Home / Browse projects / Pune, Maharashtra / PLATINUM PRIDE

Registered No litigation declared Others project

PLATINUM PRIDE

By SHREE MAULI DEVELOPERS

RG-MH-69524 · RERA P52100052347 · Last updated on MahaRERA portal: 21 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 21 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 21 months from the original
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 75%
43 of 54Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

PLATINUM PRIDE is a Others project by SHREE MAULI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100052347 on 14 Aug 2023. Possession is promised by 31 Mar 2028. The completion date has moved by 21 months from the original filing. 11 of the 54 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NamePLATINUM PRIDE
  • TypeOthers
  • Location
    • PUNE SATARA ROAD
    • GUJARWADI KATRAJ
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411046
  • Pincode411046
  • RERA no.P52100052347
  • ReraGenie IDRG-MH-69524

Builder

  • NameSHREE MAULI DEVELOPERS
  • Entity typePartnership
  • PartnersSHRIKRUSHNA DINAKR DHARPALE, SUJATA RAJENDRA JAGTAP, AJAY ANANTA KARANJKAR, PRATIK RAJENDRA SONAWANE, BHUSHAN SAMBHAJI BHOSALE
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2023First promiseJun 2026Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2023
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed84 files

Current status

20%11 of 54 units booked
60.3%Work done, per cost certificate

Figures as on 21 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PLATINUM PRIDENA77252954

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

PLATINUM PRIDE: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.55%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 21 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership12

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners12
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jun 2026
LandownerVillageDistrict
VIASHALI PRAVIN KOKATEPune (M Corp.)Pune
DATTATRAY BABURAO DHUMALPune (M Corp.)Pune
PREMKUMAR BHIKOBA TALEKARPune (M Corp.)Pune
ROHINI SHRIKRUSHNA DHARPALEPune (M Corp.)Pune
BHAGYASHREE SATISH SHINDEPune (M Corp.)Pune
NAMDEV ATMARAM CHAVANNasrapurPune
MACHINDRA BABAJI WALUNJKhadakwadiPune
SANJAY PANDURANG WALGUDEMargasaniPune
AVTARSINGH NIRMALSINGH PANESARPune (M Corp.)Pune
PRADIP TULSHIRAM BATHEDivalePune
SANDIP APPASO SHINDEMurumSatara
SWATI YUWARAJ PATILGadhinglajKolhapur

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI913.0
Proposed, not sanctioned913 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKATRAJ PUNE 411046
Estimated costRs 6.00 cr
Cost incurredRs 3.62 cr
Work done60.33%
BuildingWingEstimatedIncurred
PLATINUM PRIDENARs 5.40 crRs 3.26 cr
-NARs 60.00 lakhRs 36.20 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectWALHEKAR AND ASSOCIATES
EngineerPOPAT MOHAN SHELKE
Engineersandeep laxman chougale
Chartered AccountantSIDDHI WARULE
Chartered AccountantTANAJI CHORGHE
PartnerRole in project
SHREE MAULI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30062621624Jun 2026 → Mar 2028

