Home / Browse projects / Mumbai Suburban, Maharashtra / PARK RESIDENCES

Registration lapsed No litigation declared Others project

PARK RESIDENCES

By Gaiagen Technologies Private Limited

RG-MH-61585 · RERA P51800031874 · Last updated on MahaRERA portal: 2 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 23 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
9 of 11Construction stages donefurthest along: Internal walls, 99%
66 of 158Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

PARK RESIDENCES is a Others project by Gaiagen Technologies Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031874 on 22 Nov 2021. Possession was promised by 17 Dec 2024 and is now 22 months past that date. The completion date has moved by 23 months from the original filing. 92 of the 158 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePARK RESIDENCES
  • TypeOthers
  • Location
    • C.T.S No. 918A
    • Jaywant Sawant Road
    • Dahisar West
    • R/North Central Ward
    • Dahisar West
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • RERA no.P51800031874
  • ReraGenie IDRG-MH-61585

Builder

  • NameGaiagen Technologies Private Limited
  • Entity typeCompany
  • DirectorDevesh Birodkar

Key dates

22 months past promisethis monthRegisteredNov 2021First promiseJan 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Nov 2021
  • Promised completion17 Dec 2024
  • Revised completionRevised to 17 Dec 2024 (originally 31 Jan 2023)
  • Buildings1 building record
  • Documents filed68 files

Current status

58%92 of 158 units booked

Figures as on 2 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARK RESIDENCESNA201514315158

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

PARK RESIDENCES: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 2 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Common Areas and AmenitiesYes0%

Parking filed166

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots166
Closed/Covered166

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,477 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Oct 2025

Approvals and building plan

Sanctioning authorityBombay Municipal Corporation
Permissible FSI11130.0
Proposed, not sanctioned11,130 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 5,6,7, LINK HOUSE, GOREGAON LINK ROAD, MUMBAI 400064

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDA DESIGNS
EngineerD.S. DEORA
Chartered AccountantR M A & CO
Chartered AccountantM R P & ASSOCIATES
PartnerRole in project
Gaiagen Technologies Private Limited-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017282Jan 2023 → Nov 2023

Reason as filed by the promoterDue to the current weather conditions we are facing hardship at site leading to delays in balance work completion. This is leading to further delays in the overall completion of the project. Due to above condition, we would request you to extend our project completion date by only 3 months i.e to 30/11/2023

EXT51800013980Jan 2023 → Aug 2023

Reason as filed by the promoterLabour shortage during festival season has delayed the balance works leading to further delay in the various permissions required for completion of the project. Due to the this condition we would request you to extend our project completion date by only 3 months i.e 31-08-2023

EXT51800017985Jan 2023 → Jan 2024

Reason as filed by the promoterWe have made an application dated 27-10-2023 to the MCGM for occupancy certificate of the project and we have not received any permission as on date. Due to the above condition, we would request you to extend our project completion date by only 2 months i.e. 31/01/2024.

EXT51800012323Jan 2023 → May 2023

Reason as filed by the promoterThe project is delayed due to no allotment / sale of flats as a result of Covid 19 pandemic leading to the shortage of funds and due to delay in permission from various authorities. Refer attached document

EXT51800027277Jan 2023 → Dec 2024

Reason as filed by the promoterWe have made an application dated 27-10-2023 to the MCGM for occupancy certificate of the project and we have received the complete occupancy certificate on 17-12-2024 and the same has been duly uploaded along with FORM 4 on the MAHA RERA portal. We are seeking extension on instruction of the MAHA RERA officials as per the email dated 18-12-2024; we would request you to extend our project completion date by 17-12-2024.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503530MEHUL HARISH SHAHGaiagen Technologies Private Limited03/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Apr 2025

