ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / PRISM CITY YELLOW

Registered No litigation declared Residential / Group Housing project

PRISM CITY YELLOW

By SWASTIK BUILDTECH

RG-MH-44573 · RERA P52100054020 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 15.00 crore secured on the land, in favour of TRUHOME FINANCE LTD

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

PRISM CITY YELLOW is a Residential / Group Housing project by SWASTIK BUILDTECH in Pune, Maharashtra, registered with MahaRERA as P52100054020 on 19 Dec 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NamePRISM CITY YELLOW
  • TypeResidential / Group Housing
  • Location
    • GANPATRAO KALJE MALA
    • CHARHOLI BK
    • CHARHOLI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054020
  • ReraGenie IDRG-MH-44573

Builder

  • NameSWASTIK BUILDTECH
  • Entity typePartnership
  • PartnersBHAGYASHRI BHARATKUMAR PATEL, JAGDISHBHAI VIRJIBHAI GORANI AKA PATEL, PARSHOTTAMBHAI DHANJIBHAI PATEL, ARVIND KANTILAL PATEL, PRAVINBHAI KANJIBHAI PATEL
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredDec 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Dec 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed123 files

Current status

100.0%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

A: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed126

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots126
Closed/Covered1
Open Space125

Land and ownership19

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,580 sq m
Land owned byThe promoter, with other names on the file
Named landowners19
Encumbrance on the landDeclared present
Charge in favour ofTRUHOME FINANCE LTD
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on4 Nov 2025
LandownerVillageDistrict
REKHA RAMRAO KALAJECHARHOLIPune
SOMESHWAR RAMRAO KALAJECHARHOLIPune
MONIKA RAMRAO KALAJECHARHOLIPune
SEEMA GULABRAO KALAJECHARHOLIPune
DNYANESHWARI GULABRAO KALAJECHARHOLIPune
RAMESHWAR GULAB KALAJECHARHOLIPune
JUI GULABRAO KALAJECHARHOLIPune
JAYASHREE SHANTARAM KALAJECHARHOLIPune
VISHWESHWAR SHANTARAM KALAJECHARHOLIPune
ALANKA SHANTARAM KALAJECHARHOLIPune
AKSHADA SHANTARAM KALAJECHARHOLIPune
KUSUM VINAYAK KALAJECHARHOLIPune
SIDDHESHWAR VINAYAK KALAJECHARHOLIPune
PARAMESHWAR VINAYAK KALAJECHARHOLIPune
SONALI VINAYAK KALAJECHARHOLIPune
VINAYAK GANPAT KALJECHARHOLIPune
GULAB GANPAT KALJECHARHOLIPune
SHANTARAM GANPAT KALJECHARHOLIPune
RAMRAO GANPAT KALJECHARHOLIPune

Approvals and building plan

Sanctioning authorityPimpri chinchwad Municipal corporation
Permissible FSI10476.24
Proposed, not sanctioned4,476 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSai Mangal Bldg S No 634 Shop No 5 6 7 Pacharne Vasti Near BP Petrol Pump Wagholi Pune Maharashtra 412207
Estimated costRs 34.00 cr
Cost incurredRs 34.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
ANARs 31.50 crRs 31.50 cr
-NARs 2.50 crRs 2.50 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDREAM SPACE ARCHITECTS
EngineerGAURAV PATEL
EngineerJEEVAN CHHAGAN SAWANT
Chartered AccountantMANATU KUMBHAR
Chartered AccountantNAVNATH BHAKARE
PartnerRole in project
SWASTIK BUILDTECH-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04122518541Dec 2025 → Dec 2026

