Home / Browse projects / Pune, Maharashtra / Olympiadorous Phase I
Olympiadorous Phase I
RG-MH-83156 · RERA P52100018732 · Last updated on MahaRERA portal: 16 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 38 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Olympiadorous Phase I is a Residential / Group Housing project by Neel Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100018732 on 29 Nov 2018. Possession is promised by 28 Feb 2027. The completion date has moved by 38 months from the original filing. 2 of the 7 units on this registration are recorded sold or booked, and 40 of 44 construction stages are filed complete.
At a glance
Project
- NameOlympiadorous Phase I
- TypeResidential / Group Housing
- Location
- AT VILLAGE KHANDALA
- TALUKA MAVAL
- Lonavala (M Cl)
- Mawal
- Pune
- 410301
- Pincode410301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100018732
- ReraGenie IDRG-MH-83156
Builder
- NameNeel Buildcon
- Entity typePartnership
- GSTIN27AALFN0195L1ZT
- PartnersVilas Madanlal Kothari, Amit Sanjay Potdar, Sanjay Moreshwar Potdar, Sanjay Sampatlal Parakh, Mahesh Pandurang Vaidya, Mandar Mahesh Vaidya, Neel Vilas Kothari
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Nov 2018
- Promised completion28 Feb 2027
- Revised completionRevised to 28 Feb 2027 (originally 30 Dec 2023)
- Buildings4 building records
- Documents filed143 files
Current status
Figures as on 16 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A TYPE | NA | 4 | 2 | 2 | 0 | 2 |
| B TYPE | NA | 5 | 2 | 2 | 0 | 2 |
| C TYPE | NA | 4 | 2 | 2 | 0 | 2 |
| D TYPE | NA | 5 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
A TYPE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B TYPE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C TYPE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D TYPE91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed7
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A TYPE | 2 | 0 | 2 |
| B TYPE | 0 | 2 | 2 |
| C TYPE | 0 | 2 | 2 |
| D TYPE | 0 | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 4.25 cr | Rs 4.20 cr |
| B TYPE | NA | Rs 1.59 cr | Rs 1.49 cr |
| C TYPE | NA | Rs 1.56 cr | Rs 1.56 cr |
| A TYPE | NA | Rs 1.56 cr | Rs 1.56 cr |
| D TYPE | NA | Rs 78.62 lakh | Rs 73.62 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARAKH ASSOCIATES |
| Engineer | Vinod Shastri Shivram Shastri |
| Engineer | Swaraj Gangaram Mhatre |
| Chartered Accountant | Krishna R Moondra and Associates |
| Chartered Accountant | Satyendra & Associates |
| Chartered Accountant | Dhawan & Co |
| Partner | Role in project |
|---|---|
| Neel Buildcon | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo complete the pending finishing work of the project
Reason as filed by the promoter1. Project is 80% Complete 2. The Project has received Part OC and uploaded in other Tab 1 3. Consent of Allotees uploaded uploaded for extension 4. The Revised Form B is uploaded in Other tab No. 2 and also in the main Application 5. PERT Chart is uploaded in Other Tab No. 3 and also in Other Technical Tab of the Main Application 6. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 4 6. QPR till dates are updated.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Nov 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Nov 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 28 Feb 2027
Documents filed143
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2018-2019)File: Form-2A-2019.pdf | 16 Jul 2026 |
| Form 2A (FY 2019-2020)File: Form-2A-2020.pdf | 16 Jul 2026 |
| Form 2A (FY 2020-2021)File: Form-2A-2022.pdf | 16 Jul 2026 |
| Form 2A (FY 2021-2022)File: Form-2A-2022.pdf | 16 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form-2A-2026.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Mar-2026.pdf | 14 Jul 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-March-2026.pdf | 14 Jul 2026 |
| Withdrawal Update Form 3File: Form-3-Phase-I-Olympiadorous-March-2026.pdf | 14 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form-2A-Cert-Phase-I-Mar-2023.pdf | 14 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form-2A-Cert-Phase-I-March-2024.pdf | 14 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form-2A-Phase-2-March-2025.pdf | 14 Jul 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Mar-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Mar-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-June-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Sept-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Dec-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form-1-Arch-Cert-Phase-1-Mar-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-March-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-March-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-June-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-Sept-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-Dec-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form-2-Eng-Cert-Phase-I-March-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-Phase-I-Olympiadorous-March-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-Phase-I-Olympiadorous-March-2026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-Olympia-Phase-I-June-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-RERA-Phase-I-Sep-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-Olympia-Phase-I-Dec-2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form-3-Phase-I-Olympiadorous-March-2026.pdf | 24 Apr 2026 |
