Home / Browse projects / Raigarh, Maharashtra / PRAKASH TOWER

Registered Litigation declared Others project

PRAKASH TOWER

By JAI BUILDERS AND DEVELOPERS

RG-MH-18917 · RERA P52000077868 · Last updated on MahaRERA portal: 6 Oct 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jul 2031Possession promisedmoved 4 months from the original
1 of 11Construction stages donefurthest along: Basement (if any), 75%
20 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

PRAKASH TOWER is a Others project by JAI BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000077868 on 7 Nov 2024. Possession is promised by 31 Jul 2031. The completion date has moved by 4 months from the original filing. 12 of the 32 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NamePRAKASH TOWER
  • TypeOthers
  • Location
    • PLOT NO. 37 & 37C
    • SECTOR 12
    • KAMOTHE
    • Kamothe
    • Panvel
    • Raigarh
    • 410209
  • Pincode410209
  • RERA no.P52000077868
  • ReraGenie IDRG-MH-18917

Builder

  • NameJAI BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAHFJ6741J1Z1
  • PartnersJAYKUMAR PRAKASHBHAI PATEL, RAJESHKUMAR MULCHAND CHAVALA, RAHUL KANIYALAL KHANEJA, JETHANAND MEHRUMAL JAGWANI

Key dates

this monthRegisteredNov 2024First promiseMar 2031Revised toJul 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Nov 2024
  • Promised completion31 Jul 2031
  • Revised completionRevised to 31 Jul 2031 (originally 31 Mar 2031)
  • Buildings1 building record
  • Documents filed64 files

Current status

38%12 of 32 units booked
9.3%Work done, per cost certificate

Figures as on 6 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRAKASH TOWERNA7725732

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 75%.

PRAKASH TOWER: 16% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered65
Open Space53

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,786 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPanvel Muncipal Corporation
Permissible FSI8500.0
Proposed, not sanctioned2,143 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.38,39 PATEL HERITAGE,PLOT NO.15 AND 17 SECTOR 7, KHARGHAR NAVI MUMBAI 410210
Estimated costRs 36.27 cr
Cost incurredRs 3.37 cr
Work done9.29%
BuildingWingEstimatedIncurred
PRAKASH TOWERNARs 34.00 crRs 3.37 cr
-NARs 2.27 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESTINATION ARCHITECTURE INTERIOR DESIGNS
EngineerKunal Dattatrey Jadhav
EngineerSHRAVANI CONSULTANTS
Chartered AccountantPJPJ & ASSOCIATES
Chartered AccountantPiyush Ghatliya & Co
PartnerRole in project
JAI BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52000077868/WarMar 2031 → Jul 2031

Reason as filed by the promoterNA

Litigation declared1

CaseCourtStatus
400014/2016/2016District Court Raigad AlibagOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2031

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 DAID-RR-597-26-27-L9 2026-09-30.pdf6 Oct 2026
Withdrawal Update Form 2File: Form 2 30--09-2026.pdf6 Oct 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 30-09-26.pdf6 Oct 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-25 sign.pdf3 Oct 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-26 sign.pdf3 Oct 2026
Form 5 (FY 2025-2026)File: Form 5- Prakash Tower FY 25-26.pdf3 Oct 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE L8 2026-06-30.pdf7 Aug 2026
Withdrawal Update Form 2File: Form 2 Prakash Tower 30-06-2026.pdf7 Aug 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 30-06-2026.pdf7 Aug 2026
Withdrawal Update Form 1File: Form 1 31-03-2026.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 31-03-2026.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 31-03-2026 sign_compressed.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 Prakash Tower 30-6-2025 Sign.pdf4 Feb 2026
Withdrawal Update Form 1File: Form 1 Prakash Tower 30-9-2025.pdf4 Feb 2026
Withdrawal Update Form 1File: Form 1 Prakash Tower 31-12-2025.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2 Prakash Tower 30-6-2025.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2 Prakash Tower 30-9-2025.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2 Prakash Tower 30-9-2025.pdf4 Feb 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 30-6-2025.pdf4 Feb 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 30-9-2025.pdf4 Feb 2026
Withdrawal Update Form 3File: Form 3 Prakash Tower 31-12-2025.pdf4 Feb 2026
Form 5 (FY 2024-2025)File: Form 5- Prakash Tower FY 24-25.pdf16 Oct 2025
Form 1File: FORM 1 jay q4.pdf11 Jun 2025
Form 2File: Form 2 jay q4.pdf11 Jun 2025
Form 3File: Form 3_Prakash Tower_13-05-2025.pdf11 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold jay q4.pdf11 Jun 2025
Self-declaration of Quarterly ProgressFile: Declaration of QPR jay q4.pdf11 Jun 2025
Copy of the legal title reportFile: Legal Tittle Report 04-02-2025.pdf16 Apr 2025
Copy of the legal title reportFile: Search Report 04-02-2025.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_F.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Feb 2025
Other - FinanceFile: Declaration to MahaRERA regarding project completion date.pdf6 Nov 2024
Other - TechnicalFile: ANNEXURE A JAI.pdf29 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement - New.pdf29 Oct 2024
Proforma of Agreement for saleFile: Agreement for Sale (RERA) - Prakash Tower-New.pdf29 Oct 2024
Other - TechnicalFile: CC Verification for Development permission granted by PMC.pdf18 Oct 2024
Proforma of Allotment letterFile: Allotment Letter - Prakash Tower.pdf16 Oct 2024
Other - LegalFile: Agreement to Lease of Plot No 37 Sector 12 Kamothe (1).pdf15 Oct 2024
Other - LegalFile: Agreement to Lease of Plot No 37C Sector 12 Kamothe (1).pdf15 Oct 2024
Building plan approvalFile: CC DWG - PLOT 37, 37C, SECTOR 12, KAMOTHE (1).pdf13 Oct 2024
Layout approvalFile: CC DWG - PLOT 37, 37C, SECTOR 12, KAMOTHE (1).pdf13 Oct 2024
PAN CardFile: Pan - Jai Builders and Developers.pdf13 Oct 2024
Copy of the legal title reportFile: Legal Title Report - Prakash Tower.pdf13 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Finance.pdf13 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Legal.pdf13 Oct 2024
Copy of Layout Approval (in case of layout)File: CC DWG - PLOT 37, 37C, SECTOR 12, KAMOTHE (1).pdf13 Oct 2024
Declaration in FORM BFile: Form B.pdf13 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE - 13-09-2024.pdf13 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA CERTIFICATE - 17-09-2024.pdf13 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER CERTIFICATE - 17-09-2024.pdf13 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC COPY - PLOT 37, 37C, SECTOR 12, KAMOTHE.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: CC DWG - PLOT 37, 37C, SECTOR 12, KAMOTHE (1).pdf13 Oct 2024
Other - LegalFile: Tripartite Agreement of Plot No 37 Sector 12 Kamothe.pdf13 Oct 2024
Other - LegalFile: Tripartite Agreement of Plot No 37C Sector 12 Kamothe.pdf13 Oct 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf13 Oct 2024
CERSAI detailsFile: CERSAI Asset Based Search Report.pdf13 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A as per order 56-2024.pdf13 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf13 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter - Finance.pdf13 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter - Legal.pdf13 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf13 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B as per order 56-2024_ NEW.pdf13 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured OR Unsecured finance availed.pdf13 Oct 2024

How this compares with Raigarh

38%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 4 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRAKASH TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SECTOR 12, KAMOTHE5,900+ in Raigarh

Builder: JAI BUILDERS AND DEVELOPERS

JAI BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including PRAKASH TOWER. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if PRAKASH TOWER is delayed beyond 31 Jul 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRAKASH TOWER?

The registered promoter entity is JAI BUILDERS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAHFJ6741J1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRAKASH TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRAKASH TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRAKASH TOWER?

The professionals named in the filing: Architect: DESTINATION ARCHITECTURE INTERIOR DESIGNS; Engineer: Kunal Dattatrey Jadhav; Engineer: SHRAVANI CONSULTANTS; Chartered Accountant: PJPJ & ASSOCIATES; Chartered Accountant: Piyush Ghatliya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAKASH TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAKASH TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAKASH TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.