PALI PALMS
RG-MH-63330 · RERA P51800011792 · Last updated on MahaRERA portal: 15 Apr 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PALI PALMS is a Residential / Group Housing project by SSD HOLDINGS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011792 on 31 Aug 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NamePALI PALMS
- TypeResidential / Group Housing
- Location
- 16th Road
- Bandra West
- Andheri
- Mumbai Suburban
- 400050
- Pincode400050
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800011792
- ReraGenie IDRG-MH-63330
Builder
- NameSSD HOLDINGS LLP
- Entity typePartnership
- PartnersSANJAY JAGWANI, AMIT JAGWANI, MAHESH JAGWANI, SUNIL DOULTANI, KUMAR MORDANI
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Jun 2023
- Revised completionRevised to 30 Jun 2023 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed29 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PALI PALMS | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
PALI PALMS: 97% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 15 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PUSHKAR & CONSULTANTS |
| Engineer | Doultani & Associates |
| Chartered Accountant | RMA & Co |
| Partner | Role in project |
|---|---|
| SSD HOLDINGS LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. We, SSD Holdings LLP, promoter of PALI PALMS, registered office address 7th Floor, Notan Plaza, Turner Road, Bandra West, Mumbai- 400050, hereby apply for extension u/s 7 (3) of the registered project bearing vide no P51800011792, with more than 2/3rd consent of the Association of allottees. 2. That the Project ‘Pali Palms’ (hereinafter referred to as the project) was registered with MAHARERA on 31.08.2017, bearing Registration no. P51800011792 which was scheduled to expire on 31.12.2019, by certificate dated 18.5.2020 stand valid till 30.6.2021. 3. That we do hereby make a request for exte
Reason as filed by the promoter1. The project is sanctioned under DCR (14) of Development Control Rules and is approved by Slum Rehabilitation Authority, Mumbai. The construction of the building Pali Palms, situated on Plot having CTS No. F/575A, F/579 & F/580 comprising of ground plus 2 podium plus 14 floors has been completed as per approved plans. 2. However, under the scheme, completion and handover of 26 PTC (Permanent Transit Camps) to Slum Rehabilitation Authority, Maharashtra has to be completed. The responsibility for constructing the PTC is on Koel Developers LLP on piece of land situated at 85,85/1 to 85/58 & 86,
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000141074 | VISHAL MALIK | SSD HOLDINGS LLP | 27/09/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SSD HOLDINGS LLP 2021-2022.pdf | 15 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 (1).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (2).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (3).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: (4).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (4).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (6).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (7).pdf | 3 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: (8).pdf | 3 Jul 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC Under Circular 32.pdf | 30 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure for SoldUnsold Inventory.pdf | 30 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SSD Form 5 - 2018-19.pdf | 30 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SSD Form 5 - 2019-20.pdf | 30 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SSD Form 5 - 2020-21.pdf | 30 Jun 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Pali Palms CHS Registration Certificate.pdf | 30 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 12 Oct 2018 |
| PAN CardFile: SSD Holdings LLP.pdf | 2 Oct 2018 |
| Certificates of CA (Form 5)File: CA Certificate Form 5.pdf | 2 Oct 2018 |
| Layout approvalFile: AMENDED PLAN AND SRA LETTER.pdf | 31 Jul 2017 |
| Building plan approvalFile: INTIMATION OF APPROVAL.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: NO ENCRUMBANCE CERTIFICATE.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: AMENDED PLAN AND SRA LETTER.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: INTIMATION OF APPROVAL.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHETECT CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA FORM 3.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT SALE AGREEMENT.PDF | 31 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SAPPHIRE | CORNER OF S V ROAD AND 1ST ROAD KHAR W MUMBAI 400052 | 16 | Completed | Oct 2011 | Oct 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PALI PALMS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bandra West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 282 registered projects within 2 km.
Godrej Bandra Bay Phase 1
Godrej Properties Limited Roshni Developer
INSPIRA ONE
INSPIRA BUILDCON PRIVATE LIMITED
7 ELEMENTS
M&K Elements Realty LLP
The Waterfront
M/s Orbit Developers
Bay Heights
EXCEL ENTERPRISES INDIA PRIVATE LIMITED
33FIFTEEN
AJMERA LUXE REALTY PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: SSD HOLDINGS LLP
SSD HOLDINGS LLP has 1 registration on MahaRERA, including PALI PALMS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that PALI PALMS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PALI PALMS is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PALI PALMS?
The registered promoter entity is SSD HOLDINGS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PALI PALMS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PALI PALMS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PALI PALMS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PALI PALMS?
The professionals named in the filing: Architect: PUSHKAR & CONSULTANTS; Engineer: Doultani & Associates; Chartered Accountant: RMA & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PALI PALMS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback