Red flags
- Completion date moved by 19 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pradhan Mantri Awas Yojana-Dudulgaon is a Residential / Group Housing project by PIMPRI CHINCHWAD MUNICIPAL CORPORATION in Pune, Maharashtra, registered with MahaRERA as P52100052195 on 31 Jul 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 19 months from the original filing.
At a glance
Project
- NamePradhan Mantri Awas Yojana-Dudulgaon
- TypeResidential / Group Housing
- Location
- Dudulgaon
- Alandi Rural
- Khed
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052195
- ReraGenie IDRG-MH-81867
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Jul 2023
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 23 Nov 2025)
- Buildings5 building records
- Documents filed65 files
Current status
Figures as on 4 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing-A | NA | 16 | 0 | 0 | 0 | 0 |
| Wing-B | NA | 16 | 0 | 0 | 0 | 0 |
| Wing-C | NA | 16 | 0 | 0 | 0 | 0 |
| Wing-D | NA | 16 | 0 | 0 | 0 | 0 |
| Wing-E | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 4 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
25 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 90%.
Wing-A79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Wing-B79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Wing-C79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Wing-D79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Wing-E79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 4 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1961
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing-A | 179 | 222 | 401 |
| Wing-B | 179 | 259 | 438 |
| Wing-C | 179 | 250 | 429 |
| Wing-D | 179 | 165 | 344 |
| Wing-E | 179 | 170 | 349 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing-A | NA | Rs 28.58 cr | Rs 26.37 cr |
| Wing-B | NA | Rs 28.58 cr | Rs 26.37 cr |
| Wing-C | NA | Rs 28.58 cr | Rs 26.37 cr |
| Wing-D | NA | Rs 28.58 cr | Rs 26.37 cr |
| Wing-E | NA | Rs 28.58 cr | Rs 26.37 cr |
| - | NA | Rs 13.15 cr | Rs 1.17 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kiran Kale |
| Engineer | Satish Marathe |
| Engineer | Creations Engineers Pvt. Ltd. |
| Chartered Accountant | P R A S S & Associates LLP |
| Chartered Accountant | Saurabh lalwani & Associates |
| Partner | Role in project |
|---|---|
| PIMPRI CHINCHWAD MUNICIPAL CORPORATION | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThese project under the Pradhan Mantri Awas Yojana Scheme so Funds delay from central and state government.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2023-2024)File: Form 5 2023-24 Dudulgaon.pdf | 4 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 4 Jun 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 13 May 2026 |
| Withdrawal Update Form 1File: Architects Certificate.pdf | 13 May 2026 |
| Withdrawal Update Form 2File: Engineers Certificate.pdf | 13 May 2026 |
| Withdrawal Update Form 2File: Engineers Certificate.pdf | 13 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 13 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 13 May 2026 |
| Form 1File: Architect Certificate .pdf | 11 Nov 2025 |
| Form 2File: Engineers Certificate.pdf | 11 Nov 2025 |
| Form 3File: Form 3.pdf | 11 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold inventory Dudulgaon.pdf | 11 Nov 2025 |
| Form 1File: Architect Certificate.pdf | 4 Jul 2025 |
| Form 2File: Engineers Certificate.pdf | 4 Jul 2025 |
| Form 3File: Form 3.pdf | 4 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory Building Wise.pdf | 4 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_11zon.pdf | 3 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 3 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_11zon.pdf | 3 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Dudulgaon_11zon.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dudulgaon_11zon.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dudulgaon_11zon.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dudulgaon_11zon.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_11zon.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_11zon (1).pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf | 16 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 16 Jul 2024 |
| PAN CardFile: PAN Card.pdf | 25 Jul 2023 |
| Layout approvalFile: Layout 1_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Amenity Shopping Centre_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Typical Floor Plan_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Terrace Floor Plan_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Typical Refuge_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Section A B_compressed.pdf | 21 Jul 2023 |
| Layout approvalFile: Layout 2_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Ground Parking Floor_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: Elevation_compressed.pdf | 21 Jul 2023 |
| Copy of the legal title reportFile: Copy of Legal Title Report.pdf | 21 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: 11zon_merged-PDF.pdf | 21 Jul 2023 |
| Details of encumbrances concerned to LegalFile: 11zon_merged-PDF.pdf | 21 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Layout 1_compressed.pdf | 21 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Layout 2_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Ground Parking Floor_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Elevation_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Section A B_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Amenity Shopping Centre_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Typical Floor Plan_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Terrace Floor Plan_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Typical Refuge_compressed.pdf | 21 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Dudulgaon Building Permission.pdf | 21 Jul 2023 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 21 Jul 2023 |
| Declaration in FORM BFile: Form B.pdf | 21 Jul 2023 |
| CERSAI detailsFile: Declaration Cesai.pdf | 21 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Upload.pdf | 21 Jul 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organizations.pdf | 21 Jul 2023 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf | 21 Jul 2023 |
| Proforma of Agreement for saleFile: Model agreement Dudulgaon_11zon.pdf | 21 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Deaclaration about Separate Bank account.pdf | 21 Jul 2023 |
| Deviation Report with respect to Allotment letterFile: No deviation Model copy of Allotment.pdf | 21 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: No deviation Model copy of Agreement.pdf | 21 Jul 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| BSUP PROJECT | S No 174 P at Vetal Nagar Chinchwad Pune 411033 | 1,792 | Completed | Apr 2018 | Apr 2017 |
| EWS Project | Chikhali Sector 17 AND 19 Chikhali PCMC Pune 411062 | 8,652 | Completed | Mar 2018 | Oct 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Pradhan Mantri Awas Yojana-Dudulgaon on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dudulgaon13,700+ in Pune
Filed coordinates, straight-line distance. 136 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: PIMPRI CHINCHWAD MUNICIPAL CORPORATION
PIMPRI CHINCHWAD MUNICIPAL CORPORATION has 7 registrations on MahaRERA, including PRADHAN MANTRI AWAS YOJANA- CHARHOLI and Pradhan Mantri Awas Yojana-Pimpri R. No 77. Its filings disclose 7 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Pradhan Mantri Awas Yojana-Dudulgaon is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pradhan Mantri Awas Yojana-Dudulgaon?
The registered promoter entity is PIMPRI CHINCHWAD MUNICIPAL CORPORATION, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pradhan Mantri Awas Yojana-Dudulgaon?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Pradhan Mantri Awas Yojana-Dudulgaon?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pradhan Mantri Awas Yojana-Dudulgaon?
The professionals named in the filing: Architect: Kiran Kale; Engineer: Satish Marathe; Engineer: Creations Engineers Pvt. Ltd.; Chartered Accountant: P R A S S & Associates LLP; Chartered Accountant: Saurabh lalwani & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pradhan Mantri Awas Yojana-Dudulgaon?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback