Home / Browse projects / Pune, Maharashtra / PALAASH SADAPHULI

Completed No litigation declared Residential / Group Housing project

PALAASH SADAPHULI

By GS ASSOCIATES

RG-MH-20430 · RERA P52100003228 · Last updated on MahaRERA portal: 29 Oct 2024

Source: official MahaRERA filing

Red flags

  • 21 complaints at MahaRERA
  • Completion date moved by 74 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promisedregistration recorded completed
20 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
21Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

PALAASH SADAPHULI is a Residential / Group Housing project by GS ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100003228 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2024. The completion date has moved by 74 months from the original filing. 21 complaints are on record with the regulator.

At a glance

Project

  • NamePALAASH SADAPHULI
  • TypeResidential / Group Housing
  • Location
    • Varale
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003228
  • ReraGenie IDRG-MH-20430

Builder

  • NameGS ASSOCIATES
  • Entity typeOthers
  • Named personSHASHI GURBUX PAHLANI
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseApr 2018Revised toJun 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Apr 2018)
  • Buildings2 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA140000
BNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed175

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots175
Closed/Covered96
Open Space79
BuildingClosed/CoveredOpen SpaceTotal
A464086
B503989

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,730 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9111.37
Proposed, not sanctioned9,110 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPimple Saudagar

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAvinash Nawathe
EngineerJW CONSULTANTS LLP
Chartered AccountantCA AZAM MULANI
PartnerRole in project
GS ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013056Apr 2018 → Jun 2024

Reason as filed by the promoterWe took over the project as per the Order of the Hon'ble Authority. Only after the consent the Order came to be passed.

Complaints filed with MahaRERA21

Case no.ComplainantRespondentFiled
CC005000000010584P V WANDREKARDSK WORLDMAN PROJECTS LTD22/11/2017
CC005000000010653ATUL VASANT MAHAJANM/S DSK Worldman Project Limited02/12/2017
CC005000000010659Rohan PadgaonkarDSK Worldman Projects Pvt. Ltd10/01/2018
CC005000000010898Nilesh TupeDSK WORLDMAN PROJECTSLTD.PVT.21/01/2018
CC005000000011241Krishna Narayan Gokhale and Meghana Krishna GokhaleDSK Worldman projects Ltd.31/03/2018
CC005000000011064Rahul PalnitkarDSK Worldman Projects20/02/2018
CC005000000011080Kirankumar Prakashchand DakleDSK Worldman Projects Limited11/03/2018
CC005000000011109SONALI TUSHAR POWLEDSK WORLDMAN PROJECTS LTD.04/03/2018
CC005000000011260Neetta DeulekerDSK WORLDMAN PROJECTS LTD15/04/2018
CC005000000011551SHILPA PRATAP RAGHUVANSHIDSK WORLDMAN PROJECTS LTD22/05/2018
CC005000000011568SURESH TUKARAM KHARATDS KULKARNI, PUNE24/05/2018
CC005000000011621JAWALE PRAVIN PDSK WORLDMAN PROJECTS LTD09/06/2018
CC005000000011666LalitaDSK WORLD PROJECTS LIMITED05/07/2018
CC005000000012004Pradeep WandrekarDSK Worldman Projects Ltd11/09/2018
CC005000000023275Pradeep Wandrekar Chairman of Sadaphuli A, A1 & B CHS Ltd.DSK Worldman Projects Ltd.29/07/2019
CC005000000022090Anand Hiralal OswalDSK Worldman Projects Ltd.03/10/2018
CC005000000198135ANAND HIRALAL OSWALG S Associates17/01/2023
CC005000000022103Mihir Yashwant SambhusDSK Worldman Projects Limited04/10/2018
CC005000000177885SUMIT CHOUDHARYM/s G. S. Associates05/12/2022
CC005000000279712Kunal Yatindra ParekhDSK Worldman Projects Ltd.06/11/2023
CC005000000279860Pradip Gopal PurandareD S Kulkarni18/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 May 2024

