Home / Browse projects / Satara, Maharashtra / OM SAI RESIDENCY

De-registered No litigation declared Residential / Group Housing project

OM SAI RESIDENCY

By KAUSTUBH DILIP MORE

RG-MH-15863 · RERA P52700024157 · Last updated on MahaRERA portal: 23 Apr 2025

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 19 months past the filed date
  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

OM SAI RESIDENCY is a Residential / Group Housing project by KAUSTUBH DILIP MORE in Satara, Maharashtra, registered with MahaRERA as P52700024157 on 23 Jan 2020. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 26 months from the original filing.

At a glance

Project

  • NameOM SAI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • RAHIMATPUR ROAD
    • KARANDWADI
    • Degaon
    • Satara
    • 415004
  • Pincode415004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700024157
  • ReraGenie IDRG-MH-15863

Builder

  • NameKAUSTUBH DILIP MORE
  • Entity typeIndividual

Key dates

19 months past promisethis monthRegisteredJan 2020First promiseJan 2023Revised toMar 2025

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on23 Jan 2020
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Jan 2023)
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

1: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area375 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SAIPARAS BUILDERS AND DEVELOPERSSataraSatara

Approvals and building plan

Permissible FSI449.95
Proposed, not sanctioned450 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDESAI HEIGHTS SATARA

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
KAUSTUBH DILIP MORE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700016957Jan 2023 → Mar 2025

Reason as filed by the promoterALL RCC BRICKWORK AND PLASTER HAS BEEN COMPLETE FOR REMAING WORK WE REQURIED THIS TIME

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 23-04.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH C.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FINAL.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH C 10-7-23.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certificate 10-7.pdf11 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certificate 11-07.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 11-7.pdf11 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22 -10-7.pdf11 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH C.pdf10 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg certificate.pdf10 Jul 2023
Declaration in FORM BFile: FORM B.pdf29 Jun 2023
Declaration in FORM BFile: FORM B NEW.pdf29 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf29 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf29 Jun 2023
Proforma of Allotment letterFile: ALLOTMENT L.pdf29 Jun 2023
Proforma of Agreement for saleFile: model form of agreement jv BLANK.pdf29 Jun 2023
Details of encumbrances concerned to FinanceFile: ENCU.pdf31 Jan 2023
Details of encumbrances concerned to LegalFile: ENCU.pdf31 Jan 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf31 Jan 2023
CERSAI detailsFile: DEC CERSAI.PDF31 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DIS OF INTEREST.PDF31 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK.pdf31 Jan 2023
Deviation Report with respect to Allotment letterFile: DEC DEVI -ALLOTMENT.PDF31 Jan 2023
Deviation Report with respect to model copy of AgreementFile: DEC DEVI -AGREEMENT.PDF31 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA FORM 5 CERTIFICATE.pdf27 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH CERTIFICATE.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE CERTIFICATE MARCH 2020.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE JUN 2020.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE SEP 2020.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE DEC 2020.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE CERTIFICATE MARCH 2021.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD .pdf14 Aug 2021
Building plan approvalFile: PLAN.pdf17 Jan 2020
Layout approvalFile: LAYOUT.pdf17 Jan 2020
PAN CardFile: PAN.pdf17 Jan 2020
Copy of the legal title reportFile: SEARCH REPORT.pdf17 Jan 2020
Details of encumbrancesFile: NON ENCUMBRANCE.pdf17 Jan 2020
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf17 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf17 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: N A ORDER.pdf17 Jan 2020
Declaration in FORM BFile: FORM B K D MORE.pdf17 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT.pdf17 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT 2.pdf17 Jan 2020
Proforma of Allotment letterFile: ATS.pdf17 Jan 2020
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf17 Jan 2020
OtherFile: P A.pdf17 Jan 2020
OtherFile: DA.pdf17 Jan 2020

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 26 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep OM SAI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KARANDWADI1,100+ in Satara

2 kmOM SAI RESIDENCYCompleted 15Lapsed / revoked 21Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: KAUSTUBH DILIP MORE

KAUSTUBH DILIP MORE has 1 registration on MahaRERA, including OM SAI RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that OM SAI RESIDENCY shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OM SAI RESIDENCY is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM SAI RESIDENCY?

The registered promoter entity is KAUSTUBH DILIP MORE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM SAI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OM SAI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in OM SAI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM SAI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM SAI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.