Reason as filed by the promoterThe main reason for delay to complet project in non availabilty of different labour agencies and secondary cause is delayed process of getting approvals from planning authorities.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate-30-06-2026 (1).pdf22 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate -30-06-2026 (1).pdf22 Jul 2026
Withdrawal Update Form 3File: form 3 yellow_0001 (1).pdf22 Jul 2026
Withdrawal Update Form 1File: Form No 1 QPR-4 FY 25-26 Yellow_0001.pdf16 May 2026
Withdrawal Update Form 2File: Form No 2 QPR-4 25-26 Yellow_0001.pdf16 May 2026
Withdrawal Update Form 3File: CA Cert Yellow Q 4 25-26.pdf16 May 2026
Withdrawal Update Form 1File: form1.pdf18 Feb 2026
Withdrawal Update Form 2File: Form2.pdf18 Feb 2026
Withdrawal Update Form 3File: form3.pdf18 Feb 2026
Withdrawal Update Form 1File: FORM 1 2025-26 Q2.pdf1 Dec 2025
Withdrawal Update Form 2File: FORM 2 2025-26 Q2.pdf1 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q2 25-26_0001.pdf1 Dec 2025
Form 1File: FORM-1 2023-24 Q3.pdf30 Nov 2025
Form 2File: FORM-2 2023-24 Q3.pdf30 Nov 2025
Form 3File: FORM-3 2023-24 Q3.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2023-24 Q3.pdf30 Nov 2025
Form 1File: FORM-1 2023-24 Q4.pdf30 Nov 2025
Form 2File: FORM-2 2023-24 Q4.pdf30 Nov 2025
Form 3File: FORM-3 2023-24 Q4.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2023-24 Q4.pdf30 Nov 2025
Form 1File: FORM-1 2024-25 Q1.pdf30 Nov 2025
Form 2File: FORM-2 2024-25 Q1.pdf30 Nov 2025
Form 3File: FORM-3 2024-25 Q1.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q1.pdf30 Nov 2025
Form 1File: FORM-1 2024-25 Q2.pdf30 Nov 2025
Form 2File: FORM-2 2024-25 Q2.pdf30 Nov 2025
Form 3File: FORM-3 2024-25 Q2.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q2.pdf30 Nov 2025
Form 1File: FORM-1 2024-25 Q3.pdf30 Nov 2025
Form 2File: FORM-2 2024-25 Q3.pdf30 Nov 2025
Form 3File: FORM-3 2024-25 Q3.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q3.pdf30 Nov 2025
Form 1File: FORM-1 2024-25 Q4.pdf30 Nov 2025
Form 2File: FORM-2 2024-25 Q4.pdf30 Nov 2025
Form 3File: FORM-3 2024-25 Q4.pdf30 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q4.pdf30 Nov 2025
Form 2A (FY 2023-2024)File: Form 2 A 23-24 Yellow.pdf30 Nov 2025
Form 5 (FY 2023-2024)File: FORM-5 2023-24.pdf30 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 2024-25.pdf30 Nov 2025
Withdrawal Update Form 1File: Q1-Form-1-24-25_0001.pdf18 Nov 2025
Withdrawal Update Form 2File: Q1-Form-2-2024-25_0001.pdf18 Nov 2025
Withdrawal Update Form 3File: FORM 3 Q2 25-26_0001.pdf18 Nov 2025
Form 2A (FY 2024-2025)File: FORM ZA FOR Q 24-25_0001.pdf14 Oct 2025
Form 1File: Form 1 - 25-26 Q1_0001.pdf2 Aug 2025
Form 2File: Foirm 2- 25-26-Q1_0001.pdf2 Aug 2025
Form 3File: Form 3- 25-26 Q1_0001.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclouser of sold units_0001.pdf2 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q 4 FY-2024-2025.pdf22 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q 4 FY-2024-2025.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q 4 FY-2024-2025.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q-3 2024-2025_0001.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Q-3 2024-2025_0001.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Q-3 2024-2025_0001.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-FY-2024-25_0001.pdf26 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From-3-FY-2024-25_0001.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-FY-2024-25_0001.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5_0001.pdf26 Nov 2024
Declaration about Commencement CertificateFile: Commencement Decleration revised.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate revised.pdf9 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate revised.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate revised.pdf9 Oct 2024
Declaration about Commencement CertificateFile: Commencement Decleration revised.pdf9 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate revised.pdf9 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Certificate.pdf7 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Certificate.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q1-Form-1-24-25_0001.pdf25 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q1-Form-2-2024-25_0001.pdf25 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q1-Form-3-2024-25_0001.pdf25 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Prism City Yellow Separate Bank Account detail final_0001.pdf28 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Yellow Seperate Bank Acccount_0001.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Yellow Form-1.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Yellow Form-2.pdf27 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Yellow Form-3.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Prism City Yellow Form-1.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Prism City Yellow Form-2.pdf16 Apr 2024
Layout approvalFile: scan (1).pdf29 Mar 2024
Building plan approvalFile: scan (2).pdf29 Mar 2024
Building plan approvalFile: scan (3).pdf29 Mar 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRISM CITY YELLOW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARHOLI BK13,700+ in Pune

2 kmPRISM CITY YELLOWCompleted 76Lapsed / revoked 35Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 176 registered projects within 2 km.

Builder: SWASTIK BUILDTECH

SWASTIK BUILDTECH has 3 registrations on MahaRERA, including PRISM CITY GREEN and PRISM CITY YELLOW. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PRISM CITY YELLOW is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRISM CITY YELLOW?

The registered promoter entity is SWASTIK BUILDTECH, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRISM CITY YELLOW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRISM CITY YELLOW?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRISM CITY YELLOW?

The professionals named in the filing: Architect: DREAM SPACE ARCHITECTS; Engineer: GAURAV PATEL; Engineer: JEEVAN CHHAGAN SAWANT; Chartered Accountant: MANATU KUMBHAR; Chartered Accountant: NAVNATH BHAKARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRISM CITY YELLOW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRISM CITY YELLOW. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRISM CITY YELLOW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.