Home / Browse projects / Mumbai Suburban, Maharashtra / PARK RESIDENCY

Registration lapsed No litigation declared Others project

PARK RESIDENCY

By PAVAN SHETH AND ASSOCIATES AOP

RG-MH-63174 · RERA P51800011885 · Last updated on MahaRERA portal: 25 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 17 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 67%
1Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

PARK RESIDENCY is a Others project by PAVAN SHETH AND ASSOCIATES AOP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011885 on 31 Aug 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 17 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePARK RESIDENCY
  • TypeOthers
  • Location
    • HANUMAN TEKADI
    • DAHISAR
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011885
  • ReraGenie IDRG-MH-63174

Builder

  • NamePAVAN SHETH AND ASSOCIATES AOP
  • Entity typeOthers
  • Named personsAMAZON HOUSING AND INFRASTRUCTURE PVT LTD, PAVAN SHETH AND ASSOCIATES

Key dates

52 months past promisethis monthRegisteredAug 2017First promiseJan 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed71 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARK RESIDENCYNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 67%.

PARK RESIDENCY: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed63

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots63
Closed/Covered63

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,290 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10470.53
Proposed, not sanctioned10,324 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOHAMEDALI ROAD MUMBAI 400001

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHANTANOO RANE AND ASSOCIATES
PartnerRole in project
PAVAN SHETH AND ASSOCIATES AOP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009157Jan 2021 → Dec 2021

Reason as filed by the promoterWe have not completed our construction project work due to Covid-19 pandemic lock down, construction material have been disrupted as well as shortage of labour work force due to may have migrated back to their homes states.

Litigation declared3

CaseCourtStatus
2635/2015HIGH COURT OF JUDICATURE AT BOMBAYPENDING BEFORE HONORABLE BOMBAY HIGH COURT
548/2016MAHARASHTRA STATE CONSUMER DISPUTE REDRESSAL COMMISSIONPENDING BEFORE HONORABLE STATE CONSUMER FORUM
2635/2015HIGH COURT OF JUDICATURE AT BOMBAYTHE PETITION TO STAND DISPOSED OF ACCORDINGLY

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000023468Pandurang Namdev NalawadePavan Sheth & Associates AOP26/02/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Apr 2023

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FORM 3 1417 TO 31122021.pdf25 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT CERTIFICATE ON COMPLETION.pdf25 Apr 2023
Deviation Report with respect to Allotment letterFile: Proforma Allotment Letter-Park Residency.pdf15 Feb 2023
Deviation Report with respect to Allotment letterFile: Proforma Allotment Letter.pdf14 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC.pdf11 Jul 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Park Residency Soc Registration Certificate.pdf11 Jul 2022
Certificates of CA (Form 5)File: FORM5.pdf17 Jan 2019
Building plan approvalFile: scan 2.pdf6 Nov 2018
Building plan approvalFile: scan 2.pdf6 Nov 2018
Building plan approvalFile: scan 3.pdf6 Nov 2018
Building plan approvalFile: scan 1.pdf6 Nov 2018
Building plan approvalFile: scan 1.pdf6 Nov 2018
Building plan approvalFile: scan 2.pdf6 Nov 2018
Building plan approvalFile: scan 3.pdf6 Nov 2018
Building plan approvalFile: scan 4.pdf6 Nov 2018
Building plan approvalFile: scan 5.pdf6 Nov 2018
Building plan approvalFile: scan 6.pdf6 Nov 2018
Building plan approvalFile: scan 7.pdf6 Nov 2018
Building plan approvalFile: scan 8.pdf6 Nov 2018
Building plan approvalFile: scan 9.pdf6 Nov 2018
Building plan approvalFile: scan 10.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 2.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 2.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 3.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 1.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 1.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 2.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 3.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 4.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 5.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 6.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 7.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 8.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 9.pdf6 Nov 2018
Building Plan Approval (IOD)File: scan 10.pdf6 Nov 2018
Layout approvalFile: Scan-0002.pdf31 Jul 2017
Building plan approvalFile: scan-001.pdf31 Jul 2017
Building plan approvalFile: Scan-0005.pdf31 Jul 2017
Building plan approvalFile: Scan-0003.pdf31 Jul 2017
Building plan approvalFile: Scan-0004.pdf31 Jul 2017
Building plan approvalFile: Scan-0002.pdf31 Jul 2017
Building plan approvalFile: Scan-0006.pdf31 Jul 2017
Building plan approvalFile: Scan-0007.pdf31 Jul 2017
Building plan approvalFile: Scan-0008.pdf31 Jul 2017
Building plan approvalFile: Scan-0009.pdf31 Jul 2017
Building plan approvalFile: Scan-0010.pdf31 Jul 2017
Building plan approvalFile: Scan-0011.pdf31 Jul 2017
PAN CardFile: 02.pdf31 Jul 2017
PAN CardFile: 01.pdf31 Jul 2017
PAN CardFile: 03.pdf31 Jul 2017
Copy of the legal title reportFile: 04.pdf31 Jul 2017
Copy of the legal title reportFile: 05.pdf31 Jul 2017
Details of encumbrancesFile: 06.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Scan-0002.pdf31 Jul 2017
Building Plan Approval (IOD)File: scan-001.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0002.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0003.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0004.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0005.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0006.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0007.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0008.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0009.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0010.pdf31 Jul 2017
Building Plan Approval (IOD)File: Scan-0011.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 12.pdf31 Jul 2017
Declaration in FORM BFile: FORM B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 08.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM-3.pdf31 Jul 2017
Proforma of Allotment letterFile: compresspdf_apSvC4UW-ilovepdf-compressed.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 17 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARK RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DAHISAR6,700+ in Mumbai Suburban

2 kmPARK RESIDENCYCompleted 118Lapsed / revoked 71Other 179Dot size: filed unitsN

Filed coordinates, straight-line distance. 368 registered projects within 2 km.

Builder: PAVAN SHETH AND ASSOCIATES AOP

PAVAN SHETH AND ASSOCIATES AOP has 1 registration on MahaRERA, including PARK RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PARK RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARK RESIDENCY is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARK RESIDENCY?

The registered promoter entity is PAVAN SHETH AND ASSOCIATES AOP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARK RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARK RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARK RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARK RESIDENCY?

The professionals named in the filing: Architect: SHANTANOO RANE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.