ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PALKHI AURA

Completed No litigation declared Residential / Group Housing project

PALKHI AURA

By KCD AND SYNERGY VENTURES

RG-MH-25705 · RERA P51800009045 · Last updated on MahaRERA portal: 16 Feb 2021

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
11 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

PALKHI AURA is a Residential / Group Housing project by KCD AND SYNERGY VENTURES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009045 on 19 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NamePALKHI AURA
  • TypeResidential / Group Housing
  • Location
    • BORIVALI
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009045
  • ReraGenie IDRG-MH-25705

Builder

  • NameKCD AND SYNERGY VENTURES
  • Entity typePartnership
  • PartnersRAJIV CHANDULAL DARJI, SIDDHESH RAMDAS KADAM, YOGESH RAMDAS KADAM
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PALKHI AURA A WINGNA220000
PALKHI AURA B WINGNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 95%.

PALKHI AURA A WING85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
PALKHI AURA B WING89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 16 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,850 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
KCD & SYNERGY VENTURESBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI4413.21
Proposed, not sanctioned2,866 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI EAST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSARC
PartnerRole in project
KCD AND SYNERGY VENTURES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800003654Dec 2019 → Dec 2020

Reason as filed by the promoterDUE TO SHORTAGE OF SAND AND RAW MATERIAL AND DELAY IN OBTAINING THE PERMISSION. WE WOULD REQUEST YOU TO PLEASE GRANT US PERMISSION FOR ONE YEAR.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Feb 2021

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf16 Feb 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf12 Feb 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Rera.pdf12 Feb 2021
Certificates of CA (Form 3)File: PHASE 1.pdf29 Oct 2020
Certificates of CA (Form 3)File: PHASE 1.pdf29 Oct 2020
Certificates of CA (Form 3)File: PHASE 1.pdf29 Oct 2020
Details of Restarting of Construction work post lockdownFile: COVIDPHASE 1.pdf29 Jun 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf4 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf1 Nov 2019
Certificates of CA (Form 3)File: CA.pdf23 Oct 2019
Certificates of CA (Form 5)File: FORM 5.pdf23 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate COMP.pdf27 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH_compressed.pdf22 Aug 2019
Certificates of CA (Form 3)File: CA_compressed.pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf18 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf18 May 2019
Certificates of CA (Form 3)File: CA.pdf18 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect old.pdf18 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT NEW.pdf18 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering old.pdf18 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG NEW.pdf18 Feb 2019
Certificates of CA (Form 3)File: CA Old.pdf18 Feb 2019
Certificates of CA (Form 3)File: CA NEW.pdf18 Feb 2019
Certificates of CA (Form 5)File: FORM 5 NEW.pdf23 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Palkhi Aura CC.pdf17 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH COMP.pdf28 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate compressed.pdf28 Aug 2018
Certificates of CA (Form 3)File: CA Certificate compressed FINAL.pdf28 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch.pdf10 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate (5).pdf10 May 2018
Certificates of CA (Form 3)File: CA COMP FINAL.pdf10 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng.pdf5 Feb 2018
Certificates of CA (Form 3)File: CA final.pdf5 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch-ilovepdf-compressed.pdf3 Feb 2018
Certificates of CA (Form 3)File: NEW CA.pdf31 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate (Palkhi Aura).pdf29 Jul 2017
Certificates of CA (Form 3)File: ca.pdf29 Jul 2017
Proforma of Allotment letterFile: ilovepdf_merged (2).pdf29 Jul 2017
Layout approvalFile: kevin layout.pdf28 Jul 2017
Building plan approvalFile: kcd iod.pdf28 Jul 2017
PAN CardFile: PAN.pdf28 Jul 2017
Copy of the legal title reportFile: title report.pdf28 Jul 2017
Details of encumbrancesFile: No Encumbrances Declaration (1).pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: kevin layout.pdf28 Jul 2017
Building Plan Approval (IOD)File: kcd iod.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Jul 2017
Declaration in FORM BFile: form b.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: archi.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PALKHI AURA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI6,700+ in Mumbai Suburban

2 kmPALKHI AURACompleted 135Lapsed / revoked 76Other 192Dot size: filed unitsN

Filed coordinates, straight-line distance. 403 registered projects within 2 km.

Builder: KCD AND SYNERGY VENTURES

KCD AND SYNERGY VENTURES has 2 registrations on MahaRERA, including PALKHI AURA and PALKHI AURA - PART 18TH TO 22ND FLOOR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if PALKHI AURA is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALKHI AURA?

The registered promoter entity is KCD AND SYNERGY VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALKHI AURA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PALKHI AURA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALKHI AURA?

The professionals named in the filing: Architect: SARC. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALKHI AURA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALKHI AURA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALKHI AURA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.