Completed No litigation declared Residential / Group Housing project

PRISM CITY GREEN

By SWASTIK BUILDTECH

RG-MH-79719 · RERA P52100053211 · Last updated on MahaRERA portal: 8 Aug 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 2 months
  • 1 extension taken
  • Rs 12.00 crore secured on the land, in favour of capri global capital limited

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2026Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
42 of 78Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

PRISM CITY GREEN is a Residential / Group Housing project by SWASTIK BUILDTECH in Pune, Maharashtra, registered with MahaRERA as P52100053211 on 23 Oct 2023. The registration is recorded completed; possession was promised by 25 Feb 2026. The completion date has moved by 2 months from the original filing. 36 of the 78 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePRISM CITY GREEN
  • TypeResidential / Group Housing
  • Location
    • GANPATRAO KALJE MALA
    • NEAR CHARHOLI PHATA
    • Charoli
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100053211
  • ReraGenie IDRG-MH-79719

Builder

  • NameSWASTIK BUILDTECH
  • Entity typePartnership
  • PartnersPRAVINBHAI KANJIBHAI PATEL, BHAGYASHRI BHARATKUMAR PATEL, JAGADISHBHAI VIRJIBHAI GORANI AKA PATEL, PARSHOTTAMBHAI DHANJIBHAI PATEL, ARVIND KANTILAL PATEL
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredOct 2023First promiseDec 2025Revised toFeb 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Oct 2023
  • Promised completion25 Feb 2026
  • Revised completionRevised to 25 Feb 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed134 files

Current status

46%36 of 78 units booked
100.0%Work done, per cost certificate

Figures as on 8 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A - WINGNA10840040
B - WINGNA10838038

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

A - WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B - WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed290

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots290
Closed/Covered290
BuildingClosed/CoveredTotal
A - WING149149
B - WING141141

Land and ownership5

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,600 sq m
Land owned byNot the promoter
Named landowners5
Encumbrance on the landDeclared present
Charge in favour ofcapri global capital limited
Secured amountRs 12.00 crore
CERSAI search filedYes
Declared on6 Nov 2025
LandownerVillageDistrict
TEJAS KALURAM KALJECHARHOLIPune
KALURAM PANDURANG KALJECHARHOLIPune
LAXMIBAI KALURAM KALJECHARHOLIPune
SUVARNA RAMDAS MHALASKARBhoyarePune
BAYADABAI KALURAM KALJECHARHOLIPune

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal Corporation
Permissible FSI10396.88
Proposed, not sanctioned10,396 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIGADI,PUNE,PUNE,411044
Estimated costRs 35.00 cr
Cost incurredRs 35.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
A - WINGNARs 16.00 crRs 16.00 cr
B - WINGNARs 16.00 crRs 16.00 cr
-NARs 3.00 crRs 3.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANJALI ARBAT
EngineerGAURAV PATEL
EngineerSANKET DAULAT BHOSALE
Chartered AccountantMANATU KUMBHAR
Chartered AccountantPANKAJ PATIL
PartnerRole in project
SWASTIK BUILDTECH-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA01042620527Dec 2025 → Feb 2026

Reason as filed by the promoterThe project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with require