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SADAPHULI PHASE 1.pdf29 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.pdf14 May 2024
Certificates of CA (Form 3)File: form3_compressed (1) (1).pdf14 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate.pdf14 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: F COMPLETION.pdf14 May 2024
Architect’s Certificate on Completion of Project (Form 4)File: form4.pdf14 May 2024
Disclosure of sold/ booked inventoryFile: statement.pdf26 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARC CERTIFICATE SADAAPHULI PHASE -1.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE SADAAPHULI PHASE -1.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DETAILS SADAPHULI PHASE-1-compressed.pdf12 Jan 2024
Certificates of CA (Form 3)File: SADAAPHULI PHASE 1 FORM 3.pdf12 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GS Associate Sadaphuli Ph I FY 22-23.pdf25 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf20 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_compressed.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: STATEMENT_compressed_11zon.pdf20 Oct 2023
Certificates of CA (Form 3)File: Form 3GS Sadaphuli PH 1 FINAL.pdf20 Oct 2023
Other - LegalFile: document.pdf18 May 2023
Other - LegalFile: Completion certificate A Wing_compressed.pdf16 May 2023
Disclosure of sold/ booked inventoryFile: PHASE 1 SOLD UNSOLD DETAILS FINAL.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DECLARATION FORM 2A AND FORM 5 PHASE-1.pdf6 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 1 Arc Certificate (05042023)_compressed.pdf5 Apr 2023
Details of encumbrances concerned to FinanceFile: 20220930171227.pdf31 Mar 2023
Details of encumbrances concerned to FinanceFile: 20220930171144.pdf31 Mar 2023
Details of encumbrances concerned to LegalFile: 20220930171227.pdf31 Mar 2023
Details of encumbrances concerned to LegalFile: 20220930171144.pdf31 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: NA Order_Plot .pdf31 Mar 2023
Declaration in FORM BFile: 20220930171044.pdf31 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A PHASE -1 PALAASH SADAPHULI.pdf31 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A PHASE -1 PALAASH SADAPHULI.pdf31 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200248899260_For_Asset_Based_Search_04_10_2022_12_52_19_418.pdf31 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200248902273_For_Asset_Based_Search_04_10_2022_13_03_21_075.pdf31 Mar 2023
Proforma of Agreement for saleFile: Agreement Phase I.pdf31 Mar 2023
Proforma of Allotment letterFile: Phase I Allotment Letter.pdf31 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account - Phase I.pdf31 Mar 2023
Deviation Report with respect to Allotment letterFile: No Deviation - Allotment - Phase I.pdf31 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Phase I.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Palaash Sadaphuli.pdf25 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Palaash Sadaphuli.pdf25 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Palaash Sadaphuli.pdf25 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Palaash Sadaphuli.pdf25 Jan 2023
Declaration about Commencement CertificateFile: 20220930171204.pdf12 Dec 2022
Layout approvalFile: 1.pdf30 Jul 2017
Building plan approvalFile: 2.pdf30 Jul 2017
Building plan approvalFile: 2.pdf30 Jul 2017
Building plan approvalFile: 7.pdf30 Jul 2017
Copy of the legal title reportFile: Legal title report.pdf30 Jul 2017
Details of encumbrancesFile: Self Declaration_DSK Sadaphuli_DSKWPL.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: 1.pdf30 Jul 2017
Building Plan Approval (IOD)File: 2.pdf30 Jul 2017
Building Plan Approval (IOD)File: 2.pdf30 Jul 2017
Building Plan Approval (IOD)File: 7.pdf30 Jul 2017
Declaration in FORM BFile: FORM B - A,B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate_DSK Sadaphuli_DSKWPL.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certi_DSK Sadaphuli_DSKWPL.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment RERA.pdf30 Jul 2017
Proforma of Allotment letterFile: Agreement _sadaphuli_A-B.pdf30 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 74 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PALAASH SADAPHULI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Varale13,700+ in Pune

2 kmPALAASH SADAPHULICompleted 21Lapsed / revoked 10Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: GS ASSOCIATES

GS ASSOCIATES has 2 registrations on MahaRERA, including PALAASH SADAPHULI PHASE 2 A1 WING and PALAASH SADAPHULI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PALAASH SADAPHULI is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALAASH SADAPHULI?

The registered promoter entity is GS ASSOCIATES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALAASH SADAPHULI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PALAASH SADAPHULI?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PALAASH SADAPHULI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALAASH SADAPHULI?

The professionals named in the filing: Architect: Avinash Nawathe; Engineer: JW CONSULTANTS LLP; Chartered Accountant: CA AZAM MULANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALAASH SADAPHULI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALAASH SADAPHULI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALAASH SADAPHULI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.