ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / PADMAVATI ANGAN

Registered No litigation declared Others project

PADMAVATI ANGAN

By SAMARTH CONSTRUCTION & DEVELOPERS

RG-MH-96321 · RERA P52100046172 · Last updated on MahaRERA portal: 17 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 4 months from the original
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
39 of 66Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

PADMAVATI ANGAN is a Others project by SAMARTH CONSTRUCTION & DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100046172 on 20 Jun 2022. Possession is promised by 31 Jul 2027. The completion date has moved by 4 months from the original filing. 27 of the 66 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NamePADMAVATI ANGAN
  • TypeOthers
  • Location
    • WADMUKHWADI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046172
  • ReraGenie IDRG-MH-96321

Builder

  • NameSAMARTH CONSTRUCTION & DEVELOPERS
  • Entity typePartnership
  • GSTIN27ADNFS9944F1ZE
  • PartnerSHIVAJI DAHIFALE
  • PartnerSunil Kedar
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2022First promiseMar 2027Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Mar 2027)
  • Buildings1 building record
  • Documents filed103 files

Current status

41%27 of 66 units booked
100.0%Work done, per cost certificate

Figures as on 17 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PADMAVATI ANGANNA77521466

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PADMAVATI ANGAN: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area802 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 May 2026
LandownerVillageDistrict
CHANDRAKANT DAHIFALE-Pune
RAVIRAJ TAPKIRMoshiPune
BALASAHEB GAWADEPimpale GuravPune
YASH GAWADEPimpale GuravPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Council
Permissible FSI1476.32
Proposed, not sanctioned1,411 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHOVISAWADI, ALANDI ROAD, PUNE 412105
Estimated costRs 4.22 cr
Cost incurredRs 4.22 cr
Work done100.0%
BuildingWingEstimatedIncurred
PADMAVATI ANGANNARs 4.22 crRs 4.22 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHUBHAM KHANDEBHARAD
EngineerShrikant Kedar
EngineerAMOL NIRMAL
Chartered AccountantYMK & Associates
Chartered AccountantPGMJ & ASSOCIATES
Chartered AccountantA S JANGADA & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
SAMARTH CONSTRUCTION & DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100046172/WarMar 2027 → Jul 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2027

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Form 2A 2024.pdf17 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A 2025.pdf17 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 2026.pdf17 Sep 2026
Form 2A (FY 2022-2023)File: 2a wadmukhwadi.pdf16 Sep 2026
Withdrawal Update Form 1File: Form 1 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 26-27.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf22 Jun 2026
Withdrawal Update Form 1File: Form 1 Q2.pdf22 Jun 2026
Withdrawal Update Form 1File: Form 1 Q3 - Pad.pdf22 Jun 2026
Withdrawal Update Form 1File: Form 1 Q4 -2026 - Padmavati.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2 Q2.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2 Q3 - Pad.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2 Q4 -2026 - Padmavati.pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3 Final (1).pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3 Q2.pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3 Q3 - Pad.pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3 Q4 - 26.pdf22 Jun 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final (1).pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 25 - Pad.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final Q4.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 25 - Pad.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Circular Padmavati Mar 25.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 FY 24-25.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf30 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf30 Jan 2025
Layout approvalFile: Sanction plan highlighted.pdf10 Jan 2025
Building plan approvalFile: Building Plan 1.pdf10 Jan 2025
Building plan approvalFile: Building Plan 2.pdf10 Jan 2025
Copy of Layout Approval (in case of layout)File: Sanction plan highlighted.pdf10 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf10 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf10 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf10 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Padmawati Angan CA Vaidya.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: UPLOAD.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Circular Padmavati - Oct 24.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular Padmavati - June 24.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Signed.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular Padmavati Apr 24.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Signed.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf7 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 Padmavati.pdf22 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 Padmavati.pdf22 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 Q3 Draft.pdf22 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Padmavati Aangan Final.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold circular.pdf26 Dec 2023
Proforma of Agreement for saleFile: Agreement to Sale English.pdf21 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Signed.pdf3 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Signed.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Client Sign_compressed.pdf3 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf3 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2a wadmukhwadi.pdf23 Aug 2023
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner Jul 6, 2023 4-18 PM (1).pdf26 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DocScanner Jul 6, 2023 4-18 PM.pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 upload.pdf26 Jul 2023
Layout approvalFile: Revised Commencement Certificate.pdf11 Jul 2023
Layout approvalFile: FSI Calculations Highlighted_compressed.pdf11 Jul 2023
Copy of Layout Approval (in case of layout)File: Revised Commencement Certificate.pdf11 Jul 2023
Copy of Layout Approval (in case of layout)File: FSI Calculations Highlighted_compressed.pdf11 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q-2 Merged.pdf8 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q-3_compressed.pdf8 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q-4.pdf8 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Q-2.pdf8 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Q-3.pdf8 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Q-4.pdf8 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect Certificate for ongoing project padmawati.pdf29 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Scanned PA.pdf29 May 2023

How this compares with Pune

41%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PADMAVATI ANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADMUKHWADI13,700+ in Pune

2 kmPADMAVATI ANGANCompleted 28Lapsed / revoked 16Other 70Dot size: filed unitsN

Filed coordinates, straight-line distance. 114 registered projects within 2 km.

Builder: SAMARTH CONSTRUCTION & DEVELOPERS

SAMARTH CONSTRUCTION & DEVELOPERS has 2 registrations on MahaRERA, including PADMAVATI ANGAN and SONAI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PADMAVATI ANGAN is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PADMAVATI ANGAN?

The registered promoter entity is SAMARTH CONSTRUCTION & DEVELOPERS, a partnership as per the filing. Its GSTIN 27ADNFS9944F1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PADMAVATI ANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PADMAVATI ANGAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PADMAVATI ANGAN?

The professionals named in the filing: Architect: SHUBHAM KHANDEBHARAD; Engineer: Shrikant Kedar; Engineer: AMOL NIRMAL; Chartered Accountant: YMK & Associates; Chartered Accountant: PGMJ & ASSOCIATES; Chartered Accountant: A S JANGADA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PADMAVATI ANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PADMAVATI ANGAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PADMAVATI ANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.