Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 54 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 54 months from the original
29 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 90%
5Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Nisarga Residency is a Residential / Group Housing project by Namoh Nature Group Builders & Developers in Ratnagiri, Maharashtra, registered with MahaRERA as P52800014956 on 15 Jan 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 54 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameNisarga Residency
  • TypeResidential / Group Housing
  • Location
    • Khatatewadi Road
    • Kherdi
    • Kherdi (CT)
    • Chiplun
    • Ratnagiri
    • 415604
  • Pincode415604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800014956
  • ReraGenie IDRG-MH-41710

Builder

  • NameNamoh Nature Group Builders & Developers
  • Entity typePartnership
  • PartnerSandeep Yashwant Kadam

Key dates

this monthRegisteredJan 2018First promiseJun 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jan 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 27 Jun 2022)
  • Buildings4 building records
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nisarga Residency Wing - ANA60000
Nisarga Residency Wing - BNA60000
Nisarga Residency Wing - CNA60000
Nisarga Residency Wing - DNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 21 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

Nisarga Residency Wing - A51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Nisarga Residency Wing - B74%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Nisarga Residency Wing - C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Nisarga Residency Wing - D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22
BuildingClosed/CoveredTotal
Nisarga Residency Wing - A88
Nisarga Residency Wing - B44
Nisarga Residency Wing - C22
Nisarga Residency Wing - D88

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,928 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Santosh Anant DabholkarKherdi (CT)Ratnagiri
Sandeep Anant DabholkarKherdi (CT)Ratnagiri
Rajaram Krushnaji DabholkarKherdi (CT)Ratnagiri
Manohar Balkrishna DabholkarKherdi (CT)Ratnagiri
Dattaram Balkrishna DabholkarKherdi (CT)Ratnagiri
Vilas Balkrishna DabholkarKherdi (CT)Ratnagiri
Sagar Subhash DabholkarKherdi (CT)Ratnagiri
Sanket Subhash DabholkarKherdi (CT)Ratnagiri
Suvarna Subhash DabholkarKherdi (CT)Ratnagiri

Approvals and building plan

Permissible FSI4266.0
Proposed, not sanctioned4,266 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchshivsagar Kaviltali Chiplun 415605

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRavindra Patil
PartnerRole in project
Namoh Nature Group Builders & Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800013705Jun 2022 → Dec 2026

Reason as filed by the promoterDue to Health issue and financial problem work was slow

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000197003Viddesh Vijay ShindePravin Shinde13/05/2021
CC006000000251727Viddesh ShindePravin Shinde13/09/2022
CC12503150Vilas Nathu BagulNamoh Nature Group Builders & Developers07/09/2025
CC12503152Anil Nathu BagulNamoh Nature Group Builders & Developers07/09/2025
CC12503153sudhanshu dwarkanath vanageNamoh Nature Group Builders & Developers07/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Mar 2023.pdf21 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Dec 2023.pdf21 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Mar 2023.pdf21 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Dec 2023.pdf21 Feb 2024
Certificates of CA (Form 3)File: CA Certificate March 2023.pdf21 Feb 2024
Certificates of CA (Form 3)File: CA Certificate Dec 2023.pdf21 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf21 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 1.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 2.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 1.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 2.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate Form 2A.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate Form 2A.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Form 2A.pdf24 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold 1.pdf24 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold 4.pdf24 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200258582316_For_Asset_Based_Search_24_01_2023_23_44_30_833.pdf24 Jan 2023
Certificates of CA (Form 3)File: Form_3_March_2022_Namoh_Nature_Group.pdf24 Jan 2023
Certificates of CA (Form 3)File: Form_3_September_2022_Namoh_Nature_Group.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Namoh Nature_19-20.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Namo nature 20-21.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Namoh Nature 21-22.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf16 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf16 Oct 2018
Certificates of CA (Form 3)File: CA Certificate.pdf16 Oct 2018
Certificates of CA (Form 5)File: Namo Nature_Form 5.pdf2 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 May 2018
Certificates of CA (Form 3)File: CA Certificate.pdf10 May 2018
Layout approvalFile: Blueprint 2.pdf7 Jan 2018
Building plan approvalFile: Blueprint 1.pdf7 Jan 2018
Building plan approvalFile: Blueprint 2.pdf7 Jan 2018
PAN CardFile: PAN Card.pdf7 Jan 2018
Copy of the legal title reportFile: Search Report 36 (20).pdf7 Jan 2018
Copy of the legal title reportFile: Search Report 36 (21).pdf7 Jan 2018
Details of encumbrancesFile: Encumbrance Certificate.pdf7 Jan 2018
Copy of Layout Approval (in case of layout)File: Blueprint 2.pdf7 Jan 2018
Building Plan Approval (IOD)File: Blueprint 1.pdf7 Jan 2018
Building Plan Approval (IOD)File: Blueprint 2.pdf7 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf7 Jan 2018
Declaration in FORM BFile: Form B (Promotor).pdf7 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf7 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf7 Jan 2018
Certificates of CA (Form 3)File: CA Certificate.pdf7 Jan 2018
Proforma of Allotment letterFile: Proforma Sale Agreement.pdf7 Jan 2018
OtherFile: POA 36 (20) 1.pdf7 Jan 2018
OtherFile: POA 36 (20).pdf7 Jan 2018
OtherFile: POA 36 (21).pdf7 Jan 2018

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one moved by 54 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep Nisarga Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kherdi1,100+ in Ratnagiri

2 kmNisarga ResidencyCompleted 13Lapsed / revoked 11Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: Namoh Nature Group Builders & Developers

Namoh Nature Group Builders & Developers has 1 registration on MahaRERA, including Nisarga Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if Nisarga Residency is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nisarga Residency?

The registered promoter entity is Namoh Nature Group Builders & Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nisarga Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nisarga Residency?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nisarga Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nisarga Residency?

The professionals named in the filing: Architect: Ravindra Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nisarga Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nisarga Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nisarga Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.