| Form 1File: Form-1-Phase-I-Olympia-June-2023.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Phase-I-June-2023.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-June-2023.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory-Phase-I-June-2023.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Phase-I-Sept-2023.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Phase-I-Sept-2023.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-Sept-2023.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold-Phase-I-Sept-23.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Arch-Cert-Phase-I-March-2024.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Eng-Cert-Phase-I-March-2024.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-March-2024.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold-Unsold-Phase-I-March-2024.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Arch-Cert-Phase-1-June-2024.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Eng-Cert-Phase-I-June-2024.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-June-2024.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Decl-Sold-Unsold-Phase-I-June-2024.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Arch-Cert-Phase-I-Sept-2024.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Eng-Cert-Phase-I-Sept-2024.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-Sept-2024.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold-Unsold-Phase-I-Sept-2024.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Arch-Cert-Phase-I-Dec-2024.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Eng-Cert-Phase-1-Dec-2024.pdf | 4 Mar 2026 |
| Form 3File: Form-3-RERA-Phase-I-Dec-2024.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Discl-Sold-Unsold-Phase-I-Dec-2024.pdf | 4 Mar 2026 |
| Form 1File: Form-1-Arch-Cert-Phase-I-March-2025.pdf | 4 Mar 2026 |
| Form 2File: Form-2-Eng-Cert-Phase-I-March-2025.pdf | 4 Mar 2026 |
| Form 3File: Form-3-Phase-I-March-2025.pdf | 4 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Discl-Sold-Unsold-Phase-1-March-2025.pdf | 4 Mar 2026 |
| Other - TechnicalFile: pert chart final (8).pdf | 18 Apr 2025 |
| Declaration in FORM BFile: Olyampiodorus Phase I Revised Form B.pdf | 17 Apr 2025 |
| Certificates of CA (Form 3)File: Olyampiodorus Ph 1 FORM 3 - DEC 2024 PHASE I.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Olympioudouroud Sold Unsold Dec 2024.pdf | 17 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Olyampiodorus Phase I Form 2A 2022-23.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Olyampiadorus FORM1 - ARCHITECT CERTIFICATE Ph I Dec 24.pdf | 12 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Olyampiodorus Ph 1 FORM 1 - ARCHITECT CERTIFICATE Mar 25.pdf | 12 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Olyampiodrous FORM 2 - ENG CER - PHASE 1- DEC 2024 (1).pdf | 12 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Olyampiodrus FORM 2 - ENG CERTIFICATE - PHASE I Mar 2025.pdf | 12 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Phase-I-2023-24.pdf | 5 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch Cert-Phase-1-June-2024.pdf | 13 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certifiaccte - Phase I.pdf | 13 Dec 2024 |
| Certificates of CA (Form 3)File: Form-3-Phase-I-June-2024.pdf | 13 Dec 2024 |
| Certificates of CA (Form 3)File: Form-3-Phase-I-Sept-2024.pdf | 13 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng Cert-Phase-I-June-2024.pdf | 13 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certifiacte Phase I.pdf | 13 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Decl-Sold Unsold-Phase-I-June-2024.pdf | 13 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Phase I.pdf | 13 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch-Cert-Phase-I-March-2024.pdf | 13 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Eng-Cert-Phase-I-March-2024.pdf | 13 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Cert-Phase-I-March-2024.pdf | 13 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold-Phase-I-March-2024.pdf | 13 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Arch Cert-Phase-1-Dec-2023.pdf | 19 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 143 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Olympiadorous Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TALUKA MAVAL13,700+ in Pune
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
SAI SATYAM MEADOWS
Shree Ganesh Infrastructure
The Beverly Hills
GG Developers
Godrej Ivara
Manjari Housing Projects LLP
CANARY FARMS
CANARY FARMS
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
Builder: Neel Buildcon
Neel Buildcon has 2 registrations on MahaRERA, including Olympiadorous Phase I and Olympiodoros Phase - II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Olympiadorous Phase I is delayed beyond 28 Feb 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Olympiadorous Phase I?
The registered promoter entity is Neel Buildcon, a partnership as per the filing. Its GSTIN 27AALFN0195L1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Olympiadorous Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Olympiadorous Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Olympiadorous Phase I?
The professionals named in the filing: Architect: PARAKH ASSOCIATES; Engineer: Vinod Shastri Shivram Shastri; Engineer: Swaraj Gangaram Mhatre; Chartered Accountant: Krishna R Moondra and Associates; Chartered Accountant: Satyendra & Associates; Chartered Accountant: Dhawan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Olympiadorous Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback