Completed No litigation declared Residential / Group Housing project

PRADHAN MANTRI AWAS YOJANA- CHARHOLI

By PIMPRI CHINCHWAD MUNICIPAL CORPORATION

RG-MH-74358 · RERA P52100017367 · Last updated on MahaRERA portal: 27 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
35 of 77Construction stages doneacross 7 buildings; furthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

PRADHAN MANTRI AWAS YOJANA- CHARHOLI is a Residential / Group Housing project by PIMPRI CHINCHWAD MUNICIPAL CORPORATION in Pune, Maharashtra, registered with MahaRERA as P52100017367 on 9 Aug 2018. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NamePRADHAN MANTRI AWAS YOJANA- CHARHOLI
  • TypeResidential / Group Housing
  • Location
    • Charholi
    • charholi kh
    • Khed
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100017367
  • ReraGenie IDRG-MH-74358

Builder

  • NamePIMPRI CHINCHWAD MUNICIPAL CORPORATION
  • Entity typePublic Authority
  • Executive EngineerAnagha Pathak
  • Other registrations6 more →
  • Completed4 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredAug 2018First promiseDec 2022Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Aug 2018
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
  • Buildings7 building records
  • Documents filed71 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 1NA160000
Wing 2NA160000
Wing 3NA160000
Wing 4NA160000
Wing 5NA160000
Wing 6NA160000
Wing 7NA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

35 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Internal walls, at 95%.

Wing 184%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Wing 264%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing 357%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing 427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing 575%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Wing 680%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Wing 776%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed724

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots724
Closed/Covered724
BuildingClosed/CoveredTotal
Wing 1112112
Wing 2112112
Wing 3112112
Wing 45252
Wing 5112112
Wing 6112112
Wing 7112112

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI48355.2
Proposed, not sanctioned48,355 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPune Mumbai Highway Pimpri Chowk, Pune, MH, 411018

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKiran Kale
EngineerGulabrao Bhilare
Chartered AccountantP R A S S & Associates LLP
PartnerRole in project
PIMPRI CHINCHWAD MUNICIPAL CORPORATION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100015123Dec 2022 → Dec 2023

Reason as filed by the promoterDelay due to 2nd wave of covid 19 & Project workers going to village & home due to covid 19.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2024

