Home / Browse projects / Mumbai Suburban, Maharashtra / PARK RESIDENCES
PARK RESIDENCES
By Gaiagen Technologies Private Limited
RG-MH-61585 · RERA P51800031874 · Last updated on MahaRERA portal: 2 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 23 months
- 5 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PARK RESIDENCES is a Others project by Gaiagen Technologies Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031874 on 22 Nov 2021. Possession was promised by 17 Dec 2024 and is now 22 months past that date. The completion date has moved by 23 months from the original filing. 92 of the 158 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NamePARK RESIDENCES
- TypeOthers
- Location
- C.T.S No. 918A
- Jaywant Sawant Road
- Dahisar West
- R/North Central Ward
- Dahisar West
- Borivali
- Mumbai Suburban
- 400068
- Pincode400068
- RERA no.P51800031874
- ReraGenie IDRG-MH-61585
Builder
- NameGaiagen Technologies Private Limited
- Entity typeCompany
- DirectorDevesh Birodkar
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Nov 2021
- Promised completion17 Dec 2024
- Revised completionRevised to 17 Dec 2024 (originally 31 Jan 2023)
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 2 Apr 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PARK RESIDENCES | NA | 20 | 15 | 143 | 15 | 158 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.
PARK RESIDENCES: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 99% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 2 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Common Areas and Amenities | Yes | 0% |
Parking filed166
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DA DESIGNS |
| Engineer | D.S. DEORA |
| Chartered Accountant | R M A & CO |
| Chartered Accountant | M R P & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Gaiagen Technologies Private Limited | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the current weather conditions we are facing hardship at site leading to delays in balance work completion. This is leading to further delays in the overall completion of the project. Due to above condition, we would request you to extend our project completion date by only 3 months i.e to 30/11/2023
Reason as filed by the promoterLabour shortage during festival season has delayed the balance works leading to further delay in the various permissions required for completion of the project. Due to the this condition we would request you to extend our project completion date by only 3 months i.e 31-08-2023
Reason as filed by the promoterWe have made an application dated 27-10-2023 to the MCGM for occupancy certificate of the project and we have not received any permission as on date. Due to the above condition, we would request you to extend our project completion date by only 2 months i.e. 31/01/2024.
Reason as filed by the promoterThe project is delayed due to no allotment / sale of flats as a result of Covid 19 pandemic leading to the shortage of funds and due to delay in permission from various authorities. Refer attached document
Reason as filed by the promoterWe have made an application dated 27-10-2023 to the MCGM for occupancy certificate of the project and we have received the complete occupancy certificate on 17-12-2024 and the same has been duly uploaded along with FORM 4 on the MAHA RERA portal. We are seeking extension on instruction of the MAHA RERA officials as per the email dated 18-12-2024; we would request you to extend our project completion date by 17-12-2024.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503530 | MEHUL HARISH SHAH | Gaiagen Technologies Private Limited | 03/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Nov 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Apr 2025
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for | 2 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate_Jan 25.pdf | 5 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Jan 25.pdf | 5 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dec 24.pdf | 4 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Technologies Pvt Ltd-Q3 Park Residence_ SignED_FINAL.pdf | 4 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Form 3 01012025 till 22012025 final signed compressed.pdf | 4 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dec 24.pdf | 4 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Technologies Pvt Ltd-Q3 Park Residence_ SignED_FINAL.pdf | 26 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 22 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 signed.pdf | 17 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: New OC_signed.pdf | 17 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Architect's Certificate.pdf | 4 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form- 3.pdf | 4 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer's Certificate.pdf | 4 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Sept 24.pdf | 4 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5.pdf | 4 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: GAIAGEN-FORM-5.pdf | 4 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Gaiagen form 5.pdf | 4 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Approved Part Occupation Certficate.pdf | 21 Feb 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Letter.pdf | 21 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Dec 2023.