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate_Jan 25.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Jan 25.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dec 24.pdf4 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Technologies Pvt Ltd-Q3 Park Residence_ SignED_FINAL.pdf4 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Form 3 01012025 till 22012025 final signed compressed.pdf4 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dec 24.pdf4 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Gaiagen Technologies Pvt Ltd-Q3 Park Residence_ SignED_FINAL.pdf26 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf22 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 signed.pdf17 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: New OC_signed.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Architect's Certificate.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form- 3.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer's Certificate.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Sept 24.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: GAIAGEN-FORM-5.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Gaiagen form 5.pdf4 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Approved Part Occupation Certficate.pdf21 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Letter.pdf21 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Dec 2023.pdf5 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Dec 2023.pdf5 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Dec 2023.pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PARK RESIDENCES Q3 Dec23 (Signed).pdf5 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold - Booked Inventory Nov 2023.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form-5.pdf21 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Unsold Inventory Aug.pdf7 Aug 2023
Disclosure of sold/ booked inventoryFile: Discloure of Sold Unsold Inventory March.pdf7 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-4 Final_compressed.pdf7 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Engineers Certificate Quality Assurance.pdf22 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf15 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf15 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-3 Dec'22 1.pdf10 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Park Residencies Q-2 Sept'22 1.pdf27 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects_Certificate Q-3.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_s_Certificate Q-3.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_s_Certificate Q-3.pdf20 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer_s_Certificate Q-3.pdf20 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer_s_Certificate_Quality_Assurance 2022.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf5 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf5 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht_certificate FORM 1.pdf24 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf24 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park_Residences_Form_3_Q-4 Final.pdf12 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht certificate.pdf18 May 2022
Proforma of Allotment letterFile: Agreement for Sale.pdf18 May 2022
Proforma of Allotment letterFile: Allotment Letter.pdf18 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf11 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht_certificate.pdf11 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer_s_certificate_compressed.pdf11 Apr 2022
CERSAI detailsFile: CERSAI_Park Residencies.pdf11 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 GAIAGEN TECHNOLOGIES PVT LTD.pdf11 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amend_5_FurtherCC_signed.pdf11 Apr 2022
Copy of the legal title reportFile: 1-Format -A (legal title report).pdf12 Nov 2021
Copy of the legal title reportFile: 1-Legal Title Report-Annexue.pdf12 Nov 2021
Declaration about Commencement CertificateFile: 1-Declaration about CC.pdf12 Nov 2021
Layout approvalFile: 4-Building Layout approval-1-upload.pdf3 Nov 2021
Building plan approvalFile: 3-IOD approval.pdf3 Nov 2021
Copy of Layout Approval (in case of layout)File: 4-Building Layout approval-1-upload.pdf3 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: 3-IOD approval.pdf3 Nov 2021
Declaration in FORM BFile: 7-Form B-compressed.pdf19 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8-FORM 3.pdf19 Oct 2021
Details of encumbrancesFile: 2-Self Declaration Regarding Encumbrances.pdf18 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: 5-Commencement Certificate.pdf18 Oct 2021
Declaration about Commencement CertificateFile: 6-Form D-Declaration CC.pdf18 Oct 2021
Proforma of Allotment letterFile: 9-Self Declaration Allotment Letter.pdf18 Oct 2021
OtherFile: 10-Certificate for change of name.pdf18 Oct 2021

How this compares with Mumbai Suburban

58%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 23 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARK RESIDENCES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dahisar West6,700+ in Mumbai Suburban

Builder: Gaiagen Technologies Private Limited

Gaiagen Technologies Private Limited has 1 registration on MahaRERA, including PARK RESIDENCES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PARK RESIDENCES shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARK RESIDENCES is delayed beyond 17 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARK RESIDENCES?

The registered promoter entity is Gaiagen Technologies Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARK RESIDENCES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARK RESIDENCES?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARK RESIDENCES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARK RESIDENCES?

The professionals named in the filing: Architect: DA DESIGNS; Engineer: D.S. DEORA; Chartered Accountant: R M A & CO; Chartered Accountant: M R P & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK RESIDENCES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK RESIDENCES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK RESIDENCES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.