Home / Browse projects / Pune, Maharashtra / PHOENIX RESIDENCY
PHOENIX RESIDENCY
RG-MH-27521 · RERA P52100034724 · Last updated on MahaRERA portal: 6 Aug 2024
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 22 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PHOENIX RESIDENCY is a Residential / Group Housing project by PHOENIX INFRASPACE in Pune, Maharashtra, registered with MahaRERA as P52100034724 on 20 Apr 2022. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NamePHOENIX RESIDENCY
- TypeResidential / Group Housing
- Location
- Alandi Road
- Porwal Park
- Haveli
- Pune
- 411006
- Pincode411006
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100034724
- ReraGenie IDRG-MH-27521
Builder
- NamePHOENIX INFRASPACE
- Entity typeOthers
- Named personRAMESH GULABCHAND PORWAL (HUF) THROUGH ITS KARTA RAMESH G PORWAL
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on20 Apr 2022
- Promised completion30 Dec 2024
- Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2023)
- Buildings1 building record
- Documents filed80 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PHOENIX RESIDENCY | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
PHOENIX RESIDENCY: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 6 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Group Consultants |
| Engineer | Sunil Thorat |
| Chartered Accountant | Sanjay Mehta |
| Partner | Role in project |
|---|---|
| PHOENIX INFRASPACE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have received First Building Sanction Plan on 28/09/2021. After getting said Sanction our architect noticed that there are some technicalities arose in the previous sanctioned building plans. Therefore we have applied for the same. After theses sanction, as per our project potential we have applied for third time to load purchased TDR. So there is reason for delayed date of Project completion now we requesting for Project extension till 30/12/2024
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Dislosure 30-06-2022.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 30-09-2022.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 31-12-2022.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 30-06-2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 30-09-2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 31-03-2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 31-03-2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 31-12-2023.pdf | 6 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Dislosure 30-06-2024.pdf | 6 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2022-23 Q1.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2022-23 Q2.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2022-23 Q3.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2022-23 Q4.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2023-24 Q1.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2023-24 Q2.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2023-24 Q3.pdf | 1 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY 2023-24 Q4.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate .pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate .pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate .pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate .pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate .pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate .pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate .pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate.pdf | 31 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert.pdf | 1 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: No Encrumbrance Certificate Legal Finance.pdf | 22 Jun 2024 |
| Details of encumbrances concerned to LegalFile: No Encrumbrance Certificate Legal Finance.pdf | 22 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Format -D.pdf | 22 Jun 2024 |
| Declaration in FORM BFile: Form B -Notary.pdf | 22 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 02 2022.pdf | 22 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 03 2024.pdf | 22 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 22 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf | 22 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf | 22 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold-Booked Inventory Word.pdf | 22 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other organisations.pdf | 22 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf | 22 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 22 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Acc.pdf | 22 Jun 2024 |
| PAN CardFile: PAN COPY.pdf | 3 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023 24.pdf | 3 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment letter.pdf | 3 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agr to sale.pdf | 3 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form No 2A Eng Cert.pdf | 30 May 2024 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE CERTIFICATE.pdf | 29 May 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE CERTIFICATE.pdf | 29 May 2024 |
| Proforma of Agreement for saleFile: FINAL ATS - PHOENIX INFRASPACE.pdf | 29 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: FORMAT D.pdf | 21 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A - DISCLOSURE OF INTEREST.pdf | 21 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DETAILS.pdf | 21 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM 2A YEAR 2022-23.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 2024.pdf | 22 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- 2024.pdf | 22 Mar 2024 |
| Declaration in FORM BFile: DECLARATION FORM B.pdf | 14 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD UNIT LIST.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FORM 3_compressed (1).pdf | 14 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-2023.pdf | 11 Mar 2024 |
| Copy of the legal title reportFile: COMPRERSSED SEARCH AND TITLE REPORT PHOENIX RESIDENCY.pdf | 11 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FORM 3_compressed (1).pdf | 11 Apr 2022 |
| Proforma of Allotment letterFile: FINAL PHOENIX RESIDENCEY AGREEEMENT TO SALE.pdf | 11 Apr 2022 |
| Details of encumbrancesFile: NON ENCUMBRANCE CERTIFICATE.pdf | 29 Mar 2022 |
| Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE DECLARATION FORM D.pdf | 29 Mar 2022 |
| Declaration in FORM BFile: DECLARATION FORM B.pdf | 29 Mar 2022 |
| CERSAI detailsFile: DECLARATION - CERSAI.pdf | 29 Mar 2022 |
| Building plan approvalFile: BUILDING PLAN_compressed.pdf | 14 Mar 2022 |
| Layout approvalFile: BUILDING PLAN_compressed.pdf | 14 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN_compressed.pdf | 14 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN_compressed.pdf | 14 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 14 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 80 filed documents as one ZIP, foldered, with a manifest
Keep PHOENIX RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Porwal Park13,700+ in Pune
Filed coordinates, straight-line distance. 16 registered projects within 2 km.
VAISHNAVI OURANOS
VAISHNAVI & OM CONSTRUCTION
Nandanvan
NG Rathi Construction Private Limited
KALPANA CO OP HSG SOC LTD - PHASE 1
Bramhacorp Limited
UTTAM TOWNSCAPE LIFE HUB A,A1,B
FORTUNE DEVELOPERS AND INFRASTRUCTURES
VRUNDAVAN A WING
NG Rathi Promoters
White House A
CITY ETHERNAL LLP
Builder: PHOENIX INFRASPACE
PHOENIX INFRASPACE has 1 registration on MahaRERA, including PHOENIX RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that PHOENIX RESIDENCY shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PHOENIX RESIDENCY is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PHOENIX RESIDENCY?
The registered promoter entity is PHOENIX INFRASPACE, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PHOENIX RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PHOENIX RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PHOENIX RESIDENCY?
The professionals named in the filing: Architect: Group Consultants; Engineer: Sunil Thorat; Chartered Accountant: Sanjay Mehta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PHOENIX RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback