Home / Browse projects / Bengaluru Rural, Karnataka / Pearl at Brigade Atmosphere
Pearl at Brigade Atmosphere
RG-KA-36053 · RERA PRM/KA/RERA/1250/303/PR/220207/004671 · Last updated on RERA Karnataka portal: 14 Jan 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 4 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Pearl at Brigade Atmosphere is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/220207/004671 on 7 Feb 2022. Possession is promised by 31 Dec 2025. 132 of the 132 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.
At a glance
Project
- NamePearl at Brigade Atmosphere
- TypeResidential/Group Housing
- Location
- Devanahalli
- Bengaluru Rural
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1250/303/PR/220207/004671
- ReraGenie IDRG-KA-36053
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on7 Feb 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings18 building records
- Documents filed87 files
Current status
Figures as on 14 Jan 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block - B | - | - | - | 2 | 0 | 2 |
| Block-B1 | - | - | - | 2 | 0 | 2 |
| Cluster - I | - | - | - | 8 | 0 | 8 |
| Cluster - J | - | - | - | 8 | 0 | 8 |
| Cluster - K | - | - | - | 8 | 0 | 8 |
| Cluster - L | - | - | - | 8 | 0 | 8 |
| Cluster - M | - | - | - | 8 | 0 | 8 |
| Cluster - N | - | - | - | 8 | 0 | 8 |
| Cluster - O | - | - | - | 8 | 0 | 8 |
| Cluster - P | - | - | - | 8 | 0 | 8 |
| Cluster - Q | - | - | - | 8 | 0 | 8 |
| Cluster - R | - | - | - | 8 | 0 | 8 |
| Cluster - S | - | - | - | 8 | 0 | 8 |
| Cluster - T | - | - | - | 8 | 0 | 8 |
| Cluster - U | - | - | - | 8 | 0 | 8 |
| Cluster - V | - | - | - | 8 | 0 | 8 |
| Cluster - W | - | - | - | 8 | 0 | 8 |
| Cluster - X | - | - | - | 8 | 0 | 8 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 14 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry construction: Bricks, Concrete blocks etc | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Painting | 100% |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | 100% |
Progress on shared amenities41
As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Internal Roads & Footpaths | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 100% |
| Gym | No | Not applicable |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 100% |
| Basement | No | Not applicable |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M.R Jaishankar | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 100.80 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 5.11 cr | - |
| On-site expenditure-Site Overhead | Rs 3.81 cr | - |
| On-site expenditure-Salaries of workers | Rs 16.48 lakh | - |
| On-site expenditure-Consultants Fees | Rs 6.61 lakh | - |
| Payment of taxes | Rs 4.41 lakh | - |
| Payment of Premiums | Rs 28,623 | - |
| Payment of cess | Rs 25,221 | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar.Abhay Itty Zachariah |
| Engineer | Vinod |
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 1566 | Sr. Civil Judge & JMFC, Devanahalli | - |
| 577 | Sr. Civil Judge & JMFC, Devanahalli | - |
| 659 | Sr. Civil Judge & JMFC, Devanahalli | - |
| 542 | Sr. Civil Judge & JMFC, Devanahalli | - |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed87
As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/220207/004671 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Pearl at Brigade Atmosphere - Form 4 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Pearl - Form 5 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Pearl - Form 6 - Q3.pdf | 14 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 14 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 14 Jan 2026 |
| Agreement for SaleFile: Pearl at Atmosphere - Proforma Sale Agreement.pdf | 3 Feb 2022 |
| Bank Account StatementFile: Bank Account Statement.pdf | 28 Dec 2021 |
| Bank Account opening formFile: Pearl at Brigade Atmoshphere - Bank Account Form.pdf | 20 Dec 2021 |
| Sale Deed for Sy No. 6/4File: Sale Deed.pdf | 20 Dec 2021 |
| Conversion Order for Sy No. 6/4File: Conversion Order.pdf | 20 Dec 2021 |
| Document to show Guideline Value of the PropertyFile: Guideline Value of the Property.pdf | 20 Dec 2021 |
| Notarized Joint Affidavit Cum DeclarationFile: Pearl at Brigade Atmosphere - JD Affidavit Cum Declaration.pdf | 20 Dec 2021 |
| Demarcation Plan specifying the proposed development area (38152 sq mts)File: Master Plan-Blown up plan.pdf | 20 Dec 2021 |
| Relinquishment DeedFile: Brigade Atmosphere - Relinquishment Deed.pdf | 20 Dec 2021 |
| KSPCB NOCFile: Pearl at Brigade Atmosphere - KSPCB.pdf | 20 Dec 2021 |
| Project Landowner DetailsFile: Land Owner Details.pdf | 20 Dec 2021 |
| Project Contractor DetailsFile: Contractor Details.pdf | 20 Dec 2021 |
| STP details in the ProjectFile: Feasibility Report on STP-Atmosphere.pdf | 20 Dec 2021 |
| Central Ground Water NOCFile: Pearl at Brigade Atmosphere - CGWA NOC.pdf | 20 Dec 2021 |
| Signed copy of Project SpecificationFile: Pearl at Brigade Atmosphere - Specification.pdf | 20 Dec 2021 |
| Promoter's reply to the queries raisedFile: Pearl at Brigade Atmosphere - List of Queries raised by RERA and Brigade Enterprises Limit | 20 Dec 2021 |
| CertificateFile: Certificate of Incorporation - BEL copy.pdf | - |
| Pearl at Brigade Atmosphere - Sanction Plans | - |
| Pearl at Brigade Atmosphere - Development Plan | - |
| Pearl at Brigade Atmosphere - Plans | - |
| Sale Deed Draft | - |
| Proforma Sale Agreement - Pearl at Atmosphere | - |
| Pearl at Brigade Atmosphere - Sale Deed and RTC | - |
| Pearl at Brigade Atmosphere - Section and Specification | - |
| Pearl at Brigade Atmosphere - Development Plan | - |
| Pearl at Brigade Atmosphere - Allotment Letter | - |
| Pearl at Brigade Atmosphere - RERA Brochure | - |
| Specification | - |
| Pearl at Brigade Atmosphere - Encumbrance Certificate | - |
| Pearl at Brigade Atmosphere - Notarised Affidavit for 3(1) Violation | - |
| JD Affidavit Cum Declaration | - |
| Brigade Atmosphere - E Khata | - |
| Brigade Atmosphere - JD | - |
| Pearl at Brigade Atmosphere - Conversion Orders | - |
| Pearl at Brigade Atmosphere - Conversion Orders | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Pearl at Brigade Atmosphere - AAI | - |
| Unnamed document | - |
| Pearl at Brigade Atmosphere - CGWA NOC | - |
| Pearl at Brigade Atmosphere - CFE | - |
| Pearl at Brigade Atmosphere - Environment Clearance | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Pearl at Brigade Atmosphere - Plans and Specification | - |
| Pearl at Brigade Atmosphere - Plans and Blownup Plan | - |
| Pearl at Brigade Atmosphere - Section and Specification | - |
| Pearl at Brigade Atmosphere - Conversion Orders | - |
| Pearl at Brigade Atmosphere - Title Opinion | - |
| Balance Sheet 2019 - 2020File: Balance Sheet - 2020-21 with CA UDIN.pdf | - |
| Balance Sheet 2018 - 2019File: Balance Sheet - 2019-20.pdf | - |
| Balance Sheet 2017 - 2018File: Balance Sheet - 2018-19.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: Profti and Loss - 2020-21.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Profti and Loss - 2019-20.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: Profti and Loss - 2018-19.pdf | - |
| Director's Report 2019 - 2020File: Board Report - 2020-21.pdf | - |
| Director's Report 2018 - 2019File: Board Report - 2019-20.pdf | - |
| Director's Report 2017 - 2018File: Board Report - 2018-19.pdf | - |
| Cash Flow Statement 2019 - 2020File: Cash Flow Statement - 2020-21.pdf | - |
| Cash Flow Statement 2018 - 2019File: Cash Flow Statement - 2019-20.pdf | - |
| Auditor's Report 2019 - 2020File: Auditors Report - 2020-21.pdf | - |
| Auditor's Report 2018 - 2019File: Auditors Report - 2019-20.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Brigade Bricklane | - | Ongoing | Sep 2022 | Not delivered |
| Brigade 7 Gardens | - | Ongoing | Jul 2022 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Rural
Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.
Keep Pearl at Brigade Atmosphere on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Rural650+ in Bengaluru Rural
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Ozone Urbana
Ozone Urbana Infra Developers Pvt Ltd
Pashmina Brookwoods
Shashwati Realty Pvt Ltd
Godrej Royale Woods
Godrej Projects North Star LLP
Prestige Jindal City-Phase II
PRESTIGE SOUTHCITY HOLDINGS
Provident Botanico
Provident Housing Limited
See every Bengaluru Rural project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.
Frequently asked questions
What are my rights if Pearl at Brigade Atmosphere is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Pearl at Brigade Atmosphere?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Pearl at Brigade Atmosphere?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Pearl at Brigade Atmosphere?
The professionals named in the filing: Architect: Ar.Abhay Itty Zachariah; Engineer: Vinod. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pearl at Brigade Atmosphere?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback