Home / Browse projects / Gandhinagar, Gujarat / ORIGIN PARK

Valid until 31 Jul 2028 Mixed Development project

ORIGIN PARK

By ORIGIN DEVELOPERS

RG-GJ-20083 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12325/290923 · Last updated on GujRERA portal: 18 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2028Possession promisedno revision filed
9 of 27Construction stages doneacross 3 buildings; furthest along: Internal walls, 88%
143 of 254Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

ORIGIN PARK is a Mixed Development project by ORIGIN DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12325/290923 on 29 Sep 2023. Possession is promised by 31 Jul 2028. 111 of the 254 units on this registration are recorded sold or booked, and 9 of 27 construction stages are filed complete.

At a glance

Project

  • NameORIGIN PARK
  • TypeMixed Development
  • Location
    • S No 27A
    • Vasana Hadmatiya Village
    • Opp Saundarya 444 K Road
    • Gandhinagar
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12325/290923
  • ReraGenie IDRG-GJ-20083

Builder

  • NameORIGIN DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2023PromisedJul 2028

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2028
  • Registered on29 Sep 2023
  • Promised completion31 Jul 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed42 files

Current status

44%111 of 254 units booked
54.8%Of the estimated cost spent so far

Figures as on 18 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK D---26026
BLOCK A+B+C---13270202
BLOCK E---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 88%.

BLOCK D61%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor15%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats29%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing14%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing12%
BLOCK A+B+C59%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor15%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats17%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing11%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing10%
BLOCK E61%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor15%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats29%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing14%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing12%

Progress on shared amenities19

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes95%
Storm water drainsYes95%
Landscaping and tree plantingYes50%
Street lightingNoNot applicable
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes30%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Fire fightingYes50%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,989 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 105.00 cr
Cost incurredRs 57.54 cr
Spent of the estimate54.8%
BuildingWingEstimatedIncurred
BLOCK A+B+CNARs 63.00 crRs 39.77 cr
BLOCK DNARs 21.00 crRs 8.43 cr
BLOCK ENARs 21.00 crRs 9.34 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDipika Chavda
EngineerVIREN D PAREKH

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12325/290923 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)18 Apr 2026
Architect's certificate (Form 1)17 Apr 2026
Engineer's certificate (Form 2)17 Apr 2026
Engineer's certificate annexure17 Apr 2026
Site photograph, BLOCK D17 Apr 2026
Site photograph, BLOCK A+B+C17 Apr 2026
Site photograph, BLOCK E17 Apr 2026
RERA registration certificate29 Sep 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

44%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep ORIGIN PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmORIGIN PARKOther 170Dot size: filed unitsN

Filed coordinates, straight-line distance. 170 registered projects within 2 km.

Builder: ORIGIN DEVELOPERS

ORIGIN DEVELOPERS has 1 registration on GujRERA, including ORIGIN PARK. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if ORIGIN PARK is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ORIGIN PARK?

The registered promoter entity is ORIGIN DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ORIGIN PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ORIGIN PARK?

The professionals named in the filing: Architect: Dipika Chavda; Engineer: VIREN D PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORIGIN PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORIGIN PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORIGIN PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.