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: PMAY Charholi FORM B for RERA.pdf27 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_11zon.pdf26 Mar 2025
Certificates of CA (Form 3)File: Form 3_11zon.pdf26 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_11zon.pdf26 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf26 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Charholi_11zon.pdf26 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Project.pdf2 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architect certificate charholi.pdf28 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Charholi Building No 4 Completion.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Charholi.pdf1 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf1 Jan 2024
CERSAI detailsFile: CERSAI_Search_Report_200260084937_For_Asset_Based_Search_10_02_2023_15_22_18_358.pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Charholi CA Letter Sign_1_11zon.pdf10 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate Charholi.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 15-01-23.pdf31 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 15-01-23.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: RERA form 2A certificate 1 FY 2020 Charholi.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA form 2A certificate 2 FY 2021 Charholi.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RERA form 2A certificate 3 FY 2022 Charholi.pdf31 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account.pdf24 Jan 2023
Details of encumbrances concerned to FinanceFile: No encumbrances concerned to legal.pdf19 Jan 2023
Details of encumbrances concerned to LegalFile: No encumbrances concerned to legal.pdf19 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Charholi Revise Building Permission_11zon.pdf19 Jan 2023
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf19 Jan 2023
Proforma of Agreement for saleFile: Proforma of Agreement LH.pdf19 Jan 2023
Deviation Report with respect to Allotment letterFile: No deviation model copy of allotment letter.pdf19 Jan 2023
Deviation Report with respect to model copy of AgreementFile: No deviation model copy of agreement.pdf19 Jan 2023
Certificates of CA (Form 3)File: Form 3 Q4 1MB.pdf21 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Charholi.pdf6 May 2022
Certificates of CA (Form 3)File: Form 3 Q3.pdf30 Apr 2022
Certificates of CA (Form 3)File: Form 3 FY 21-22 Q1_compressed (1).pdf30 Sep 2021
Certificates of CA (Form 3)File: RERA Certificate Form3- Charholi Q4_compressed.pdf7 Jul 2021
Certificates of CA (Form 3)File: FORM 3-compressed.pdf25 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 19-20.pdf25 Mar 2021
Certificates of CA (Form 3)File: FORM3 Q2 Charholi_compressed.pdf23 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: Form3- Charholi_Q1.pdf1 Oct 2020
Certificates of CA (Form 3)File: Form3- Charholi_Q1.pdf1 Oct 2020
Certificates of CA (Form 3)File: Form 3.pdf16 Jul 2020
Certificates of CA (Form 3)File: Form 3.pdf16 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: From 5.pdf24 Jan 2020
Certificates of CA (Form 3)File: form3 Q2_compressed.pdf3 Jan 2020
Certificates of CA (Form 3)File: Form 3 Charoli_compressed.pdf30 Sep 2019
Certificates of CA (Form 3)File: RERA Certificate form 3_Q 4- scanned_compressed.pdf5 Jul 2019
Certificates of CA (Form 3)File: Charoli Form 3_Q3V1.pdf29 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Jan 2019
Certificates of CA (Form 3)File: Form 3.pdf1 Jan 2019
Building plan approvalFile: WING 1 ELEVATION SECTION -6.pdf21 Jul 2018
Building plan approvalFile: WING 2 ELEVATION SECTION -9.pdf21 Jul 2018
Building plan approvalFile: WING 3 ELEVATION SECTION -12.pdf21 Jul 2018
Building plan approvalFile: WING 4 ELEVATION SECTION-23.pdf21 Jul 2018
Building plan approvalFile: WING 5 ELEVATION SECTION -15.pdf21 Jul 2018
Building plan approvalFile: WING 6 ELEVATION SECTION -18.pdf21 Jul 2018
Building plan approvalFile: WING 7 ELEVATION SECTION -21.pdf21 Jul 2018
Layout approvalFile: LAYOUT PLAN- 1.pdf21 Jul 2018
PAN CardFile: PCMC PAN pdf.pdf21 Jul 2018
Copy of the legal title reportFile: Search Report.pdf21 Jul 2018
Details of encumbrancesFile: Non Encumbrances.pdf21 Jul 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN- 1.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 1 ELEVATION SECTION -6.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 2 ELEVATION SECTION -9.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 3 ELEVATION SECTION -12.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 4 ELEVATION SECTION-23.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 5 ELEVATION SECTION -15.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 6 ELEVATION SECTION -18.pdf21 Jul 2018
Building Plan Approval (IOD)File: WING 7 ELEVATION SECTION -21.pdf21 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_1.pdf21 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_2.pdf21 Jul 2018
Declaration in FORM BFile: RERA Affidavit Form B.pdf21 Jul 2018
Certificates of CA (Form 3)File: RERA Form 3.pdf21 Jul 2018
Proforma of Allotment letterFile: Draft Agreement for Sale.pdf21 Jul 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
BSUP PROJECTS No 174 P at Vetal Nagar Chinchwad Pune 4110331,792CompletedApr 2018Apr 2017
EWS ProjectChikhali Sector 17 AND 19 Chikhali PCMC Pune 4110628,652CompletedMar 2018Oct 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRADHAN MANTRI AWAS YOJANA- CHARHOLI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Charholi13,700+ in Pune

Builder: PIMPRI CHINCHWAD MUNICIPAL CORPORATION

PIMPRI CHINCHWAD MUNICIPAL CORPORATION has 7 registrations on MahaRERA, including PRADHAN MANTRI AWAS YOJANA- CHARHOLI and Pradhan Mantri Awas Yojana-Pimpri R. No 77. Its filings disclose 7 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PRADHAN MANTRI AWAS YOJANA- CHARHOLI is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRADHAN MANTRI AWAS YOJANA- CHARHOLI?

The registered promoter entity is PIMPRI CHINCHWAD MUNICIPAL CORPORATION, a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRADHAN MANTRI AWAS YOJANA- CHARHOLI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRADHAN MANTRI AWAS YOJANA- CHARHOLI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRADHAN MANTRI AWAS YOJANA- CHARHOLI?

The professionals named in the filing: Architect: Kiran Kale; Engineer: Gulabrao Bhilare; Chartered Accountant: P R A S S & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRADHAN MANTRI AWAS YOJANA- CHARHOLI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRADHAN MANTRI AWAS YOJANA- CHARHOLI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRADHAN MANTRI AWAS YOJANA- CHARHOLI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.