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dec 2023.pdf | 5 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Dec 2023.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PARK RESIDENCES Q3 Dec23 (Signed).pdf | 5 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory Nov 2023.pdf | 21 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5.pdf | 21 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Unsold Inventory Aug.pdf | 7 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Discloure of Sold Unsold Inventory March.pdf | 7 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-4 Final_compressed.pdf | 7 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Engineers Certificate Quality Assurance.pdf | 22 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf | 15 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 15 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-3 Dec'22 1.pdf | 10 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-2 Sept'22 1.pdf | 27 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects_Certificate Q-3.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_s_Certificate Q-3.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_s_Certificate Q-3.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer_s_Certificate Q-3.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer_s_Certificate_Quality_Assurance 2022.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 5 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 5 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 5 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht_certificate FORM 1.pdf | 24 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 24 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park_Residences_Form_3_Q-4 Final.pdf | 12 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht certificate.pdf | 18 May 2022 |
| Proforma of Allotment letterFile: Agreement for Sale.pdf | 18 May 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 18 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf | 11 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht_certificate.pdf | 11 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer_s_certificate_compressed.pdf | 11 Apr 2022 |
| CERSAI detailsFile: CERSAI_Park Residencies.pdf | 11 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 GAIAGEN TECHNOLOGIES PVT LTD.pdf | 11 Apr 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amend_5_FurtherCC_signed.pdf | 11 Apr 2022 |
| Copy of the legal title reportFile: 1-Format -A (legal title report).pdf | 12 Nov 2021 |
| Copy of the legal title reportFile: 1-Legal Title Report-Annexue.pdf | 12 Nov 2021 |
| Declaration about Commencement CertificateFile: 1-Declaration about CC.pdf | 12 Nov 2021 |
| Layout approvalFile: 4-Building Layout approval-1-upload.pdf | 3 Nov 2021 |
| Building plan approvalFile: 3-IOD approval.pdf | 3 Nov 2021 |
| Copy of Layout Approval (in case of layout)File: 4-Building Layout approval-1-upload.pdf | 3 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 3-IOD approval.pdf | 3 Nov 2021 |
| Declaration in FORM BFile: 7-Form B-compressed.pdf | 19 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8-FORM 3.pdf | 19 Oct 2021 |
| Details of encumbrancesFile: 2-Self Declaration Regarding Encumbrances.pdf | 18 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: 5-Commencement Certificate.pdf | 18 Oct 2021 |
| Declaration about Commencement CertificateFile: 6-Form D-Declaration CC.pdf | 18 Oct 2021 |
| Proforma of Allotment letterFile: 9-Self Declaration Allotment Letter.pdf | 18 Oct 2021 |
| OtherFile: 10-Certificate for change of name.pdf | 18 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PARK RESIDENCES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dahisar West6,700+ in Mumbai Suburban
ICON
RAGHU LEELA REALTORS PRIVATE LIMITED
ORNATE SOLITAIRE
ORNATE DAHISAR DEVELOPERS
EMPIRE HEIGHTS
EMPIRE REALTY
SHAKTI DHAM-WING A, VRINDAVAN-WING B RESIDENTI
DHARTI DEVELOPERS
RAGHUKUL CHSL
RAMNIYATI REALITIES LLP
Earth Residency Wing C and Wing D
Earth Estate Developers Pvt Ltd
See every Mumbai Suburban project, with the district possession charts
Builder: Gaiagen Technologies Private Limited
Gaiagen Technologies Private Limited has 1 registration on MahaRERA, including PARK RESIDENCES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that PARK RESIDENCES shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PARK RESIDENCES is delayed beyond 17 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PARK RESIDENCES?
The registered promoter entity is Gaiagen Technologies Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PARK RESIDENCES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PARK RESIDENCES?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PARK RESIDENCES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PARK RESIDENCES?
The professionals named in the filing: Architect: DA DESIGNS; Engineer: D.S. DEORA; Chartered Accountant: R M A & CO; Chartered Accountant: M R P & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PARK RESIDENCES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback