Home / Browse projects / Mumbai City, Maharashtra / Parasmani - B
Parasmani - B
By Parasmani Constructions Pvt .Ltd
RG-MH-21679 · RERA P51900023727 · Last updated on MahaRERA portal: 27 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
- Rs 295.00 crore secured on the land, in favour of Piramal Trusteeship Services Private Limited
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Parasmani - B is a Others project by Parasmani Constructions Pvt .Ltd in Mumbai City, Maharashtra, registered with MahaRERA as P51900023727 on 2 Jan 2020. Possession was promised by 20 May 2025 and is now 17 months past that date. The completion date has moved by 12 months from the original filing. 23 of the 27 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameParasmani - B
- TypeOthers
- Location
- Vidyavihar Station Road
- Vidyavihar (E)
- Mumbai City
- 400077
- Pincode400077
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900023727
- ReraGenie IDRG-MH-21679
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Jan 2020
- Promised completion20 May 2025
- Revised completionRevised to 20 May 2025 (originally 20 May 2024)
- Buildings1 building record
- Documents filed111 files
Current status
Figures as on 27 Sep 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B | NA | 14 | 14 | 27 | 0 | 27 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 93%.
B: 86% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 72% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 82% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 93% |
Progress on shared amenities15
As on 27 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B | NA | Rs 13.60 cr | Rs 14.36 cr |
| - | NA | Rs 2.24 cr | Rs 2.32 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Saloni Dheodhar |
| Engineer | Harshad Pendse |
| Chartered Accountant | Supriya Mundada |
| Chartered Accountant | GMKS & Co. |
| Partner | Role in project |
|---|---|
| Parasmani Constructions Pvt .Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Shortage of labor and delay in material procurement we are unable to complete the project in time.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed111
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5_Parasmani_B_Signed.pdf | 27 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar CertiFicate_Signed.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate_compressed.pdf | 25 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of Sold Inventory.pdf | 25 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- Parasmani B.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of sold inventory.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 2400415_DOI_KKJ.pdf | 16 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 240415_DOI_HKJ.pdf | 16 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 2400415_DOI_SM.pdf | 16 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_ Arch Certificate.pdf | 15 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 15 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5_Form 2A.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold inventory.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 15 Apr 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: 240308_Decl about Grievance Redressal Cell.pdf | 8 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf | 2 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold inventory.pdf | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 15 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 15 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 15 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: 22_Parasmani - B.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 35_Parasmani - B.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 31 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 18 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 18 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: 28_Parasmani - B.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 21 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 21 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 21 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 21 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 21 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 17 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 17 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 17 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 17 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: 28_Parasmani - B.pdf | 13 Jan 2023 |
| Proforma of Agreement for saleFile: 221012_Allot and Agreement.pdf | 15 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: 28_Parasmani - B.pdf | 19 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 35_Parasmani - B.pdf | 14 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 35_Parasmani - B.pdf | 14 Oct 2022 |
| Layout approvalFile: 221012_Layout.pdf | 13 Oct 2022 |
| Building plan approvalFile: 221012_Building Plan_1.pdf | 13 Oct 2022 |
| Building plan approvalFile: 221012_Building Plan_2.pdf | 13 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: 221012_Layout.pdf | 13 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 221012_Building Plan_1.pdf | 13 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 221012_Building Plan_2.pdf | 13 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 221012_Commencement Certificate.pdf | 13 Oct 2022 |
| Declaration about Commencement CertificateFile: 220322_Declaration about CC.pdf | 13 Oct 2022 |
| Declaration about Commencement CertificateFile: 221012_Declaration about CC.pdf | 13 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: 28_Parasmani - B_Disclosure of Sold Inventory.pdf | 21 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 19 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 19 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 5_Quality Certificate_Form 2A.pdf | 19 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: 28_Parasmani - B_Disclosure of Sold Inventory.pdf | 19 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 19 Apr 2022 |
| Layout approvalFile: 220322_Layout.pdf | 22 Mar 2022 |
| Building plan approvalFile: 220322_Building Plan_1.pdf | 22 Mar 2022 |
| Building plan approvalFile: 220322_Building Plan_2.pdf | 22 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: 220322_Layout.pdf | 22 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 220322_Building Plan_1.pdf | 22 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 220322_Building Plan_2.pdf | 22 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 220322_Commencement Certificate.pdf | 22 Mar 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Parasmani - A | Vidyavihar Mumbai | 53 | Completed | Dec 2018 | Late, Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 111 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Parasmani - B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vidyavihar (E)780+ in Mumbai City
Filed coordinates, straight-line distance. 14 registered projects within 2 km.
Mahindra Rainforest Phase 1
Anthurium Developers Limited
Mahindra Rainforest Phase 2
Anthurium Developers Limited
CRYSTAL PRIME MERIDIAN
ARYAMAAN DEVELOPERS PRIVATE LIMITED
AARADHYA ONEPARK
MICL CREATORS LLP
CENTRONA ZEN-A
ELEVATED AVENUE REALTY LLP
CENTRONA ZEN-B
ELEVATED AVENUE REALTY LLP
See every Mumbai City project, with the district possession charts
Builder: Parasmani Constructions Pvt .Ltd
Parasmani Constructions Pvt .Ltd has 2 registrations on MahaRERA, including Parasmani - A and Parasmani - B. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that Parasmani - B shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Parasmani - B is delayed beyond 20 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Parasmani - B?
The registered promoter entity is Parasmani Constructions Pvt .Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Parasmani - B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Parasmani - B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Parasmani - B?
The professionals named in the filing: Architect: Saloni Dheodhar; Engineer: Harshad Pendse; Chartered Accountant: Supriya Mundada; Chartered Accountant: GMKS & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Parasmani - B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback