Registration approved No litigation declared Residential/Group Housing project

NVG RAKSHAK

By AT HOMES ENTERPRISES

RG-KA-77188 · RERA PRM/KA/RERA/1251/472/PR/091024/007138 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 95%
162 of 390Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 147 documents Report an error

NVG RAKSHAK is a Residential/Group Housing project by AT HOMES ENTERPRISES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/091024/007138 on 9 Oct 2024. Possession is promised by 31 Dec 2029. 228 of the 390 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameNVG RAKSHAK
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 562149
  • Pincode562149
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/091024/007138
  • ReraGenie IDRG-KA-77188

Builder

  • NameAT HOMES ENTERPRISES
  • Entity typePartnership Firm
  • GSTIN29ACAFA1039R1Z4
  • Authorized SignatoryN VENKATE GOWDA

Key dates

this monthRegisteredOct 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Oct 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings5 building records
  • Documents filed147 files

Current status

58%228 of 390 units booked
14.3%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NVG RAKSHAK TOWER-1---52052
NVG RAKSHAK TOWER-2---52052
NVG RAKSHAK TOWER-3---52052
NVG RAKSHAK TOWER-4---52052
NVG RAKSHAK TOWER-5---1820182

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 95%.

Building: 20% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work95%
Foundation footing work70%
Upto Plinth Level65%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)15%
Retaining wall (All types)0%
RCC or MS Framed structure65%
Masonry Construction2%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,117 sq m
Named landowners1
LandownerVillageDistrict
AT HOMES ENTERPRISES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 245.46 cr
Cost incurredRs 35.18 cr
Spent of the estimate14.33%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 180.46 crRs 34.13 cr
On-site expenditure-Consultants FeesRs 40.00 cr-
On-site expenditure-Salaries of workersRs 10.00 crRs 65.23 lakh
On-site expenditure-Site OverheadRs 10.00 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 cr-
Payment of taxes-Rs 39.95 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYUKTI (G BHANUMATHY)
EngineerINDIGO CONSULTANTS (ARUN KUMAR S R)
Chartered AccountantRAJANI M

