Registration lapsed No litigation declared Residential / Group Housing project

PARAISO-2

By SARTHAK BUILDTECH

RG-MH-04837 · RERA P52100021705 · Last updated on MahaRERA portal: 16 Dec 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

PARAISO-2 is a Residential / Group Housing project by SARTHAK BUILDTECH in Pune, Maharashtra, registered with MahaRERA as P52100021705 on 19 Jul 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date.

At a glance

Project

  • NamePARAISO-2
  • TypeResidential / Group Housing
  • Location
    • SURVEY NO-155P
    • 156P
    • 157P
    • DEHU-ALANDI ROAD
    • SASTEWADI
    • MOSHI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100021705
  • ReraGenie IDRG-MH-04837

Builder

  • NameSARTHAK BUILDTECH
  • Entity typePartnership
  • PartnersPATEL AMAN BALWANT, PATEL PARTH HIRALAL, POKAR DIPAKKUMAR RAJUBHAI, PATEL ASHWIN NARAN, BHEMAT NARENDRA PASHABHAI, PATEL BALWANT CHHAGANBHAI
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredJul 2019PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Jul 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA80000
B WINGNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

A WING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership17

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,977 sq m
Land owned byThe promoter, with other names on the file
Named landowners17
LandownerVillageDistrict
DATTU SAHADU SASTE-Pune
MAHESH HUNAJI TALELE-Pune
BALU SAHADU SASTE-Pune
JAYWANT SAHADU SASTE-Pune
SHRIRANG KONDIBA SASTE-Pune
SACHIN SHRIRANG SASTE-Pune
MURLIDHAR KONDIBA SASTE-Pune
NITIN MURLIDHAR SASTE-Pune
ATUL MURLIDHAR SASTE-Pune
ANKUSH BABAN SASTE-Pune
SUNIL BABAN SASTE-Pune
RAHUL SADASHIV SASTE-Pune
MANOHAR HUNAJI TALELE-Pune
AMAR SADASHIV SASTE-Pune
POPAT KONDIBA SASTE-Pune
ANIL BABAN SASTE-Pune
DATTATRAY SADASHIV SASTE-Pune

Approvals and building plan

Permissible FSI5756.5
Proposed, not sanctioned3,956 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEMPIRE ESTATE CHINCHWAD

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANIK S BUCHADE
PartnerRole in project
SARTHAK BUILDTECH-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Plan 1.pdf16 Dec 2021
Building plan approvalFile: Plan 2.pdf16 Dec 2021
Building plan approvalFile: Plan 3.pdf16 Dec 2021
Building plan approvalFile: Plan 4.pdf16 Dec 2021
Layout approvalFile: Plan 3.pdf16 Dec 2021
Copy of Layout Approval (in case of layout)File: Plan 3.pdf16 Dec 2021
Building Plan Approval (IOD)File: Plan 1.pdf16 Dec 2021
Building Plan Approval (IOD)File: Plan 2.pdf16 Dec 2021
Building Plan Approval (IOD)File: Plan 3.pdf16 Dec 2021
Building Plan Approval (IOD)File: Plan 4.pdf16 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate.pdf16 Dec 2021
Declaration about Commencement CertificateFile: C C Declaration.pdf16 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 03-21.pdf16 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 09-21.pdf16 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 12-21.pdf16 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 30-09-2020.pdf16 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 30-03-2021.pdf16 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Adobe Scan 16-Dec-2021 (11).pdf16 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report_200225986984_For_Asset_Based_Search_16_12_2021_12_14_00_840.pdf16 Dec 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf16 Dec 2021
Certificates of CA (Form 3)File: Form-3 12-21.PDF16 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5 19-20.pdf16 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 -20-21.pdf16 Dec 2021
Copy of the legal title reportFile: SERCH REPORT COM.pdf21 Jun 2019
Details of encumbrancesFile: SERCH REPORT COM.pdf21 Jun 2019
Declaration in FORM BFile: PATEL B FORM.pdf21 Jun 2019
Certificates of CA (Form 3)File: ANKIT.pdf21 Jun 2019
Proforma of Allotment letterFile: paraiso-ii_flat 1agreement_Part-I.pdf17 Apr 2019
Proforma of Allotment letterFile: paraiso-ii_flat 2agreement_Part-II.pdf17 Apr 2019
Building plan approvalFile: PAGE11.pdf11 Apr 2019
Building plan approvalFile: PAGE2.pdf11 Apr 2019
Building plan approvalFile: PAGE3.pdf11 Apr 2019
Building plan approvalFile: PAGE4.pdf11 Apr 2019
Building plan approvalFile: PAGE5.pdf11 Apr 2019
Building plan approvalFile: PAGE1.pdf11 Apr 2019
Layout approvalFile: PAGE11.pdf11 Apr 2019
Copy of Layout Approval (in case of layout)File: PAGE11.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE11.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE2.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE3.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE4.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE5.pdf11 Apr 2019
Building Plan Approval (IOD)File: PAGE1.pdf11 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: PARAISO-2 CC.pdf11 Apr 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARAISO-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SASTEWADI,MOSHI13,700+ in Pune

Builder: SARTHAK BUILDTECH

SARTHAK BUILDTECH has 2 registrations on MahaRERA, including PARAISO-1 and PARAISO-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PARAISO-2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARAISO-2 is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARAISO-2?

The registered promoter entity is SARTHAK BUILDTECH, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARAISO-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARAISO-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARAISO-2?

The professionals named in the filing: Architect: MANIK S BUCHADE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARAISO-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARAISO-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARAISO-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.