Piccadilly IV

By Royal Palms India Pvt. Ltd.

RG-MH-11626 · RERA P51800004140 · Last updated on MahaRERA portal: 16 Jan 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 92 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2019Possession promised92 months past this date
2 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
6Complaints at MahaRERAon this registration
Jump to the 26 documents Report an error

Piccadilly IV is a Others project by Royal Palms India Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004140 on 8 Aug 2017. Possession was promised by 28 Feb 2019 and is now 92 months past that date. The completion date has moved by 12 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NamePiccadilly IV
  • TypeOthers
  • Location
    • Aarey road
    • Goregaon
    • Borivali
    • Mumbai Suburban
    • 400065
  • Pincode400065
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004140
  • ReraGenie IDRG-MH-11626

Builder

  • NameRoyal Palms India Pvt. Ltd.
  • Entity typeCompany
  • ChairpersonAmir Ahmedally Nensey
  • Declared earlier projects1 →

Key dates

92 months past promisethis monthRegisteredAug 2017First promiseFeb 2018Revised toFeb 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Aug 2017
  • Promised completion28 Feb 2019
  • Revised completionRevised to 28 Feb 2019 (originally 28 Feb 2018)
  • Buildings1 building record
  • Documents filed26 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Piccadilly IVNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Piccadilly IV: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 16 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes95%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes20%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered1
Open Space44

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,384 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2384.25
Proposed, not sanctioned2,384 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBharat co op bank Mumbai ltd Town centre Mumbai 400059

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVinayak Lomate
PartnerRole in project
Royal Palms India Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000839Feb 2018 → Feb 2019

Reason as filed by the promoterDear Sir / Ma'am we want to apply for an extension for our project "Piccadilly IV". Date of completion mentioned earlier was 28/02/2018. This date was mentioned by mistake from our staff. Our project is scheduled to be completed on 28 February 2019. The revised completion date would be 28 February 2019. Kindly consider our request for an extension in completion date.

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000001346SAMIR KUMARAMIR NANCY26/10/2017
CC006000000078187Sudhir Diwakar RautRoyal Palms (India) Pvt. Ltd.21/02/2019
CC006000000161382Uma MasurkarMr. Muhammed Nensey03/11/2019
CC006000000171461Swapnaja S. PatkarRoyal Palms India Pvt. Ltd.08/11/2019
CC006000000429171SUDHIR DIWAKAR RAUTMr. Dilawar Nensey and Mr. Omer Nensey23/05/2024
CC12602628Sadhana Sunil MasurkarRoyal Palms India Pvt. Ltd.06/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Jun 2022

Documents filed26

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FORM 3_ROYALPALMS_19122018_01112022 (1).pdf16 Jan 2023
Certificates of CA (Form 3)File: FORM 3_ROYALPALMS_30042022_01112022 (1).pdf16 Jan 2023
Certificates of CA (Form 3)File: FORM 3_ROYALPALMS_26122018_01112022 (1).pdf16 Jan 2023
Certificates of CA (Form 5)File: Form 5_ 2018-19 (1).pdf16 Jan 2023
Certificates of CA (Form 5)File: Form 5_ 2017-18 (1).pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_ 2018-19 (1).pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_ 2019-20 (1).pdf16 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_ 2020-21 (1).pdf16 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2303013_OC_signed.pdf10 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1431851400NoteSheet_11530_signed.pdf11 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT CERTIFICATE.pdf11 Apr 2022
Layout approvalFile: Layout plan.pdf29 Jul 2017
Building plan approvalFile: IOD-min.pdf29 Jul 2017
PAN CardFile: PAN card - Royal Palms India Pvt Ltd.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate002-min.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrances details.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD-min.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: piccadilly 4 CC-min.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: service apt form 1-min.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer'sCertificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf29 Jul 2017
Certificates of CA (Form 5)File: RPIPL Cert in Form 5 of MahaRera.pdf29 Jul 2017
Proforma of Allotment letterFile: Picaddilly 4-FORMAT.pdf29 Jul 2017
Declaration in FORM BFile: Form - B009.pdf28 Jul 2017
Declaration in FORM BFile: Form - B010.pdf28 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Ruby IsleSurvey No 169 Aarey milk colony near unit no 26 Royal Palms Estate Goregaon East Mumbai 400065288CompletedSep 2013Late, Oct 2013

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Piccadilly IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon6,700+ in Mumbai Suburban

2 kmPiccadilly IVCompleted 41Lapsed / revoked 20Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 102 registered projects within 2 km.

Builder: Royal Palms India Pvt. Ltd.

Royal Palms India Pvt. Ltd. has 1 registration on MahaRERA, including Piccadilly IV. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Piccadilly IV shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Piccadilly IV is delayed beyond 28 Feb 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Piccadilly IV?

The registered promoter entity is Royal Palms India Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Piccadilly IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Piccadilly IV?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Piccadilly IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Piccadilly IV?

The professionals named in the filing: Architect: Vinayak Lomate. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Piccadilly IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Piccadilly IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Piccadilly IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.