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12603650Abhishek Vijay GunjalSWASTIK BUILDTECH12/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Nov 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Occupancy Certificate with OC confirmation.pdf8 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf6 Aug 2026
Withdrawal Update Form 1File: Architect Cerificate.pdf11 May 2026
Withdrawal Update Form 2File: Engineer Cerificate.pdf11 May 2026
Withdrawal Update Form 3File: CA Cerificate.pdf11 May 2026
Withdrawal Update Form 1File: Formgreen.pdf18 Apr 2026
Withdrawal Update Form 2File: Form2 Q3 25-26 Green_0001.pdf18 Apr 2026
Withdrawal Update Form 3File: FORM-3 2025-26 Q2.pdf18 Apr 2026
Withdrawal Update Form 1File: Formgreen.pdf19 Feb 2026
Withdrawal Update Form 2File: Form2 Q3 25-26 Green_0001.pdf19 Feb 2026
Withdrawal Update Form 3File: Form3 Q3 25-26 Green_0001.pdf19 Feb 2026
Withdrawal Update Form 1File: FORM-1 2025-26 Q2.pdf1 Dec 2025
Withdrawal Update Form 2File: FORM-2 2025-26 Q2.pdf1 Dec 2025
Withdrawal Update Form 3File: FORM-3 2025-26 Q2.pdf1 Dec 2025
Commencement certificateFile: COMMENCEMENT CERTIFICATE-30-03-2024_11zon.pdf28 Nov 2025
Withdrawal Update Form 1File: FORM-1 2025-26 Q2.pdf28 Nov 2025
Withdrawal Update Form 2File: FORM-2 2025-26 Q2.pdf28 Nov 2025
Withdrawal Update Form 3File: FORM-3 2025-26 Q2.pdf28 Nov 2025
Form 1File: FORM-1 2023-24 Q3.pdf27 Nov 2025
Form 2File: FORM-2 2023-24 Q3.pdf27 Nov 2025
Form 3File: FORM-3 2023-24 Q3.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2023-24 Q3.pdf27 Nov 2025
Form 1File: FORM-1 2023-24 Q4.pdf27 Nov 2025
Form 2File: FORM-2 2023-24 Q4.pdf27 Nov 2025
Form 3File: FORM-3 2023-24 Q4.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2023-24 Q4.pdf27 Nov 2025
Form 1File: FORM-1 2024-25 Q1.pdf27 Nov 2025
Form 2File: FORM-2 2024-25 Q1.pdf27 Nov 2025
Form 3File: FORM-3 2024-25 Q1.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q1.pdf27 Nov 2025
Form 1File: FORM-1 2024-25 Q2.pdf27 Nov 2025
Form 2File: FORM-2 2024-25 Q2.pdf27 Nov 2025
Form 3File: FORM-3 2024-25 Q2.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q2.pdf27 Nov 2025
Form 1File: FORM-1 2024-25 Q3.pdf27 Nov 2025
Form 2File: FORM-2 2024-25 Q3.pdf27 Nov 2025
Form 3File: FORM-3 2024-25 Q3.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD 2024-25 Q3.pdf27 Nov 2025
Form 2A (FY 2023-2024)File: FORM-2A 2023-24.pdf27 Nov 2025
Form 5 (FY 2023-2024)File: FORM-5 2023-24.pdf27 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 2024-25.pdf27 Nov 2025
Form 2A (FY 2024-2025)File: FORM 2A FOR Q24-25_0001.pdf14 Oct 2025
Form 1File: Form 1 Q 4 FY-2024-2025.pdf2 Aug 2025
Form 2File: Form 2 Q 4 FY-2024-2025.pdf2 Aug 2025
Form 3File: Form 3 Q 4 FY-2024-2025.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Desclouser of sold units_0001.pdf2 Aug 2025
Form 1File: Form 1 -2025-26_0001.pdf2 Aug 2025
Form 2File: Form 2025-26_0001.pdf2 Aug 2025
Form 3File: Form 3 2025-26_0001.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclouser of Q1_0001.pdf2 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q 3 2024-2025_0001.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Q 3 2024-2025_0001.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Q 3 2024-2025_0001.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Q2-2024-25_0001.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From-2-Q2-2024-25_0001.pdf26 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Q1-2024-25__0001.pdf7 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Q1-2024-25_0001_0001.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Q1-2024-25_0001.pdf7 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Green Form 3.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Green Form 1.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Green Form 2.pdf27 Apr 2024
Layout approvalFile: FSI Stetement.pdf16 Apr 2024
Building plan approvalFile: scan (2).pdf16 Apr 2024
Building plan approvalFile: scan (3).pdf16 Apr 2024
Layout approvalFile: scan (4).pdf16 Apr 2024
Building plan approvalFile: scan (6) a2.pdf16 Apr 2024
Building plan approvalFile: scan (7).pdf16 Apr 2024
Building plan approvalFile: scan (8).pdf16 Apr 2024
Copy of Layout Approval (in case of layout)File: FSI Stetement.pdf16 Apr 2024
Copy of Layout Approval (in case of layout)File: scan (4).pdf16 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: scan (2).pdf16 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: scan (3).pdf16 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: scan (6) a2.pdf16 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: scan (7).pdf16 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: scan (8).pdf16 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf16 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: scan (5) -a2.pdf16 Apr 2024
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf16 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: 20240315070933_compressed.pdf29 Mar 2024
Layout approvalFile: scan 112 Layout Plan_compressed.pdf23 Mar 2024

How this compares with Pune

46%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 2 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRISM CITY GREEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR CHARHOLI PHATA13,700+ in Pune

2 kmPRISM CITY GREENCompleted 76Lapsed / revoked 36Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 192 registered projects within 2 km.

Builder: SWASTIK BUILDTECH

SWASTIK BUILDTECH has 3 registrations on MahaRERA, including PRISM CITY GREEN and PRISM CITY YELLOW. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PRISM CITY GREEN is delayed beyond 25 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRISM CITY GREEN?

The registered promoter entity is SWASTIK BUILDTECH, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRISM CITY GREEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PRISM CITY GREEN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PRISM CITY GREEN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRISM CITY GREEN?

The professionals named in the filing: Architect: ANJALI ARBAT; Engineer: GAURAV PATEL; Engineer: SANKET DAULAT BHOSALE; Chartered Accountant: MANATU KUMBHAR; Chartered Accountant: PANKAJ PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRISM CITY GREEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRISM CITY GREEN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRISM CITY GREEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.