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed147

As listed on the registration, under the names the promoter filed them with; the newest 80 of 147 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/091024/007138 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate - NVG Rakshak - QU Sep 2026_.pdf12 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate AT Homes QU Sep 2026.pdf12 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate AT Homes QU Sep 2026.pdf12 Oct 2026
Q2 2026-27 Water supply and sewage board12 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)12 Oct 2026
Q2 2026-27 KPTCL- BESCOM12 Oct 2026
Q2 2026-27 Fire and Safety12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate - June 26 - NVG.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 - June 26 - NVG.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 -June 26 - NVG.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA March 26 NVG.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect March 26 - NVG.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer March 26 - NVG.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Dec 25.pdf12 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Dec 25.pdf12 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Dec 25.pdf12 Feb 2026
Q3 2025-26 Water supply and sewage board12 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)12 Feb 2026
Q3 2025-26 KPTCL- BESCOM12 Feb 2026
Q3 2025-26 Fire and Safety12 Feb 2026
Q3 2025-26 Airport Authority of India12 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department12 Feb 2026
BS with Schedules FY 2022-23File: 1 BS with Schedules FY 2022-23.pdf17 Sep 2024
BS with Schedules FY 2023-24File: 1 BS with Schedules FY 2023-24.pdf17 Sep 2024
P&L FY 2022-23File: 1 P&L FY 2022-23.pdf17 Sep 2024
P&L FY 2023-24File: 1 P&L FY 2023-24.pdf17 Sep 2024
KhathaFile: 2 Khatha.pdf17 Sep 2024
Airport Noc_compressedFile: Airport Noc_compressed.pdf28 Aug 2024
Allotment letter plot no R_9_BFile: Allotment letter plot no R_9_B.pdf28 Aug 2024
area sketch drawing single layout planFile: area sketch drawing single layout plan.jpeg28 Aug 2024
C CFile: C C.pdf28 Aug 2024
Commencement certificateFile: Commencement certificate.pdf28 Aug 2024
DEMAND NOTE building permitFile: DEMAND NOTE building permit.pdf28 Aug 2024
ECFile: EC.pdf28 Aug 2024
Environmental clearance_compressed (1)File: Environmental clearance_compressed (1).pdf28 Aug 2024
Fire and Emergency Services Noc and fee receipt (3)File: Fire and Emergency Services Noc and fee receipt (3).pdf28 Aug 2024
IAF NOC G2 (2)File: IAF NOC G2 (2).pdf28 Aug 2024
KIADB - Possession certificate (2)File: KIADB - Possession certificate (2).jpeg28 Aug 2024
KIADB - Possession certificateFile: KIADB - Possession certificate.jpeg28 Aug 2024
KIADB Fee Receipt (2)File: KIADB Fee Receipt (2).jpeg28 Aug 2024
KSPCBFile: KSPCB.pdf28 Aug 2024
lease cum sale agreement (2)_compressedFile: lease cum sale agreement (2)_compressed.pdf28 Aug 2024
Legal opinion _compressedFile: Legal opinion _compressed.pdf28 Aug 2024
Mutation DeclarationFile: Mutation Declaration.pdf28 Aug 2024
Possession certificateFile: Possession certificate.pdf28 Aug 2024
RTC DeclarationFile: RTC Declaration.pdf28 Aug 2024
Water NOCFile: Water NOC.pdf28 Aug 2024
At homes Rera AcFile: At homes Rera Ac.pdf28 Aug 2024
Basement & Ground Floor PlanFile: Basement & Ground Floor Plan.pdf28 Aug 2024
Commence Certificate DeclarationFile: Commence Certificate Declaration.pdf28 Aug 2024
DeclarationFile: Declaration.pdf28 Aug 2024
Homes EnterprisesFile: Homes Enterprises.pdf28 Aug 2024
INDIA NON JUDICIALFile: INDIA NON JUDICIAL.pdf28 Aug 2024
Industry_ProfileFile: Industry_Profile.pdf28 Aug 2024
KIADB CDP Plam DemarcatedFile: KIADB CDP Plam Demarcated.pdf28 Aug 2024
Master PlanFile: Master Plan.jpg28 Aug 2024
Ms AT HOMES ENTERPRISES (2)File: Ms AT HOMES ENTERPRISES (2).pdf28 Aug 2024
Ms AT HOMES ENTERPRISESFile: Ms AT HOMES ENTERPRISES.pdf28 Aug 2024
paid receiptFile: paid receipt.jpeg28 Aug 2024
PAYMENT RECEIPTFile: PAYMENT RECEIPT.pdf28 Aug 2024
receitpFile: receitp.jpeg28 Aug 2024
Site PlanFile: Site Plan.pdf28 Aug 2024
Terrace floor plan Section & ElevationFile: Terrace floor plan Section & Elevation.pdf28 Aug 2024
Typical Floor PlanFile: Typical Floor Plan.pdf28 Aug 2024
Village MapFile: Village Map.jpeg28 Aug 2024
State level single window clearance committee- order_compressedFile: State level single window clearance committee- order_compressed.pdf28 Aug 2024
HomesFile: Homes.pdf28 Aug 2024
KIADB CDP Plam DemarcatedFile: KIADB CDP Plam Demarcated.pdf28 Aug 2024

How this compares with Bengaluru Urban

58%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep NVG RAKSHAK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNVG RAKSHAKOther 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: AT HOMES ENTERPRISES

AT HOMES ENTERPRISES has 1 registration on RERA Karnataka, including NVG RAKSHAK. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if NVG RAKSHAK is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NVG RAKSHAK?

The registered promoter entity is AT HOMES ENTERPRISES, a partnership firm as per the filing. Its GSTIN 29ACAFA1039R1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NVG RAKSHAK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NVG RAKSHAK?

The professionals named in the filing: Architect: YUKTI (G BHANUMATHY); Engineer: INDIGO CONSULTANTS (ARUN KUMAR S R); Chartered Accountant: RAJANI M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NVG RAKSHAK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NVG RAKSHAK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NVG RAKSHAK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.