella 2
- TypeResidential/Group Housing
- Location
- Hosakote
- Bengaluru Rural
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/304/PR/190719/002702
- ReraGenie IDRG-KA-59895
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Jul 2019
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Sep 2024)
- Buildings3 building records
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | - | - | 88 |
| Tower 6 | - | - | - | 88 | 0 | 88 |
| Tower 7 | - | - | - | - | - | 169 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | Not applicable |
| Joinery: Doors, Windows, Ventilators etc | Not applicable |
| Basic work of Water supply, Sanitary and Electrification | Not applicable |
| Dadoing, Skirting, Flooring, Tiles work (All types) | Not applicable |
| Railing and Grill fixing | Not applicable |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | No | Not applicable |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Design Desk |
| Engineer | Base Engineering Services |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed51
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/190719/002702 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: PHL_ROC_Certificate Of Incorporation.pdf | - |
| RERA_Commencement Certificate | - |
| Site Plan | - |
| Approved Plans | - |
| Allotment Letter | - |
| Allotment Letter | - |
| RERA_Title_RTC | - |
| Sectional_and_Specs | - |
| Site Plan | - |
| Allotment Letter | - |
| Capella Brochure | - |
| Specifications | - |
| RERA_EC | - |
| 3_1 Affidavit (Capella_2) | - |
| Joint Affidavit_2 | - |
| RERA_Khata | - |
| JDA-566-18-19 bw | - |
| Conversions OM | - |
| Fire NOC | - |
| AAI | - |
| BESCOM | - |
| Water | - |
| KSPCB_Compressed | - |
| SEIAA_Comp | - |
| Unnamed document | - |
| Approved Plans | - |
| Approved Plans | - |
| Sectional_and_Specs | - |
| Legal Opinion (Samethanahalli) | - |
| Balance Sheet 2017 - 2018File: 2018 Bal Sheet.pdf | - |
| Balance Sheet 2016 - 2017File: 2017 Bal Sheet.pdf | - |
| Balance Sheet 2015 - 2016File: 2016 Bal Sheet.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: 2018 PandL.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: 2017 PandL.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 2016 PandL.pdf | - |
| Director's Report 2017 - 2018File: 2018 (PHL) Directors Report.pdf | - |
| Director's Report 2016 - 2017File: 2017 (PHL) Directors Report.pdf | - |
| Director's Report 2015 - 2016File: 2016 (PHL) Directors Report.pdf | - |
| Cash Flow Statement 2017 - 2018File: 2018 Cash Flow.pdf | - |
| Cash Flow Statement 2016 - 2017File: 2017 Cash Flow.pdf | - |
| Auditor's Report 2017 - 2018File: 2018 Aud Report.pdf | - |
| Auditor's Report 2016 - 2017File: 2017 Aud Report.pdf | - |
| Auditor's Report 2015 - 2016File: 2016Auditors Report.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: PHL - ITR V Mar-18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: PHL - ITR V Mar-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: PHL - ITR V Mar-16.pdf | - |
| RERA_Form_B_Capella_2 | - |
| Prospectus/BrochureFile: Provident Capella - Brochure_30th Jul 2019.pdf | - |
| Advertisement Copy 1File: Capella Full page ad - TOI_8th Dec.pdf | - |
| Advertisement Copy 2File: Capella half page ad - TOI_21st Dec 2019.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1250_304_PR_190719_002702.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Provident Capella 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 22 registered projects within 2 km.
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
Pashmina Brookwoods
Shashwati Realty Pvt Ltd
Godrej Royale Woods
Godrej Projects North Star LLP
Prestige Jindal City-Phase II
PRESTIGE SOUTHCITY HOLDINGS
Provident Botanico
Provident Housing Limited
See every Bengaluru Rural project, with the district possession charts
Builder: Provident Housing Limited
Provident Housing Limited has 12 registrations on RERA Karnataka, including Provident Capella 1 and Provident Capella 2. Its filings declare 6 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Provident Capella 2 is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Provident Capella 2?
The registered promoter entity is Provident Housing Limited, a company as per the filing. Its CIN U45200KA2008PLC048273 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Provident Capella 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Provident Capella 2?
The professionals named in the filing: Architect: Design Desk; Engineer: Base Engineering Services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Provident Capella 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback