ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / NIVRUTTI HEIGHTS

Completed No litigation declared Residential / Group Housing project

NIVRUTTI HEIGHTS

By KALKI DEVELOPERS

RG-MH-12362 · RERA P52100011757 · Last updated on MahaRERA portal: 12 Oct 2023

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2020Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
6Complaints at MahaRERAon this registration
Jump to the 25 documents Report an error

NIVRUTTI HEIGHTS is a Residential / Group Housing project by KALKI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100011757 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2020. The completion date has moved by 18 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameNIVRUTTI HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011757
  • ReraGenie IDRG-MH-12362

Builder

  • NameKALKI DEVELOPERS
  • Entity typePartnership
  • PartnerNIRANJAN DATTATRAY DASHPUTE
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toSep 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Sep 2020
  • Revised completionRevised to 30 Sep 2020 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed25 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIVRUTTI HEIGHTSNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

NIVRUTTI HEIGHTS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
RAJKUMAR NIVRUTTI SASTEPimpri Chinchawad (M Corp.)Pune
VIJAY NIVRUTTI SASTEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI3536.58
Proposed, not sanctioned2,542 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS NO 183,SHIV ANGAN SOCIETY,PIMPLE SAUDAGHAR,PUNE-411027

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHENDRA THAKUR AND ASSOCIATES
PartnerRole in project
KALKI DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002354Mar 2019 → Mar 2020

Reason as filed by the promoterLAND OWNNER ISSUE.

EXT52100000186Mar 2019 → Mar 2020

Reason as filed by the promotersanction for TDR yet not approved

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000011519Niranjan DashputeRajKumar Nivrutti Saste, Sanjay Nivrutti Saste, Vijay Nivritti Saste17/05/2018
CC005000000064651Vijay Arvind DabhadeKalki Developers - Authorized Person - Mr. Dattatray Ramdas Dashpute11/10/2020
CC005000000022813Rakeshkumar Rampyare Jaiswar and Pushpa Rakeshkumar JaiswarM/s. Kalki Developers & Ors.01/04/2019
CC005000000054186NAVNATH ARVIND DABHADEM/S. KALKI DEVELOPERS26/03/2020
CC005000000085327Rajkumar Nivrutti SasteM/s Kalki Developers18/03/2021
CC12600772Vandana Sanjay SulKALKI DEVELOPERS10/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Oct 2023

Documents filed25

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: KD - Final Completion Certification.pdf12 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for26 Jun 2023
Status of ConveyanceFile: Adobe Scan 28 Apr 2022 (2)_compressed.pdf28 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 25 Sep 2021-compressed.pdf25 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 25 Sep 2021 (1).pdf25 Sep 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Formation Certificate (1).pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 (KALKI DEVELOPERS).pdf10 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: New Doc 2018-04-06 (1).pdf28 Jun 2018
Building plan approvalFile: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Building plan approvalFile: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Building plan approvalFile: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Copy of the legal title reportFile: New Doc 2017-07-31 (13)-ilovepdf-compressed (1).pdf31 Jul 2017
Copy of the legal title reportFile: New Doc 2017-07-31 (14)-ilovepdf-compressed.pdf31 Jul 2017
Details of encumbrancesFile: New Doc 2017-07-31 (1)_1.pdf31 Jul 2017
Building Plan Approval (IOD)File: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Building Plan Approval (IOD)File: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Building Plan Approval (IOD)File: New Doc 2017-07-31 (15)_1.pdf31 Jul 2017
Declaration in FORM BFile: New Doc 2017-07-31 (3).pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New Doc 2017-07-31 (1) (1).pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2017-07-31-ilovepdf-compressed.pdf31 Jul 2017
Certificates of CA (Form 3)File: New Doc 2017-07-31 (16).pdf31 Jul 2017
Layout approvalFile: New Doc 2017-07-31 (15)_1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: New Doc 2017-07-31 (15)_1.pdf30 Jul 2017
Proforma of Allotment letterFile: Rera.pdf29 Jul 2017
Proforma of Allotment letterFile: allotment letter.pdf29 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NIVRUTTI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune

2 kmNIVRUTTI HEIGHTSCompleted 65Lapsed / revoked 38Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 187 registered projects within 2 km.

Builder: KALKI DEVELOPERS

KALKI DEVELOPERS has 3 registrations on MahaRERA, including NIVRUTTI HEIGHTS and Nanekar Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if NIVRUTTI HEIGHTS is delayed beyond 30 Sep 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIVRUTTI HEIGHTS?

The registered promoter entity is KALKI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIVRUTTI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NIVRUTTI HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NIVRUTTI HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIVRUTTI HEIGHTS?

The professionals named in the filing: Architect: MAHENDRA THAKUR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIVRUTTI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIVRUTTI HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIVRUTTI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.