Reason as filed by the promoterDue to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/03/2028 to complete the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: f1.pdf21 Sep 2026
Withdrawal Update Form 2File: f2.pdf21 Sep 2026
Withdrawal Update Form 3File: f3.pdf21 Sep 2026
Withdrawal Update Form 1File: Architect Certificate signed.pdf3 Sep 2026
Withdrawal Update Form 2File: Engineer Cert.pdf3 Sep 2026
Withdrawal Update Form 3File: June 2025 form 3.pdf3 Sep 2026
Form 2A (FY 2025-2026)File: FORM 2A (2).pdf3 Sep 2026
Form 1File: f1.pdf27 Jun 2026
Form 2File: f2.pdf27 Jun 2026
Form 3File: f3.pdf27 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold.pdf27 Jun 2026
OthersFile: Revised Layout plan_compressed.pdf27 Jun 2026
Form 1File: f1.pdf27 Jun 2026
Form 2File: f2.pdf27 Jun 2026
Form 3File: f3.pdf27 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold.pdf27 Jun 2026
OthersFile: Revised Building plan_compressed.pdf27 Jun 2026
Form 1File: f1.pdf27 Jun 2026
Form 2File: f2.pdf27 Jun 2026
Form 3File: f3.pdf27 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold.pdf27 Jun 2026
OthersFile: Revised Building plan1_compressed.pdf27 Jun 2026
Form 1File: F1.pdf8 Jun 2026
Form 2File: F2.pdf8 Jun 2026
Form 3File: F3.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD.pdf8 Jun 2026
OthersFile: Scan_20260307_150600_compressed.pdf8 Jun 2026
Form 1File: form 1 platinum pride_page-0001.pdf27 May 2026
Form 2File: MARCH 2026 FORM 2_page-0001.pdf27 May 2026
Form 3File: March 2026 form 3.pdf27 May 2026
Disclosure of Sold and Booked InventoryFile: sold unsold (3).pdf27 May 2026
Form 1File: FORM 1 SEP 2025.pdf22 Apr 2026
Form 3File: form 3 sep 2025.pdf22 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf22 Apr 2026
Form 2File: form 2 sep 2025.pdf22 Apr 2026
Form 1File: New Doc 04-21-2026.pdf21 Apr 2026
Form 2File: form 2 March 2025 (2).pdf21 Apr 2026
Form 3File: form 3 March 2025.pdf21 Apr 2026
Disclosure of Sold and Booked InventoryFile: image (5).pdf21 Apr 2026
Form 1File: New Doc 04-21-2026.pdf21 Apr 2026
Form 2File: JUNE 2025 FORM 2.pdf21 Apr 2026
Form 3File: June 2025 form 3.pdf21 Apr 2026
Disclosure of Sold and Booked InventoryFile: image (3).pdf21 Apr 2026
Form 1File: New Doc 04-21-2026.pdf21 Apr 2026
Form 2File: DECEMBER 2025 FORM 2.pdf21 Apr 2026
Form 3File: form 3 dec 2025.pdf21 Apr 2026
Disclosure of Sold and Booked InventoryFile: image.pdf21 Apr 2026
Form 1File: New Doc 04-21-2026.pdf21 Apr 2026
Form 2File: MARCH 2026 FORM 2.pdf21 Apr 2026
Form 3File: March 2026 form 3.pdf21 Apr 2026
Disclosure of Sold and Booked InventoryFile: image (6).pdf21 Apr 2026
Form 1File: New Doc 04-21-2026.pdf21 Apr 2026
Form 2File: MARCH 2026 FORM 2.pdf21 Apr 2026
Form 3File: March 2026 form 3.pdf21 Apr 2026
Disclosure of Sold and Booked InventoryFile: image (6).pdf21 Apr 2026
Proforma of Agreement for saleFile: AGREEMENT DRAFT.pdf6 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Mauli Dev Signed.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory.pdf26 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate signed.pdf7 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert.pdf7 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Mauli Dev Signed.pdf7 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Revised_compressed.pdf17 Jul 2023
Declaration about Commencement CertificateFile: Declaration About Comencement Cert latest.pdf13 Jul 2023
Declaration in FORM BFile: Form B Declaration.pdf6 Jul 2023
PAN CardFile: PAN Shree Mauli Developers.pdf30 Jun 2023
Copy of the legal title reportFile: Search and Title Report updated.pdf24 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations All Partners.pdf1 Jun 2023
Proforma of Agreement for saleFile: Proforma Agreement Part 1.pdf1 Jun 2023
Proforma of Agreement for saleFile: Proforma Agreement Part 2.pdf1 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report agreement and Allotment Letter.pdf1 Jun 2023
Layout approvalFile: PLan LAYOUT_compressed.pdf20 May 2023
Building plan approvalFile: Parking and Floor Plan_compressed.pdf20 May 2023
Details of encumbrances concerned to FinanceFile: Declaration Encumbrunces Finance and Legal.pdf20 May 2023
Details of encumbrances concerned to LegalFile: Declaration Encumbrunces Finance and Legal.pdf20 May 2023
Copy of Layout Approval (in case of layout)File: PLan LAYOUT_compressed.pdf20 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Parking and Floor Plan_compressed.pdf20 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert.pdf20 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf20 May 2023
CERSAI detailsFile: Declaration CERSAI.pdf20 May 2023

How this compares with Pune

20%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 21 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PLATINUM PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GUJARWADI KATRAJ13,700+ in Pune

Builder: SHREE MAULI DEVELOPERS

SHREE MAULI DEVELOPERS has 2 registrations on MahaRERA, including SAI MAULI APARTMENT and PLATINUM PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PLATINUM PRIDE is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PLATINUM PRIDE?

The registered promoter entity is SHREE MAULI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PLATINUM PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PLATINUM PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PLATINUM PRIDE?

The professionals named in the filing: Architect: WALHEKAR AND ASSOCIATES; Engineer: POPAT MOHAN SHELKE; Engineer: sandeep laxman chougale; Chartered Accountant: SIDDHI WARULE; Chartered Accountant: TANAJI CHORGHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PLATINUM PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PLATINUM PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PLATINUM PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.