Home / Browse projects / Raigarh, Maharashtra / POOJA NAGAR

Registration lapsed No litigation declared Others project

POOJA NAGAR

By SHREE LAXMI NARAYAN DEVELOPERS

RG-MH-10324 · RERA P52000004776 · Last updated on MahaRERA portal: 26 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 39 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
41 of 88Construction stages doneacross 8 buildings; furthest along: Internal walls, 78%
1Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

POOJA NAGAR is a Others project by SHREE LAXMI NARAYAN DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000004776 on 9 Aug 2017. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 39 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePOOJA NAGAR
  • TypeOthers
  • Location
    • near neral station
    • Neral
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000004776
  • ReraGenie IDRG-MH-10324

Builder

  • NameSHREE LAXMI NARAYAN DEVELOPERS
  • Entity typePartnership
  • PartnersNIKHIL S UDANI, MAHESH G PATEL, SHANTILAL G PATEL, NARENDRA V CHANDRA, JAIRAM D KESWANI, VISHWANATH R PANVELKAR, RAJESH D SHAH, ASHALATA V PANVELKAR

Key dates

19 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Dec 2021)
  • Buildings8 building records
  • Documents filed55 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING FNA60000
WING GNA60000
WING HNA60000
WING ANA60000
WING BNA60000
WING CNA60000
WING DNA60000
WING ENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 26 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

41 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Internal walls, at 78%.

WING F57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING G0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING H0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises78%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING D60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING E48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40
BuildingClosed/CoveredTotal
WING F55
WING G55
WING H55
WING A55
WING B55
WING C55
WING D55
WING E55

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,500 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jul 2025

Approvals and building plan

Sanctioning authorityraigadh zillaparisad, alibaug
Permissible FSI6975.83
Proposed, not sanctioned6,976 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchm g road,ghatkopar west

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESTINATION ARCHITECTURE INTERIOR DESIGN
EngineerS V PATEL & ASSOCIATES
Chartered Accountantpratik
PartnerRole in project
SHREE LAXMI NARAYAN DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000010904Dec 2021 → Dec 2022

Reason as filed by the promoterDue to Scarcity of Labour and Material in corona pandemics our project has been delayed therefor we kindly request you to accept our extension .

EXT52000013856Dec 2021 → Mar 2025

Reason as filed by the promoterDue to the covid and not sufficient funds arranged.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000199276Suresh Sayaji KorabuShree Laxmi Narayan Developers07/12/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form-1_architect certificate_31-3-2025.pdf26 Jul 2025
Form 2File: form- 2.pdf26 Jul 2025
Form 3File: from 3_compressed.pdf26 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf26 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf25 Mar 2025
Certificates of CA (Form 3)File: form 3.pdf25 Mar 2025
Certificates of CA (Form 3)File: from 3.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_SIGNED.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FROM 2 SIGNED.pdf25 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_.pdf6 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_.pdf6 Mar 2024
Certificates of CA (Form 3)File: Form 3_.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: kalpesh dalvi 2.pdf2 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: kalpesh dalvi 3.pdf2 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: kalpesh dalvi 2.pdf31 Mar 2023
Disclosure of sold/ booked inventoryFile: S 6.pdf31 Mar 2023
Declaration in FORM BFile: Form B-Laxminarayan.pdf23 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A.pdf23 Mar 2023
Disclosure of sold/ booked inventoryFile: sold unsoled inventory.pdf23 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21) (3).pdf15 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate_Form 1_.pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg_certificate_31-03-2021.pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg certificate_form no II_svp assocoates_2021-22.pdf13 Feb 2023
Certificates of CA (Form 3)File: FORM-3_31-03-2021.pdf13 Feb 2023
Certificates of CA (Form 3)File: FORM-3_31-12-2022.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5_31-03-2022.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5_31-03-2021.pdf11 Feb 2023
Deviation Report with respect to model copy of AgreementFile: FORM-5_31-03-2022.pdf11 Feb 2023
Declaration about Commencement CertificateFile: Commencement declaration.pdf16 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance.pdf16 Sep 2021
Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf16 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA CERTIFICATE_Form5.pdf5 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certifiate_ .pdf4 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: engg_certificate_31-03-2020.pdf4 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ca audit report_2018-19.pdf29 Jun 2021
Certificates of CA (Form 5)File: Shree Laxmi Narayan.pdf28 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect cert_28-03-2018 (1).pdf6 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect cert_28-03-2018 (1).pdf6 Dec 2018
Certificates of CA (Form 5)File: CA AUTIT CERTIFICATE_31-03-2018_ SHREE LAXMI NARAYAN DEVELOPERS.pdf3 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: CC_ZP ORDER _.pdf28 Mar 2018
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: allotment letter AND sale deed.pdf28 Jul 2017
Details of encumbrancesFile: encumbrances certificate.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf27 Jul 2017
Declaration in FORM BFile: shree laxmi narayan_form B.pdf18 Jul 2017
Layout approvalFile: LAY OUT PLAN.pdf17 Jul 2017
Building plan approvalFile: IOD.pdf17 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf17 Jul 2017
Copy of Layout Approval (in case of layout)File: LAY OUT PLAN.pdf17 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf17 Jul 2017
PAN CardFile: pan_laxmi narayan.pdf12 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 39 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep POOJA NAGAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Neral5,900+ in Raigarh

2 kmPOOJA NAGARCompleted 17Lapsed / revoked 17Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: SHREE LAXMI NARAYAN DEVELOPERS

SHREE LAXMI NARAYAN DEVELOPERS has 1 registration on MahaRERA, including POOJA NAGAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that POOJA NAGAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if POOJA NAGAR is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of POOJA NAGAR?

The registered promoter entity is SHREE LAXMI NARAYAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in POOJA NAGAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against POOJA NAGAR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for POOJA NAGAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at POOJA NAGAR?

The professionals named in the filing: Architect: DESTINATION ARCHITECTURE INTERIOR DESIGN; Engineer: S V PATEL & ASSOCIATES; Chartered Accountant: pratik. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in POOJA NAGAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About POOJA NAGAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save POOJA NAGAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.