Home / Browse projects / Raigarh, Maharashtra / PAL GARDEN PHASE II

Completed No litigation declared Residential / Group Housing project

PAL GARDEN PHASE II

By Alexandra And Pal Estates Private Limited

RG-MH-96306 · RERA P52000015378 · Last updated on MahaRERA portal: 19 Jun 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
31 of 44Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

PAL GARDEN PHASE II is a Residential / Group Housing project by Alexandra And Pal Estates Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000015378 on 20 Feb 2018. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NamePAL GARDEN PHASE II
  • TypeResidential / Group Housing
  • Location
    • S. NO. 17
    • KARJAT
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000015378
  • ReraGenie IDRG-MH-96306

Builder

  • NameAlexandra And Pal Estates Private Limited
  • Entity typeCompany
  • Managing DirectorsLaldhari Jagunandan Pal, Arjunsingh Bahadursingh Gaur
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2018First promiseDec 2022Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on20 Feb 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
  • Buildings4 building records
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E WINGNA60000
F WINGNA60000
G WINGNA60000
H WINGNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 19 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 95%.

E WING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
F WING87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor60%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
G WING80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
H WING80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 19 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,765 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4369.84
Proposed, not sanctioned4,370 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP POLICE GROUND NEAR POLICE STATION KARJAT

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANUP SALVI
EngineerATUL KUDTARKAR
PartnerRole in project
Alexandra And Pal Estates Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013632Dec 2022 → Dec 2023

Reason as filed by the promoterOur projects got disturbed by Covid-19 pandemic very badly. Our construction activity not yet got stable, as our labour and contractors migrated to their hometown. We still not able to get competent labour and contractors to get the work completed. Please grant us extension.

EXT52000019407Dec 2022 → Dec 2025

Reason as filed by the promoterMy projects got disturbed by Covid-19 pandemic very badly. Our construction activity not yet got stable, as our labour and contractors migrated to their hometown. We still not able to get competent labour and contractors to get the work completed. Please grant us extension.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Pal Garden Phase II OC.pdf19 Jun 2025
Declaration in FORM BFile: FORM B.pdf5 Apr 2024
Declaration in FORM BFile: FORM B.pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Pal Garden, Karjat.pdf21 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance 2022-23.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory of the project.pdf21 Mar 2024
Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf21 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 Annual Report 2022-23.pdf21 Mar 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE.pdf2 Mar 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE.pdf2 Mar 2023
Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf2 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Pal Garden II.pdf2 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Pal Garden II.pdf2 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A-31-03-2020.pdf2 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A-31-03-2021.pdf2 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A-31-03-2022.pdf2 Mar 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVVENTORY.pdf2 Mar 2023
CERSAI detailsFile: CERSAI.pdf2 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE INTEREST ORDEER.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 FY 2017 18 11zon.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 2018 19 11zon.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 2019 20 11zon.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020 21 11zon.pdf2 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLERATION ABOUT SEPRATE BANK ACCOUNT.pdf2 Mar 2023
Building plan approvalFile: PLAN PASSING.pdf15 Feb 2018
Layout approvalFile: PLAN PASSING.pdf15 Feb 2018
PAN CardFile: 2PAN OF THE COMPANY.pdf15 Feb 2018
Copy of the legal title reportFile: 9PAL GARDEN SEARCH TITLE REPORT.pdf15 Feb 2018
Details of encumbrancesFile: 3NO ENCUMBRANCE.pdf15 Feb 2018
Copy of Layout Approval (in case of layout)File: PLAN PASSING.pdf15 Feb 2018
Building Plan Approval (IOD)File: PLAN PASSING.pdf15 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: 8PAL GADEN PHASE 2 - CC.pdf15 Feb 2018
Declaration in FORM BFile: 1Form B.pdf15 Feb 2018
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf15 Feb 2018
Proforma of Allotment letterFile: Flat Agreement PAL GARDEN PHASE 2- UNDER RERA ACT.pdf15 Feb 2018
OtherFile: PAL GARDEN 7 12 EXTRACT.pdf15 Feb 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Pal Garden Phase 1Survey No 17.1C51CompletedJul 2016Late, Dec 2016

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 36 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PAL GARDEN PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARJAT5,900+ in Raigarh

2 kmPAL GARDEN PHASE IICompleted 24Lapsed / revoked 29Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 97 registered projects within 2 km.

Builder: Alexandra And Pal Estates Private Limited

Alexandra And Pal Estates Private Limited has 1 registration on MahaRERA, including PAL GARDEN PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if PAL GARDEN PHASE II is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PAL GARDEN PHASE II?

The registered promoter entity is Alexandra And Pal Estates Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PAL GARDEN PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PAL GARDEN PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PAL GARDEN PHASE II?

The professionals named in the filing: Architect: ANUP SALVI; Engineer: ATUL KUDTARKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PAL GARDEN PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PAL GARDEN PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PAL GARDEN PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.